Smith v. Town of Vinton

43 So. 2d 18, 216 La. 9, 1949 La. LEXIS 1023
CourtSupreme Court of Louisiana
DecidedJune 30, 1949
DocketNo. 39098.
StatusPublished
Cited by37 cases

This text of 43 So. 2d 18 (Smith v. Town of Vinton) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smith v. Town of Vinton, 43 So. 2d 18, 216 La. 9, 1949 La. LEXIS 1023 (La. 1949).

Opinion

HAMITER, Justice.

Previously, this case, in which plaintiff seeks recovery of $3986.09 for work performed (including materials furnished) on defendant’s electrical distribution system, came before us on exceptions of no right and no cause of action directed at the allegations of the petition. 209 La. 587, 25 So. 2d 237, 238. With reference to those allegations, to quote from our reported opinion, we observed:

' “To summarize the petition’s substantial factual averments, which are to be accepted as true for the purpose of considering defendant’s exceptions, plaintiff on March 20, •1944, entered into a verbal contract with W. J. Romero, Mayor of the Town of Vinton, for his furnishing of the labor and equipment necessary in the repair of the electrical distribution system owned and operated by that municipality, he to be paid weekly as the work progressed. The Mayor, at the time, represented that he was duly authorized to make the contract and to proceed with the work, and further that an emergency existed because the, system was in a condition dangerous to life and property; on all of which representations plaintiff relied. Defendant used the distribution system not only for municipal purposes, but also in furnishing electricity to the inhabitants of the town and to persons residing outside of its corporate limits.

“Pursuant to the contract plaintiff commenced the repair job on March 27,' 1944, and continued it until April 11, 1944, at which time he was forced to cease his work because of defendant’s failure to make any of the agreed payments. For the labor, materials and equipment furnished and used between those dates defendant is indebted to plaintiff in the sum of $3986.09.

“Throughout the construction period all of the members of the Town Council witnessed the performance of the work and knew that the repairs were being made. Also they knew that the system was in a condition dangerous to life and property, that an emergency existed, and that plaintiff had been authorized by the Mayor to proceed with the undertaking. Notwithstanding such knowledge, not one offered *13 any protest or objection. Defendant -has used and is using the construction work performed on the system and is reaping the benefits of the labor, materials and equipment furnished by plaintiff at his cost and expense.

“After specially pleading estoppel, plaintiff prayed for judgment on the contract in the sum of the alleged indebtedness, or, alternatively, on quantum meruit for the amount of the claim.”

At the former hearing, under the exceptions, defendant contended that there had been no compliance with the provisions of Act No. 73 of 1926, as amended by Act No. 127 of 1940, which required a contract for public work exceeding the sum of $500 to be awarded to the lowest responsible bidder after advertisement. Since the petition had alleged that plaintiff’s contract provided for the making of repairs to the system, with reference to which an emergency existed because it was in a condition dangerous to life and property, that contention was held untenable under the provision of Section 1 of such statute reciting “ * * * that the procedure herein shall not be necessary in cases of extreme public emergency or for labor necessary and used in the maintenance of public works built and completed.”

Further, at the former hearing, defendant argued that the petition failed to disclose a cause of action inasmuch as it did not allege the granting of authority by defendant’s Board of Aldermen for the Mayor’s entering into the agreement with plaintiff. In answer to this argument we' said:

“ * * * As a general rule a Mayor acting alone is without power to execute a contract incurring a debt on the part of his city or town. He can act only with and under the authority, usually evidenced by a resolution or ordinance, of the Board of Aldermen. But when with the full knowledge of all the members of that Board, and with' no objection or protest being voiced by any of them, the Mayor contracts for and engages in the making of necessary repairs to a municipally owned and operated utility, the town upon being sued on the contract will not be permitted, rather it is estopped, to urge lack of the Mayor’s authority in the incurring of the debt. Especially is this true when the work -performed is used for the advantage and benefit of the town. * * * A situation of the kind just described is alleged in the petition of -this cause; whether plaintiff can prove his allegations is a question which is not before us. If true, and they are deemed so for the purpose of this consideration, his special plea of estoppel must be sustained.”

The exceptions of no right and no cause of action were overruled and -the case was remanded for further proceedings.

On a trial of the merits, following the remand, there -was judgment in favor of plaintiff for $2716.67.

*15 From that judgment defendant is appealing. Plaintiff has answered the appeal praying that the judgment be amended so as to sustain his plea of estoppel and to award the amount demanded in his petition.

As disclosed by his written reasons for judgment the trial judge found as a fact (and the record sustains the finding) that the work performed by plaintiff was pursuant to a verbal agreement with defendant’s Mayor; that the council members, although not having authorized it, had knowledge that plaintiff was engaged in carrying out the agreement and offered no protest until April 10, 1944, or one day prior to the cessation of the work; and that plaintiff’s efforts and undertaking inured to the benefit of defendant, the Town of Vinton.

If lack of authority from the members of the town council were the only irregularity attending the confection of the Mayor’s contract with plaintiff, this defendant, in view of the mentioned circumstances and as pointed out in our former opinion, would be estopped to deny plaintiff’s claim in its entirety. But the agreement in question was affected with another, and a more serious, irregularity, one that rendered it void ab initio. It was an absolute nullity, of the kind that cannot be ratified, either expressly or impliedly, and to which the doctrine of estoppel has no application.

In addition to providing for the making of repairs to the electrical distribution system necessitated by the existence of an emergency, as alleged in the petition, the contract entered into between plaintiff and defendant’s Mayor contemplated, as the record discloses, the rebuilding of the entire system, for all of which a price estimated at approximately $25,000 was to be paid. With reference to this agreement plaintiff testified:

“Q. Mr. Smith, what were the terms of this agreement with Mr. Romero personally? A. We agreed to start the emergency work right away and to submit to the Council the plans for the rebuilding of the entire system and that we would start that work promptly, that they were afraid the water sytem would fail and they might have a fire and cause a lot of damage.
“Q. I believe you stated that the terms you agreed on were $500 a day, each day? A. $500 a job.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Roy Sattler Construction, Inc. v. City of Bossier City
903 So. 2d 503 (Louisiana Court of Appeal, 2005)
Opinion Number
Louisiana Attorney General Reports, 1991
Airline Const. v. Ascension Parish School Board
568 So. 2d 1029 (Supreme Court of Louisiana, 1990)
Pittman Const. Co., Inc. v. PARISH OF E. BATON ROUGE
493 So. 2d 178 (Louisiana Court of Appeal, 1986)
In Re Beychok
484 So. 2d 912 (Louisiana Court of Appeal, 1986)
Hagberg v. John Bailey Contractor
435 So. 2d 580 (Louisiana Court of Appeal, 1983)
Davis v. Franklin Parish School Bd.
412 So. 2d 1131 (Louisiana Court of Appeal, 1982)
Budd Const. Co., Inc. v. City of Alexandria
401 So. 2d 1070 (Louisiana Court of Appeal, 1981)
Williams v. BOARD OF SUP'RS, ETC.
388 So. 2d 438 (Louisiana Court of Appeal, 1980)
Haughton Elevator Division v. STATE, ETC.
367 So. 2d 1161 (Supreme Court of Louisiana, 1979)
College Associates v. City of Baton Rouge
369 So. 2d 1066 (Louisiana Court of Appeal, 1979)
Haskins v. Clary
338 So. 2d 166 (Louisiana Court of Appeal, 1977)
Harp v. Town of Lake Providence
338 So. 2d 169 (Louisiana Court of Appeal, 1976)
Coleman v. Bossier City
305 So. 2d 444 (Supreme Court of Louisiana, 1974)
DJ Talley & Son, Inc. v. City of New Orleans
303 So. 2d 195 (Louisiana Court of Appeal, 1974)
Coleman v. City of Bossier City
291 So. 2d 410 (Louisiana Court of Appeal, 1974)
Succession of Killingsworth
292 So. 2d 536 (Supreme Court of Louisiana, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
43 So. 2d 18, 216 La. 9, 1949 La. LEXIS 1023, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smith-v-town-of-vinton-la-1949.