Moore v. Housing Authority of City of Opelousas

125 So. 2d 504, 1960 La. App. LEXIS 1304
Louisiana Court of Appeal·Decided December 19, 1960·No. No. 159·Published·Cited by 3 cases

Opinion

SAVOY, Judge.

This matter is before the Court on appeal by plaintiff from a judgment of the lower court rejecting his demands against defendant for a money judgment.

Defendant advertised for bids for the construction of low rent housing units in the City of Opelousas. Several bids were received by said defendant, the lowest bidder being Danel-Ryder Construction Company. Defendant accepted the Ryder bid, but the Public Housing Administration, Fort Worth, Texas, Office, refused to approve this bid on the ground that Ryder, a member of the firm, had only recently resigned as a member of the defendant’s board. The second lowest bid was submitted by Pittman Construction Company. Defendant refused to accept this bid and accepted the bid of George G. Marquette, Jr., doing business as Marco Construction Company.

Shortly thereafter, Pittman Construction Company filed a suit in the Federal District Court, Western District of Louisiana, seeking to declare null and void the bid accepted by defendant and the contract between Marco and defendant.

During the course of the litigation in Federal Court in the Pittman suit, plaintiff as a sub-contractor entered into an agreement with Marco Construction Company to do plumbing, heating, air conditioning, and other related work. The contract was in writing and contained the regular clauses in contracts of that type. There was an addendum to the sub-contract dated several months after the original agreement between the parties. This addendum contained the following words, to-wit:

“Not withstanding anything to the contrary herein stated, it is agreed and understood that there is presently pending in the United States District Court for the Western District of Louisiana in Civil Action No. 7030 a petition for an injunction, which if granted would in effect enjoin further performance of the contractor and sub-contractors, accordingly any unpaid sums due the contractor by the Opelousas Housing Authority and in turn due the subcontractor hereinabove set out, would of necessity be negotiated for with the local Opelousas Housing Authority.
[506]*506“Therefore any claim for labor and material or any other sums or demands upon Marco Construction Company under the contract shall be settled and adjusted with Marco Construction Company upon the same basis and terms as the Marco Construction Company’s settlement and adjustment with the Housing Authority,
“It is further agreed and understood that any proof of claim to be filed in accordance with the laws, rules, and regulations applicable thereto shall be filed by the Marco Construction Company including the claim of the sub-contractor.
“It is further agreed and understood that no claim shall mature for the purpose of litigation against the Marco Construction Company until such a time as the Marco Construction Company shall settle with the Opelousas Housing Authority, whereupon all claims shall be settled and adjusted on the same pro-rata basis as is received by the said Marco Construction Company.”

The addendum to the sub-contract was duly signed by the parties.

The materials as well as the work performed by plaintiff on the housing authority job under the sub-contract were included in four periodic cost estimates submitted to the defendant by Marco Construction Company. The first three were paid as presented.

The Pittman case was finally tried in the Federal District Court, and the district judge held the contract between defendant and Marco Construction Company to be null and void. The decision was affirmed by the United States Circuit Court of Appeal. See Pittman Construction Co. v. Housing Authority of City of Opelousas, D.C., 167 F.Supp. 517, Id., 5 Cir., 264 F.2d 695. In the Pittman case, supra, the Court held that defendant was required by LSA-R.S. 38:2211 to award the contract to the lowest responsible bidder, and that defendant arbitrarily rejected the bid of Pittman Construction Company, and that defendant’s action was null and void when it attempted to award the job and enter into a contract with Marco Construction Company.

The Housing Authority, after the decision in the Pittman case, supra, refused to pay the fourth estimate submitted by Marco Construction Company, because of a difference in the amount which Marco claimed and that which defendant thought it owed.

Plaintiff then filed suit against the Housing Authority on a quantum meruit basis. Defendant filed an answer to the suit denying that it owed plaintiff any money for work, labor, materials, insurance and equipment rental furnished by plaintiff on the housing project. Further answering the suit, defendant alleged that at the time of the execution of said sub-contract by plaintiff with Marco, both parties were aware of the pending suit. Defendant also stated that Marco Construction Company had been paid for all the work performed by plaintiff on the housing authority job, with the exception of the fourth estimate in dispute, and that under the terms of the addendum to the sub-contract agreement between plaintiff and Marco, plaintiff is estopped from collecting any sums from it which might be due him for work, labor, materials and supplies furnished on the said project.

Defendant alleged further that on November 19, 1958, plaintiff filed a lien against Marco Construction Company and defendant for work, materials and supplies furnished on said project, said lien being recorded in the Mortgage Records of St. Landry Parish; that for that reason plaintiff is estopped to deny that he has a legal and valid claim against Marco Construction-Company for any sums still owing to him. by virtue of work performed or materials furnished on said project.

Defendant prayed that the demands of plaintiff be rejected.

[507]*507In brief and in oral argument attorney for plaintiff contended that the sub-con-tract and the addendum thereto between plaintiff and Marco became null and void upon the final decision in the Pittman case, supra, annulling the contract between Marco and defendant, and cited as authority Articles 21 and 1965 of the LSA-Civil Code, and cases of Boxwell v. Dept. of Highways, 203 La. 760, 14 So.2d 627; Smith v. Town of Vinton, 216 La. 9, 43 So.2d 18; Cummings v. Saux, 30 La.Ann. 207; and 17 C.J.S. Contracts § 285.

Articles 21 and 1965 of the LSA-Civil Code recite the following:

“Art. 21. In all civil matters, where there is no express law, the judge is bound to proceed and decide according to equity. To decide equitably, an appeal is to be made to natural law and reason, or received usages, where positive law is silent.”
“Art. 1965. The equity intended by 'this rule is founded in the Christian principle not to do unto others that which we would not wish others should do unto us; and on the moral maxim of the law that no one ought to en•rich himself at the expense of another. When the law of the land, and that which the parties have made for themselves by their contract, are silent, courts must apply these principles to determine what ought to be incidents to a contract, which are required by equity.”

Free access — add to your briefcase to read the full text and ask questions with AI

Moore v. Housing Authority of City of Opelousas, 125 So. 2d 504, 1960 La. App. LEXIS 1304 (La. Ct. App. 1960).

125 So. 2d 504 (Moore v. Housing Authority of City of Opelousas) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Whitehall Oil Company v. Boagni
217 So. 2d 707 (Louisiana Court of Appeal, 1969)
Thompson v. Taylor
192 So. 2d 609 (Louisiana Court of Appeal, 1966)
Marquette v. Housing Authority of Opelousas
137 So. 2d 374 (Louisiana Court of Appeal, 1962)