Service Steel Erectors Co. v. SCE, INC.

573 F. Supp. 177, 1983 U.S. Dist. LEXIS 13966
CourtDistrict Court, W.D. Virginia
DecidedSeptember 9, 1983
DocketCiv. A. 81-0061-C
StatusPublished
Cited by4 cases

This text of 573 F. Supp. 177 (Service Steel Erectors Co. v. SCE, INC.) is published on Counsel Stack Legal Research, covering District Court, W.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Service Steel Erectors Co. v. SCE, INC., 573 F. Supp. 177, 1983 U.S. Dist. LEXIS 13966 (W.D. Va. 1983).

Opinion

MEMORANDUM OPINION

MICHAEL, District Judge.

This diversity action comes before the court on defendants’ summary judgment motion pursuant to Fed.R.Civ.P. 56. The matter has been fully briefed and argued to the court and is now ripe for disposition.

In this action, plaintiff, Service Steel Erectors Company (“Service Steel”), claims damages of $245,270 for alleged breaches of a construction subcontract by SCE, Inc. (“SCE”). SCE was the general contractor for the Moore’s Creek Advanced Water *178 Treatment Plant constructed for the Rivanna Water and Sewer Authority (“Owner”). Other defendants who joined in the summary judgment motion are Federal Insurance Company, the bonding company for the project, and Sullivan, Long & Hagerty, Inc., the parent corporation of SCE. Service Steel subcontracted to install reinforcing steel for the project. The subcontract provided that Service Steel should unload and erect in place the reinforcing steel and wire mesh according to the plans and trade practices. The essence of Service Steel's claims is that it performed extra work for which it is due compensation under the subcontract. Service Steel contends additionally that it suffered consequential damages such as lost profits resulting from SCE’s failure to pay for the extra work.

Service Steel alleges that between May 1979 and September 1980 it was required to refabricate the steel sent from the supplier, Owen Steel, not a party to this action. It states that in many instances the steel was not fabricated properly. Deposition testimony from both the Service Steel superintendent on the project, Michael Jernigan, and the SCE field superintendent, Kenneth Allen, indicates that on a number of occasions Service Steel had to “field bend” steel in order to make it suitable for the project. Service Steel now asserts that this refabrication was extra work not included in the subcontract.

The contract between Service Steel and SCE provides specific requirements for extra work claims. In short, the contract contains two primary requirements:

(1) No extra work is compensable unless authorized by written order of the contractor, SCE.
(2) All claims for extra work must be made in writing within seven days after cost is incurred. All claims must include an itemized cost sheet showing the actual cost of performance of the work. 1

Service Steel does not claim to be unaware of these requirements. Indeed, in deposition testimony both the president of Service Steel, Emory Jernigan, and its project superintendent, Michael Jernigan, indicated that these requirements were standard industry practice. Michael Jernigan admitted that SCE’s Kenneth Allen mentioned the seven day claims limitation to him frequently, reminding Jernigan that after seven days SCE was not responsible for any extra work.

The Supreme Court of Virginia in Atlantic & Danville Ry. v. Delaware Construction Co., 98 Va. 503, 37 S.E. 13, 16 (1900), has endorsed contractual provisions that call for prior agreement as to extras, stating:

An obvious purpose of such a provision is to avoid subsequent disagreement, and prevent just such a controversy as has arisen in this case____ All are aware of the frequency with which it happens in the construction of buildings and other improvements that claims are made for alleged extra work, which give rise to disputes and litigation. Such a provision is a wise, and not an unusual, one in building contracts, and it is held by the authorities to be obligatory upon the parties, and not to be disregarded.

Service Steel nevertheless concedes that it did not comply with either the written approval requirement or the timely claim requirement. Rather, the sole issue for determination is whether SCE waived its contract rights as to both requirements. *179 While admitting that it failed to obtain written approval for extras and failed to make itemized claims for extras, Service Steel asserts that by its conduct SCE waived these provisions. In asserting waiver Service Steel has the burden of establishing “by clear and unmistakable evidence” that SCE waived these contractual requirements. May v. Martin, 205 Va. 397, 137 S.E.2d 860, 865 (1964).

SCE contends that the contract itself expressly defines and limits the circumstances' that will constitute a waiver. Article 51 of the General Conditions provides:

No oral order, objection, claim or notice given by any party to the others shall affect or modify any of the terms or obligations contained in any of the Contract documents, and none of the Contract documents shall be held to be waived or modified by reason of any act whatsoever, other than by a definitely agreed, upon waiver or modification thereof in writing, and no evidence of any other waiver or modification shall be introduced in any proceeding.

This express merger clause was certainly clear and unambiguous. Nor has Service Steel made any claims other than on the contract containing this merger clause such as claims of oral contracts or quasi-contractual recovery. Certainly there is no dispute that the contract was entered into by two commercially sophisticated parties. SCE’s argument that the contract provisions themselves bar any sort of implied waiver is consequently persuasive. The court finds no Virginia authority on this specific point, nor has SCE disclosed such authority, but in Chemical Construction Corp. v. Continental Engineering, Ltd,., 407 F.2d 989 (5th Cir.1969), the court held that such a merger clause permitted a directed verdict against the subcontractor who claimed he was due compensation for extra work in spite of the contract provision requiring express written change orders. The court, of course, may not make a new contract for the parties. Marshall v. Murray Oldsmobile Co., 207 Va. 972, 154 S.E.2d 140, 144 (1967).

Nonetheless, even if the merger clause failed to bar any implied waiver by SCE of the contractual provisions requiring written approval and timely claims for extra work, there appears to be no genuine issue of material fact regarding such an implied waiver. Service Steel argues that waiver may be found if the party performing the extra work did not create the need for the extra work, if the general contractor or owner ordered the extra work and understood that the party performing the work would be paid for it, and if the facts together with the trade practices demonstrate that the type of work would not normally be undertaken without additional compensation.

Service Steel cites three cases for this implied waiver rule that it claims reflects the “well established” Virginia law on implied waiver. The first, Jefferson Hotel Co. v. Brumbaugh, 168 F.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

West v. United States Postal Service
907 F. Supp. 154 (E.D. Virginia, 1995)
McDevitt & Street Co. v. Marriott Corp.
713 F. Supp. 906 (E.D. Virginia, 1989)
United States v. Centex Const. Co., Inc.
638 F. Supp. 411 (W.D. Virginia, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
573 F. Supp. 177, 1983 U.S. Dist. LEXIS 13966, Counsel Stack Legal Research, https://law.counselstack.com/opinion/service-steel-erectors-co-v-sce-inc-vawd-1983.