Donaldson v. Sutherland Manufacturing Co.

5 Ohio N.P. (n.s.) 425
CourtOhio Superior Court, Cincinnati
DecidedJanuary 19, 1907
StatusPublished

This text of 5 Ohio N.P. (n.s.) 425 (Donaldson v. Sutherland Manufacturing Co.) is published on Counsel Stack Legal Research, covering Ohio Superior Court, Cincinnati primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Donaldson v. Sutherland Manufacturing Co., 5 Ohio N.P. (n.s.) 425 (Ohio Super. Ct. 1907).

Opinion

Hoffheimer, J.;

Murphy, J., concurs; Hosea, J., dissents — ■ see separate opinion.

Defendant in error, manufacturer of and dealer in gas and electric fixtures, contracted to furnish and install gas and electric fixtures in the house of plaintiff! in error. According to the contract, the combination electric and gas fixtures were to be put up complete, and were to be to the satisfaction of Mr. Donaldson, afnd it was agreed that the job was to be first class [426]*426in every particular, and that everything was to be done in accordance with the rules and regulations of the National Board of Underwriters, and to Mr. Donaldson’s entire satisfaction, “the whole to be $875.”

The fixtures are set out in the schedule, also the individual prices. The agreement was, however, as already stated, to pay a lump sum. It is also conceded that Mr. Donaldson reserved the right to disapprove of any of the fixtures, in which event the same were to be exchanged for others. The fixtures were selected from photographs, and had to be manufactured, with the exception of one. With the exception of two all had been delivered when, without fault of either party and before the house was ready for occupancy, it was destroyed by five. Defendant in error subsequently tendered the remaining fixtures, but they were refused.

Suit was brought on the account for the entire contract price, and a verdict was rendered for the full amount of the contract. A motion for a new trial was overruled and judgment entered up for the full amount of the contract price.

Error is prosecuted to this court, and it is claimed by plaintiff in error that the judgment should have been for plaintiff in error, because under the conceded facts the Sutherland Manufacturing Company could not allege and prove performance; and furthermore that it can not recover as on quantum meruit for the part performed. In other words, it is claimed that the contract entered into between these parties was an entire and indivisible one, and that as the destruction of the premises, including such part of the fixtures as were already delivered, was without fault of either party, it was impossible for the Sutherland Company to perform its contract, and therefore there could be no recovery.

The contract in our judgment was not a present sale of chattels, as claimed by defendant in error. -It could not have been such a contract because all the articles, with the exception perhaps of one, had to be manufactured according to special design and photographs. It was an executory contract to manufacture a complete lot of fixtures, which were to be to the satisfaction of the vendee, and were to be installed as already indicated.

[427]*427The undisputed evidence shows that the contract was entered into in Kentucky and was to be performed in Kentucky. The validity, obligation, and effect of the contract is determinable therefore under the laws of Kentucky. Montana Coal & Coke Company v. The Cincinnati Coal & Coke Company, 69 Ohio State, 351.

The contract being an entire one, under the authorities of that state there could be no recovery either on the contract or on quantum meruit. The latest expression of the supreme court of that state is found in the case of Louisville Foundry & Machine Co. v. Patterson (Kentucky Court of Appeals, 1906, not yet reported). This case, it seems, is decisive, and would bar recovery. It was held that there could be no recovery for the part performance of a contract to install an elevator when the elevator and building were destroyed by fire without fault of either party, although the building of the elevator had so far progressed as to be in running order, and it would require but little more to place the elevator in the condition required by the contract. After pointing out- that the elevator was to be paid for when accepted by the architect, and that it was destroyed before it was completed or accepted, the court goes on to say: '

“It has been ruled in a number of cases that under contracts like the one in this case, where the property has been destroyed before the completion of the contract or the acceptance of the property by the owner, the loss must fall on the contractor.” Citing Lewing v. Ruttles, 97 N. C., 350; Richardson v. Shaw, 1 Mo. App., 234; Tompkins v. Dudley, 25 N. Y., 272.

The principle is laid down in Appleby v. Meyers, L. R., 2 C. P., 651, wherein it was held that where there is an executory contract of such a nature that the parties contemplate the continued existence of a thing, and the thing is destroyed without fault of either party, and performance of the contract is thereby rendered impossible, no recovery can be had on the contract because it has not been performed, nor can there be recovery for the part performance.

The express language in the contract that the fixtures were to be put up complete and that everything was to be done in accordance with the rules and regulations of the National Board [428]*428of Underwriters and to Mr. Donaldson’s entire satisfaction, rendered it manifestly impossible for plaintiff below to prove performance; for he was not able to prove that the job was complete, or that all the fixtures were satisfactory, or that all had been installed in accordance with the rules of the National Board of Underwriters. Had the contract been an Ohio one, this alone would defeat recovery (Ashley v. Henahan, 56 Ohio St., 559). And the Kentucky case already alluded to expresses the same principle.

The additional point that we desire to make, however, is that the contract provides for the payment of a lump sum, and that this is conditioned among other things upon everything being done; the ordinary significance of which language is that all the fixtures ordered were to be installed in accordance with said conditions before anything became due, and that all the fixtures were to be satisfactory.

It was shown at the trial below that the fixtures already supplied were up to Donaldson’s expectation, and that he had expressed satisfaction with such as had been furnished; but this could not affect the nature of the contract or the liability thereunder, for plaintiff in error was not bound to pay the lump sum as agreed upon until the entire contract had been performed according to its terms. Andrews v. Durant, 11 N. Y. Ct. App., 35; Clarkson v. Stephens, 106 U. S., 505; Wright v. Tetlow, 99 Mass., 397.

And although Donaldson expressed approval of the fixtures delivered, such expressions on his part could not be made the basis of any different acceptance than that provided for in the contract. Until the whole job was complete and all the fixtures satisfactory, he had the express right to change his mind as to any or every fixture. Ellis v. Mortimer, 1 Bos. & Pull. N. R., 257.

If the contract in question is an Ohio one, the common law rule as laid down in "Wald’s Pollock on Contracts (1 Amer. Ed., p. 363) would obtain, and the loss would be placed on defendant in error. See also Withrow v. Withrow, 16 Ohio, 238; Lumber Co. v. Purdam, 41 Ohio St., 373. And in other cases where it clearly appears that a contract is entered into with reference [429]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Clarkson v. Stevens
106 U.S. 505 (Supreme Court, 1882)
Tompkins v. . Dudley
25 N.Y. 272 (New York Court of Appeals, 1862)
Dexter v. . Norton
47 N.Y. 62 (New York Court of Appeals, 1871)
State v. . Craige
89 N.C. 475 (Supreme Court of North Carolina, 1883)
Wooten v. . Walters
14 S.E. 734 (Supreme Court of North Carolina, 1892)
Lawing v. . Rintles
2 S.E. 252 (Supreme Court of North Carolina, 1887)
Wright v. Tetlow
99 Mass. 397 (Massachusetts Supreme Judicial Court, 1868)
Wells v. Calnan
107 Mass. 514 (Massachusetts Supreme Judicial Court, 1871)
Young & Conant Manufacturing Co. v. Wakefield
121 Mass. 91 (Massachusetts Supreme Judicial Court, 1876)
Watson v. Kirby & Sons
112 Ala. 436 (Supreme Court of Alabama, 1895)
Richardson v. Shaw
1 Mo. App. 234 (Missouri Court of Appeals, 1876)
Atlantic & Danville Railway Co. v. Delaware Construction Co.
37 S.E. 13 (Supreme Court of Virginia, 1900)
Clark v. Bayley
5 Or. 343 (Oregon Supreme Court, 1874)
Morris v. Wibaux
43 N.E. 837 (Illinois Supreme Court, 1895)
Siegel, Cooper & Co. v. Eaton & Prince Co.
165 Ill. 550 (Illinois Supreme Court, 1896)
Huyett & Smith Manufacturing Co. v. Chicago Edison Co.
47 N.E. 384 (Illinois Supreme Court, 1897)
Fildew v. Besley
3 N.W. 278 (Michigan Supreme Court, 1879)
Nicol v. Fitch
72 N.W. 988 (Michigan Supreme Court, 1897)
Barrett v. Coal Co.
41 S.E. 220 (West Virginia Supreme Court, 1902)
Saunders v. Short
86 F. 225 (Ninth Circuit, 1898)

Cite This Page — Counsel Stack

Bluebook (online)
5 Ohio N.P. (n.s.) 425, Counsel Stack Legal Research, https://law.counselstack.com/opinion/donaldson-v-sutherland-manufacturing-co-ohsuperctcinci-1907.