"Automatic" Sprinkler Corp. of America v. Coley & Petersen, Inc.

250 S.E.2d 765, 219 Va. 781, 1979 Va. LEXIS 170
CourtSupreme Court of Virginia
DecidedJanuary 12, 1979
DocketRecord 770728
StatusPublished
Cited by40 cases

This text of 250 S.E.2d 765 ("Automatic" Sprinkler Corp. of America v. Coley & Petersen, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
"Automatic" Sprinkler Corp. of America v. Coley & Petersen, Inc., 250 S.E.2d 765, 219 Va. 781, 1979 Va. LEXIS 170 (Va. 1979).

Opinion

COMPTON, J.,

delivered the opinion of the Court.

This appeal arises from a contract to construct a public facility. Following an incident which resulted in damage to portions of the structure, two subcontractors sued a third subcontractor for recovery of costs and expenses incurred during repair of the damage. Upon review, we consider whether the plaintiffs below had standing to sue, whether contractual waiver provisions barred the plaintiffs’ actions, and whether certain items of damage were properly admitted in evidence.

In 1968, the City of Roanoke entered into a lump sum contract in the amount of $11 million with Nello L. Teer Company, the general contractor, for construction of the Roanoke Civic Center, consisting of an Auditorium, Coliseum and Exhibit Hall. Thereafter, Teer entered into separate written subcontracts with plaintiff-appellee Coley & Petersen, Inc., plaintiff-appellee Clear-Bullock Electrical Company, Inc. and defendant-appellant “Automatic” Sprinkler Corporation of America for installation of the mechanical work (heating, air-conditioning, plumbing), electrical work and the automatic sprinkler system respectively. Several years later, and before final completion of the project, a cast iron pipe installed by the defendant broke causing water damage to some of the mechanical and electrical equipment in a basement below the Auditorium. The plaintiffs repaired the damage and when the defendant refused their demands for reimbursement of the amounts of their claimed losses, these two actions in tort, filed separately but later consolidated, followed in 1972. Coley & Petersen initially sought to recover approximately $15,000 while Clear-Bullock’s suit was for almost $36,000.

Evidentiary hearings by the trial court sitting without a jury were held in 1976 upon defendant’s several special pleas and motions. At these hearings, the court considered the questions of *784 standing and waiver, ruling adversely to defendant. Later in 1976, a four-day jury trial was held on the merits at which responsibility for the damage was fixed upon the defendant and damages were assessed in favor of the plaintiffs. Coley & Petersen was awarded $8,934.47 and Clear-Bullock recovered $24,770.59. Subsequently, the trial court overruled defendant’s post-trial motions and we granted defendant a writ of error to the February 1977 judgment orders confirming the verdicts.

We will first examine the questions of standing to sue and waiver. All the evidence pertaining to these issues was taken at the pre-trial hearings.

The record reveals that immediately following the March 1968 execution of the prime contract between the City and Teer, the general contractor entered into the three subcontracts, containing identical basic provisions, with the parties to this action. The work proceeded for a period of about four years. Final completion and the City’s final acceptance of the project occurred during February of 1972.

In early 1971, in part because the City had “booked at least one and maybe more activities” for the Civic Center in 1971 which would have been “extremely costly” to cancel, the City and Teer agreed that the City would be permitted to use certain parts of the building provided the architect made an inspection and issued a certificate of substantial completion. Accordingly on March 24, 1971, such a certificate was issued and March 25, 1971 was established as the date of substantial completion. The certificate further provided that the City had the responsibility to purchase and maintain insurance to protect itself, Teer, the public, and “all other parties from claims or losses which may arise out of or result from [the City’s] occupancy and use” of the completed portions of the project. On March 19,1971, the City had obtained an insurance policy providing coverage for the Civic Center against the peril of fire, with extended coverage. Effective March 25, 1971, the builder’s risk insurance policy for the project obtained by Teer was cancelled. Teer then obtained, as required by the certificate of substantial completion, an “Insurance Installation Floater Policy” providing coverage for losses which might arise from its operations in completing the work. According to the testimony and the exhibits, the Civic Center “opened” on March 27,1971 and at least six more events were held there prior to the date the damage in issue happened.

*785 On May 18, 1971, a break occurred in the flange of the six-inch sprinkler main at a point just inside the interior wall of the basement of the Auditorium. The basement area was flooded and a substantial amount of equipment and other installed work of the plaintiffs in the area was heavily damaged. At the time, although plaintiffs had completed substantially all their work, neither had fully performed its contract. Each had remaining responsibilities to Teer under the subcontracts. The defendant had finished its work of installing the sprinkler system prior to March 25, 1971.

The day after the damage occurred, Teer notified defendant and its liability insurance carrier that “Automatic” Sprinkler was required under its subcontract to repair any damage it had caused as a result of its work. Defendant refused to authorize the several subcontractors to proceed with the repairs and on May 28, 1971, Teer issued written notice to the plaintiffs that under their contracts they had the duties to protect their work from damage until final acceptance, to make any and all repairs necessary and to prepare all work acceptable to the architect and to the owner. Article 20 of the subcontracts provided:

The Subcontractor will be responsible for the care and protection of his work until the final inspection and acceptance by the Architect and/or Owner. The Contractor assumes no responsibility for the collection of any charges claimed by this Subcontractor against another Subcontractor and/or Supplier.
Any damage inflicted by another Subcontractor shall be repaired by this Subcontractor and be billed on a weekly basis to the Subcontractor responsible for the damage. The party responsible for the damage must be notified, in writing, before repairs or corrective work is done.

Pursuant to that provision, Teer advised both plaintiffs in the May 28 letter that

if your work is damaged by others or by another subcontractor, the burden is upon you *786 to collect the cost of such damages from him. You will note that work should not start until you have given him proper written notice.

The letter concluded with the request that plaintiffs “act immediately,” as outlined in the letter, because “expedient completion of the work is an essential element of [Teer’s] contract with the owner.” The plaintiffs then proceeded to repair the damage, after giving written notice to defendant. Subsequently, defendant failed to reimburse plaintiffs for any of the expenses incurred.

The first question is whether the trial court was correct in ruling that the plaintiffs could bring these tort actions against the defendant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Joseph John Melick v. Commonwealth of Virginia
816 S.E.2d 599 (Court of Appeals of Virginia, 2018)
King David Manning, Jr. v. Commonwealth of Virginia
Court of Appeals of Virginia, 2017
Deon Christopher Cobb v. Commonwealth of Virginia
Court of Appeals of Virginia, 2013
Ernesto Wilfredo Solano Godoy v. Commonwealth of Virginia
742 S.E.2d 407 (Court of Appeals of Virginia, 2013)
Edwin Miller v. Commonwealth of Virginia
Court of Appeals of Virginia, 2011
Trang Chau v. Commonwealth of Virginia
Court of Appeals of Virginia, 2011
Cooper v. Commonwealth
680 S.E.2d 361 (Court of Appeals of Virginia, 2009)
Wesley Eugene Baker, II v. Commonwealth of Virginia
Court of Appeals of Virginia, 2009
Donald H. Roper v. Commonwealth of Virginia
Court of Appeals of Virginia, 2007
McDowell v. Com.
641 S.E.2d 507 (Supreme Court of Virginia, 2007)
1924 Leonard Road, L.L.C. v. Van Roekel
636 S.E.2d 378 (Supreme Court of Virginia, 2006)
Nicky Neofotis v. Commonwealth
Court of Appeals of Virginia, 2006
Brenda S. Neofotis v. Commonwealth
Court of Appeals of Virginia, 2006
Stevens v. Commonwealth
603 S.E.2d 642 (Court of Appeals of Virginia, 2004)
Parker v. Commonwealth
587 S.E.2d 749 (Court of Appeals of Virginia, 2003)
Bernice Wilson v. Fairfax County Dept. Social Svc
Court of Appeals of Virginia, 2003
Jones v. Commonwealth
563 S.E.2d 364 (Court of Appeals of Virginia, 2002)
Sylvester Leo Guy v. Commonwealth of Virginia
Court of Appeals of Virginia, 2002
Kevin Dwayne Smith v. Commonwealth of Virginia
Court of Appeals of Virginia, 2000

Cite This Page — Counsel Stack

Bluebook (online)
250 S.E.2d 765, 219 Va. 781, 1979 Va. LEXIS 170, Counsel Stack Legal Research, https://law.counselstack.com/opinion/automatic-sprinkler-corp-of-america-v-coley-petersen-inc-va-1979.