Breaux Bros. Construction Co. v. Associated Contractors, Inc.

77 So. 2d 17, 226 La. 720, 1954 La. LEXIS 1376
CourtSupreme Court of Louisiana
DecidedDecember 13, 1954
Docket41474
StatusPublished
Cited by34 cases

This text of 77 So. 2d 17 (Breaux Bros. Construction Co. v. Associated Contractors, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Breaux Bros. Construction Co. v. Associated Contractors, Inc., 77 So. 2d 17, 226 La. 720, 1954 La. LEXIS 1376 (La. 1954).

Opinion

HAWTHORNE, Justice.

Breaux Brothers Construction Company, a Louisiana commercial partnership, instituted this suit against Associated Contractors, Inc., a Louisiana corporation, seeking to recover damages in the sum of $42,802.99 for the breach of an oral contract which plaintiff allegedly had with defendant to' remove dirt from certain drainage canals' in Lafourche Parish. After trial on the merits there was judgment rejecting plaintiff’s demands, and plaintiff has appealed.

The only issue in this case is whether there was a valid contract entered into by the plaintiff and the defendant.

Plaintiff contends that it has proven all the requisites necessary to the validity of a contract prescribed by Article 1779 of the Civil Code, that is: Parties legally capable of contracting; their consent legally given*; *723 a certain object which forms the matter of agreement; and, finally, a lawful purpose. A:s we have found that the element of consent is lacking in the case at bar, it is not necessary to consider whether the other three requisites set out in Article 1779 are present.

Defendant concedes that the parties entered into negotiations with regard to a possible contract, but avers, among other •things, first, that there was never any final, binding contract made because the object and the price were never agreed on, and, second, that it was contemplated that any agreement which might be reached as a result of their negotiations would be reduced to writing and -signed by the parties, and thi.s was- never done.

•' 'The pertinent facts necessary for the decision in this -case-are these: The Police Jury of Lafourche Parish gave notice that it-would receive bids on Má'rch 14, 1951, for thé' construction of'approximately 36 miles b'f drainage canals in that parish involving thfe' excavation and removal of approximately-"871;000 cubic yards of dirt. Associated Contractors, Inc., was contemplating bidding for this construction work, and on March,,4,. 1951, .Ray, and Freund, two offiqeirSsOf defendant corporation, went, to the site of the proposed work to look things pver. On their way home they happened to . meet Fred Breaux, a member of plaintiff partnership. The work involved in the construction of the .drainage canals, requj^e.d equipment,, for. doing both “dry land work” and “water work”, according to the terminology used by the parties. Since the defendant had no equipment to do the water work, Breaux at that time informed the defendant’s officers that his company had such equipment and would be interested in subcontracting for that part of the construction requiring this kind of equipment. It appears that during the March 4 meeting the parties examined blueprints of the proposed work and discussed the possibility of defendant’s subcontracting the water work to the plaintiff should the defendant be the successful bidder on the job. Breaux testified that the portion of the work which his company was to do was definitely agreed on at that time, and that the defendant’s officers agreed that his company would be subcontracted that portion of the work which would have to be done from a barge. However, this is denied by Ray and Freund. Before parting the three men agreed that they would meet again on March 14 at Thibodaux.

It is plaintiff’s contention that the alleged oral contract entered into between it and the defendant was perfected in the course of the two meetings which took place on March 4 and March 14, 1951, between Breaux, Ray, and Freund.

At the first meeting on March 4, discussed ■ above, no definite agreement was reached concerning the price to be paid plaintiff for its work. Consequently no valid contract came into existence as a result of this meeting.

*725 The second meeting of these parties took place at Thibodaux on March 14, a short time before the bids for the canal construction work were submitted to the police jury. During the trial Breaux testified that at this second meeting he discussed with Ray and Freund the amount which the defendant would bid on the proposed work. He stated that he suggested a bid of from $.15% to $.17% per cubic yard for the excavation of dirt, and that they all agreed that-defendant would submit a bid of $.1569 for each cubic yard to be removed in the construction of the canals. Breaux further testified that he agreed to do his part of the work under a subcontract at the same price as that bid by defendant. It is apparent from the record that when this meeting ended Breaux considered that his company had a binding agreement with the defendant.

Ray and Freund, on the other hand, flatly denied at the trial that there was any understanding between the parties as to the price. They testified that Breaux had no knowledge of the price in defendant’s bid until after its bid was opened; that, after defendant’s bid had been opened and accepted, Breaux informed them that he wanted the same price they had bid, $.1569, for the removal of the dirt involved in the water work under a subcontract; that they asked Breaux whether he would be willing to pay any part of the one per cent bonding costs (approximately $1,360) which defendant would have to pay to its bonding company under the principal contract; that.Breaux refused to do so; that they neyer reached any agreement as to the price,'and' that at this point all negotiations terminated.

As the testimony as to the price of the proposed work is in direct conflict, we do not think that plaintiff has established with reasonable certainty that there was any agreement as to the price of the proposed work. Breaux himself admitted that, after defendant’s bid had been accepted, they were still discussing the price and who, would pay the bonding costs.

Article 1798 of the. Civil Code, which deals with the consent necessary to give validity to a contract, provides:

“As there must be two parties at least to every contract, so there must be something proposed by one and accepted and agreed to by another to form the matter of such contract; the will of both parties must unite on the same point.” (All italics ours.) "

As it has not been proved to our satisfaction that the will of the parties in the case at bar united on the price, we are of the opinion that one of the requisites necessary to the validity of a contract as set out in Article 1779 of the Code is wanting— the consent of the parties legally given.

Moreover, we have found that the consent of the parties in the instant case is defective for still another reason. Both Ray and Freund insisted throughout their testimony that all during the negotiations it was intended by all parties that any agreement reached by them as to a subcontract *727 involving $60,000 would be incorporated in a written contract to be signed by all parties and secured by a performance bond. Fred Breaux’s own testimony corroborates that of the defendant’s witnesses on this point. Fie stated:

■ “Q. Now you know about how much money was involved in this contract that you claim that you had negotiated ? A. I do know that.
“Q. About $60,000.00 was it not? A. Just about, yes.
“Q. And wasn’t there anything said about you submitting a written proposal as to what you would do? A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arc Industries, L.L.C. v. William H. Nungesser
Louisiana Court of Appeal, 2018
Usie v. Sunshine Homes, Inc.
222 So. 3d 171 (Louisiana Court of Appeal, 2017)
Doris H. Usie v. Sunshine Homes, Inc.
Louisiana Court of Appeal, 2017
Sunset Realty, Inc. v. Culp
184 So. 3d 256 (Louisiana Court of Appeal, 2016)
Harter v. Harter
127 So. 3d 5 (Louisiana Court of Appeal, 2013)
Shaw Constructors, Inc. v. Hpd, LLC
749 F. Supp. 2d 474 (E.D. Louisiana, 2010)
Rainey v. Entergy Gulf States, Inc.
35 So. 3d 215 (Supreme Court of Louisiana, 2010)
Lambert v. Ray Brandt Dodge, Inc.
31 So. 3d 1108 (Louisiana Court of Appeal, 2010)
Coleman v. Jim Walter Homes, Inc.
6 So. 3d 179 (Supreme Court of Louisiana, 2009)
Bayou Louie Farm, Inc. v. White (In Re Heigle)
401 B.R. 752 (S.D. Mississippi, 2008)
Rainey v. Entergy Gulf States, Inc.
993 So. 2d 735 (Louisiana Court of Appeal, 2008)
Klebanoff v. Haberle
978 So. 2d 598 (Louisiana Court of Appeal, 2008)
JCD Marketing Co. v. Bass Hotels and Resorts, Inc.
812 So. 2d 834 (Louisiana Court of Appeal, 2002)
O'GLEE v. Whitlow
756 So. 2d 1288 (Louisiana Court of Appeal, 2000)
Grabert v. Greco
686 So. 2d 1032 (Louisiana Court of Appeal, 1996)
Carter v. Huber & Heard, Inc.
657 So. 2d 409 (Louisiana Court of Appeal, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
77 So. 2d 17, 226 La. 720, 1954 La. LEXIS 1376, Counsel Stack Legal Research, https://law.counselstack.com/opinion/breaux-bros-construction-co-v-associated-contractors-inc-la-1954.