Marquette v. Housing Authority of Opelousas

137 So. 2d 374
Louisiana Court of Appeal·Decided January 16, 1962·No. 391·Published·Cited by 11 cases

Opinion

137 So.2d 374 (1962)

George MARQUETTE d/b/a Marco Construction Company, Plaintiff and Appellee,
v.
HOUSING AUTHORITY OF OPELOUSAS, Louisiana, Defendant and Appellant.

No. 391.

Court of Appeal of Louisiana, Third Circuit.

January 16, 1962.
Rehearing Denied February 21, 1962.

*375 Andrus & Pavy, by Alex Andrus, Jr., Harry B. Garland and Lessley P. Gardiner, Jr., Opelousas, for defendant-appellant.

Robert F. DeJean and Joseph A. LaHaye, by Robert F. DeJean, Opelousas, for plaintiff-appellee.

Before FRUGE, CULPEPPER and HOOD, Judges.

HOOD, Judge.

This is a suit by George Marquette, d/b/a Marco Construction Company, against The Housing Authority of the City of Opelousas, Louisiana. Plaintiff seeks to recover the sum of $172,924.75, plus legal interest and costs, for work allegedly done and materials allegedly supplied by the plaintiff and/or his subcontractors under a purported contract with the defendant, which contract was declared null and void by judgment of the U. S. District Court for the Western District of Louisiana, and that *376 action was affirmed by the U. S. Court of Appeals, Fifth Circuit. The trial court rendered judgment in favor of plaintiff and against defendant for the sum of $139,361.54, with five percent interest thereon from date of judicial demand until paid, and for all costs of the suit. Defendant has appealed from that judgment.

The record shows that during May, 1958, the defendant, a public body, advertised for sealed bids for the construction of 140 lowrent housing units in the City of Opelousas, Louisiana. Pursuant thereto several bids were received, and among them was a bid submitted by plaintiff in the amount of $1,169,118.00. The defendant accepted the bid of plaintiff, and a contract was entered into between plaintiff and defendant for the construction of this project. After the contract was awarded to plaintiff, another contractor who had submitted a lower bid for the same job, Pittman Construction Company, filed suit against defendant in the U. S. District Court for the Western District of Louisiana to annul that contract, and plaintiff intervened in that suit. As a result of that action the contract between plaintiff and defendant was declared null and void as not having been awarded to the lowest bidder, contrary to the public contract laws of Louisiana (LSA-R.S. 38:2211 et seq.). See Pittman Construction Company v. Housing Authority of City of Opelousas, 167 F.Supp. 517. The defendant appealed that decision to the U. S. Court of Appeals, Fifth Circuit, which affirmed the judgment of the U. S. District Court. Pittman Construction Company v. Housing Authority of City of Opelousas, Louisiana, 264 F.2d 695.

The contract between plaintiff and defendant was entered into on June 25, 1958, and plaintiff commenced performance within one month after that date. The judgment of the U. S. District Court annulling the contract was rendered on October 1, 1958, and all work being done by plaintiff under that contract was halted at that time. Later, however, with the approval of the U. S. District Court, some preservative work was done on the job by plaintiff, for which he claims the sum of $6,660.57, and which amount is included in his total claim.

Prior to the annulling of the contract by the U. S. District Court, plaintiff submitted three monthly estimates, showing work purportedly in place and materials purportedly stored on the site of the job, which estimates represented plaintiff's charges for that work and materials, less 10% retained as provided in the contract. These three estimates covered the periods ending July 31, 1958, August 31, 1958, and September 30, 1958. Defendant paid to plaintiff the amount due according to these three estimates, the total amount so paid amounting to $146,440.87. After the judgment annulling the contract had been rendered by the U. S. District Court, a fourth estimate was submitted by plaintiff, covering the period ending October 11, 1958, but the amount purported to be due under that estimate has not been paid by defendant. Also, a subsequent statement was submitted by plaintiff for the preservative work done by him, as authorized by the U. S. District Court, but the amount claimed under that statement has not been paid.

Plaintiff originally filed suit against defendant for $192,742.18, which he alleged was still due him for work done and materials supplied under the contract. To this suit defendant filed exceptions of no right and no cause of action and an exception of vagueness. In the meantime the defendant had advertised for bids for the completion of the job, and had awarded a contract therefor to Residential Developers, Inc. The plaintiff then amended his original petition, making Residential Developers a party to the suit, seeking an injunction against defendant and Residential Developers, and reducing his demand against defendant to $172,925.75.

Pursuant to a stipulation entered into by and between all parties the amended and supplemental petition filed by plaintiff was dismissed, thereby eliminating Residential Developers as a party to the suit. It was *377 further stipulated between plaintiff and defendant that all pleadings before the court thereafter would address themselves to the original demand in the petition, with the exception that the demand was reduced to $172,925.75, without prejudice to the rights of either party and subject to the court's ruling on the exceptions theretofore filed by defendant. In accordance with that stipulation, a second supplemental and amended petition was filed by plaintiff amending the prayer of his petition to demand only a money judgment for the reduced amount.

The trial court overruled the exceptions of no right and no cause of action, but sustained the exception of vagueness filed by defendant, and plaintiff was ordered to amend his petition to further itemize the amounts claimed. Plaintiff thereupon filed a third supplemental and amended petition, to which pleading there was attached and made a part thereof an itemized statement showing a balance due by defendant to plaintiff of the sum of $172,925.75.

Defendant then filed an answer pleading a number of defenses and praying that plaintiff's demands be limited strictly to any unpaid balance of the actual cost to him of labor, materials used and stored, equipment rentals and preservative work, and that his claims for all other items be rejected, and that the amounts previously paid to plaintiff be attributed to only those items for which he might be entitled to recover. Defendant prayed, in the alternative, that if plaintiff was allowed to recover for certain items of overhead or performance bond costs, that defendant be credited with the fair market value of any tangible items remaining in his possession, the cost of which may have been included in such overhead, and for any refund which plaintiff may receive upon cancellation of said bond. Defendant finally prayed for costs, or an equitable apportionment of costs, and for general and equitable relief.

After trial of the case on its merits the trial court rejected plaintiff's claim for attorney's fees, but concluded that plaintiff was entitled to recover all other amounts claimed. Accordingly judgment was rendered for the principal sum of $139,361.54, plus interest and costs, being the amount remaining after deducting the amount claimed as attorneys fees. It is from this judgment that defendant has appealed. No answer has been filed to the appeal.

Free access — add to your briefcase to read the full text and ask questions with AI

Marquette v. Housing Authority of Opelousas, 137 So. 2d 374 (La. Ct. App. 1962).

137 So. 2d 374 (Marquette v. Housing Authority of Opelousas) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Sam Staub Enterprises, Inc. v. Chapital
88 So. 3d 690 (Louisiana Court of Appeal, 2012)
Hagberg v. John Bailey Contractor, Inc.
499 So. 2d 1132 (Louisiana Court of Appeal, 1986)
Jack A. Parker & Assoc., Inc. v. STATE, ETC.
454 So. 2d 162 (Louisiana Court of Appeal, 1984)
Hagberg v. John Bailey Contractor
435 So. 2d 580 (Louisiana Court of Appeal, 1983)
Coleman v. Bossier City
305 So. 2d 444 (Supreme Court of Louisiana, 1974)
Coleman v. City of Bossier City
291 So. 2d 410 (Louisiana Court of Appeal, 1974)
Corbello v. Jefferson Davis Parish Police Jury
262 So. 2d 151 (Louisiana Court of Appeal, 1972)
Kirchberg v. Holloman
248 So. 2d 347 (Louisiana Court of Appeal, 1971)
Southern Construction Co. v. Housing Authority of Opelousas
189 So. 2d 454 (Louisiana Court of Appeal, 1966)
Pittman Const. Co. v. Housing Auth. of New Orleans
169 So. 2d 122 (Louisiana Court of Appeal, 1965)