McIntosh v. Funge

292 P. 960, 210 Cal. 592, 74 A.L.R. 420, 1930 Cal. LEXIS 427
CourtCalifornia Supreme Court
DecidedOctober 28, 1930
DocketDocket No. S.F. 13365.
StatusPublished
Cited by10 cases

This text of 292 P. 960 (McIntosh v. Funge) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McIntosh v. Funge, 292 P. 960, 210 Cal. 592, 74 A.L.R. 420, 1930 Cal. LEXIS 427 (Cal. 1930).

Opinion

CURTIS, J.

This is an appeal by defendant from a joint judgment rendered in favor of the plaintiffs in three actions, originating in the same controversy, which had been consolidated for trial. These actions grew out of an alleged breach of contract for the construction of a two-story dwelling-house in the residential district of San Francisco, known as St. Francis Wood. Due to disagreement which- arose between the defendant owner, W. W. Funge, Jr., and the principal contractors, McIntosh Bros., shortly after the commencement of building operations, the building was never completed. Action 173914 was begun by McIntosh Bros., the principal contractors, for the reasonable value of the services rendered and materials supplied to the defendant owner in the construction of said building and for the profit which would have been realized had the contract been completed. Action 171926 was commenced by Smith Lumber Company of San Francisco against McIntosh Bros., as defendants, for the agreed price of the lumber furnished, by said company and used by McIntosh Bros, in the construction of said building, and against the owner, as co-defendant, to foreclose a materialman’s lien against the property. Action 174168 was instituted by G. Massagli & Co. against McIntosh Bros., as defendants, for the agreed value of the services rendered and the materials furnished in. the construction of the concrete work upon said building, and against the owner, as co-defendant, to foreclose a mechanic’s and materialman’s lien against said property. A cross-complaint was filed by the defendant owner, W. W. Funge, Jr., against McIntosh Bros., in action 173914, for damages alleged to have resulted to said defendant by reason of the failure of McIntosh Bros, to furnish necessary labor and materials to complete in a workmanlike manner said dwelling-house. Upon the consolidated trial of the three actions *595 the court found in favor of the plaintiffs in the above-entitled actions that McIntosh Bros, were entitled to a judgment for $877 against the defendant W. W. Funge, Jr.; that Smith Lumber Company were entitled to a personal judgment of $731.20 against McIntosh Bros, and to have their lien in the sum of $674 foreclosed against the property, and that G. Massagli & Co. were entitled to a personal judgment of $476.80 against McIntosh Bros, and to have their lien in that sum foreclosed against the said property. From said judgment in favor of McIntosh Bros, and from those portions of the judgment which decree that the sums due Smith Lumber Company and G. Massagli & Co. shall be a lien against said property the defendant owner appeals.

The circumstances which gave rise to this controversy, briefly stated, are as follows:

On February 11, 1926, appellant W. W. Funge, Jr., as owner, entered into a contract with William McIntosh and David McIntosh, doing business under the firm name and style of McIntosh Bros., for the construction of a building on appellant’s lot in the city and county of San Francisco. The plans, drawings and specifications were personally prepared by the owner who was not, however, a licensed architect. The owner also acted as his own superintendent of construction. On February 24,1926, McIntosh Bros, commenced work upon the construction of the building. Two subcontracts were entered into by McIntosh Bros., one contract with Smith Lumber Company for lumber to be furnished for the construction of said building, and the other contract with G. Massagli & Co. for the labor and materials used for all of the concrete work specified in the construction of said building. Differences arose between the owner and the principal contractors with reference to the construction of the building, which the owner claimed was not being constructed according to the plans and specifications, and on March 16, 1926, the owner gave notice to the contractors to discontinue work on the house. On March 29, 1926, he wrote to the General Contractors Association of San Francisco, an organization of building contractors of San Francisco, complaining of faulty work and faulty materials being used in the construction of the building. The board of arbitration of said association, consisting of three members, made a personal inspection of the construction of the *596 structure and of the workmanship and materials used and rendered its report in writing on April 1, 1926. The owner refused to accept this report and on April 12, 1926, filed his dissent with the association. The association thereupon made further inspection and investigation and on April 22, 1926, made a supplemental report and finding. In this supplemental report it was stipulated that a competent superintendent of construction should be employed by the owner. The owner refused to accede to this requirement, repudiated the report of the General Contractors Association and refused to employ a superintendent of construction. The matter having come to a deadlock, McIntosh Bros., in accordance with the provisions of paragraph ten of the contract, demanded that the matter be submitted to arbitration. In accordance with the provisions of the contract each of the parties selected one arbitrator and the report and findings of these arbitrators was made on August 13, 1926. On August 19, 1926, McIntosh Bros, notified the owner in writing that they accepted said report and offered to make any changes in the construction required by the report of the arbitrators. The contractors believed that it was possible for them to conform to the award by replacing certain pieces of lumber and strengthening others, and on August 30, 1926, they resumed work. The owner, on the other hand, insisted that in order to conform to the report of the arbitrators it would be necessary for the contractors to take down the frame to the first floor and entirely rebuild it. Upon the refusal of the contractors to tear down the frame, the owner refused to permit them to continue and on August 31, 1926, gave them formal notice to stop work. Thereafter on October 11, 1926, the plaintiff contractors instituted the first of these actions. The consolidated cases went to trial on November 3, 1927. However, the findings were not signed and judgment formally entered until July 30, 1928. During this interim, from the time the plaintiff contractors were notified to stop work on August 31, 1926, until April 14, 1928, the frame of the building stood unfinished, an eyesore to the district and a menace to the children of the neighborhood. On the latter date, the owner, •pursuant to a resolution of the board of public works, had said building torn down and the concrete foundation broken up and removed. At the date, therefore, of the formal ren *597 dering of the judgment the building had been completely demolished and only the excavation of the basement remained.

The complaint of the plaintiff contractors alleged in substance the making of the contract; that plaintiffs commenced to furnish the necessary labor and materials and to perform the work in accordance with the plans and specifications of said contract; that a dispute arose respecting the true construction of said specifications and the sufficiency of the performance of said work; that two arbitrators were selected to settle said dispute; that the plaintiffs accepted the decision of said arbitrators and so notified the defendant owner in writing; that plaintiffs thereafter commenced to again perform said contract but were notified by the defendant in writing that said contract was terminated.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pacific Coast Refrigeration, Inc. v. Badger
52 Cal. App. 3d 233 (California Court of Appeal, 1975)
McDonald v. Filice
252 Cal. App. 2d 613 (California Court of Appeal, 1967)
Marquette v. Housing Authority of Opelousas
137 So. 2d 374 (Louisiana Court of Appeal, 1962)
Nolte v. Smith
189 Cal. App. 2d 140 (California Court of Appeal, 1961)
In Re Smith's Estate
1946 OK 165 (Supreme Court of Oklahoma, 1946)
Borden v. Day
1946 OK 121 (Supreme Court of Oklahoma, 1946)
Albuquerque Lumber Co. v. Montevista Co.
38 P.2d 77 (New Mexico Supreme Court, 1934)
McIntosh v. Funge
16 P.2d 1006 (California Court of Appeal, 1932)

Cite This Page — Counsel Stack

Bluebook (online)
292 P. 960, 210 Cal. 592, 74 A.L.R. 420, 1930 Cal. LEXIS 427, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcintosh-v-funge-cal-1930.