Chemical Construction Corporation v. Continental Engineering, Ltd., Continental Engineering, Ltd. v. Chemical Construction Corporation

407 F.2d 989, 1969 U.S. App. LEXIS 8774
Court of Appeals for the Fifth Circuit·Decided February 25, 1969·No. 26008·Published·Cited by 5 cases

Opinion

AINSWORTH, Circuit Judge:

This is a diversity case arising out of a multistate cost-plus-fixed-fee subcontract for the engineering and construction of a fertilizer handling and storage facility on the Arkansas-Louisiana Gas Company (ARKLA) site at Helena, Arkansas. Continental Engineering, Ltd. (Continental), an Alabama corporation and subcontractor, sued Chemical Construction Corporation (Chemico), a New York corporation and ARKLA’s prime contractor, for a $540,000 equitable fee adjustment and for $400,000 in allegedly incurred but non-reimbursed costs. The trial court directed a verdict for Chemico on the fee adjustment issue (Count One) and submitted the 18 separate cost items (Count Two) to the jury, after reserving judgment pursuant to Fed.R.Civ.P. 50(a), with instructions that a special verdict be rendered as to each cost item. The jury returned verdicts in Continental’s favor on 16 of 18 cost items. Judgment thereon was entered but later modified when the trial court granted Chemico judgment notwithstanding the verdict with respect to two of the cost items relating to overtime bonuses to exempt employees ($14,127) and to overhead on job shoppers ($31,149). Chemico’s motion for judgment n. o v. as to certain other cost items was denied.

Chemico appeals from the denial of its motion for judgment notwithstanding the verdict with respect' to two cost items which pertain to sand ($66,108) and to shop detail drawings ($137,653). Continental cross-appeals from the judgment entered upon a directed verdict for Chemico on the equitable fee adjustment issue and from the judgment for Chemico notwithstanding the verdict on the two disputed overtime bonuses and job shopper overhead cost items. Without detailing the complex procedural history and factual context of this case, this Court’s appellate review is limited to only five controverted issues: Did the district judge properly grant Chemico a directed verdict on the equitable fee adjustment issue; was the trial court correct in granting Chemico judgment notwithstanding the verdict on two disputed cost issues, namely, the overtime bonuses and job shopper overhead items; and in denying Chemico judgment notwithstanding the verdict on the other two *991 cost issues relating to sand and shop detail drawings? We think so in all respects, and affirm the judgment.

On the equitable fee adjustment issue, the trial court directed a verdict for Chemieo, denying any adjustment in Continental’s favor. Continental did not seek relief on this issue by resort to the contract, which clearly provided for an equitable fee adjustment on the basis of written change orders whereby Chemieo would acknowledge a material increase in the scope of the work (Article F). No written change orders had been made, and those which had been requested were denied by Chemieo with the excuse that it was unable to secure similar relief from ARKLA. Consequently, Continental made a frontal assault on the written contract which had been executed "on” and “as of” February 2, 1966, and which contained an express merger clause. 1 The subcontractor’s theory was as follows: (1) The written contract is ambiguous as to what wa3 its effective date; (2) therefore, parol evidence is admissible to show that the August 1965 subcontract negotiations were consummated in a final, oral contract (later to be “memorialized” in writing); 2 (3) this oral agreement firmly established the project scope; and (4) all subsequent scope changes instituted orally or in writing by Chemieo should be a basis for predicating an equitable fee adjustment claim, notwithstanding the subsequent written contract provision requiring express written change orders. (Article F.)

The trial judge was not persuaded by Continental’s theory, nor are we. The directed verdict for Chemieo was correctly granted for several reasons. First, the written contract containing the express merger clause was clear, unambiguous, and subject to no more than one interpretation. See 3 Corbin, Contracts § 554, pp. 222-223 (1960). Therefore, it need not be opened to judicial construction, even if giving effect to its literal terms will work a hardship on one party. See National Surety Corp. v. Western Fire & Indemnity Co., 5 Cir., 1963, 318 F.2d 379, 387.

“A provision of a contract, which is clear and unambiguous and not subject to more than one interpretation, is not open to construction, even if giving effect to its literal terms will work a hardship on one of the parties. The rule has been applied to insurance contracts.” [Citations omitted.]

See also Jacksonville Terminal Co. v. Railway Exp. Agency, Inc., 5 Cir., 1961, 296 F.2d 256, 261; Simpson Timber Co. v. Palmberg Const. Co., 9 Cir., 1967, 377 F.2d 380, 386; Jackson v. Sam Finley, Inc., 5 Cir., 1966, 366 F.2d 148, 155; Florida Canada Corp. v. Union Carbide & Carbon Corp., 6 Cir., 1960, 280 F.2d 193, 196, and cases cited therein. The fact that Continental vigorously objected to the original $233,000 fixed fee on more than one occasion before execution of the written contract and that the subcontractor attempted (but failed) to secure a contemporaneous oral agreement for a post-performance equitable adjustment from Chemieo indicates that the subcontractor was in the weaker bargaining position. With the trial court we agree that Continental “should have stopped right there and said we won’t go one foot further until .you give us a [written] change order.”

Free access — add to your briefcase to read the full text and ask questions with AI

Chemical Construction Corporation v. Continental Engineering, Ltd., Continental Engineering, Ltd. v. Chemical Construction Corporation, 407 F.2d 989, 1969 U.S. App. LEXIS 8774 (5th Cir. 1969).

407 F.2d 989 (Chemical Construction Corporation v. Continental Engineering, Ltd., Continental Engineering, Ltd. v. Chemical Construction Corporation) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related