Southern Construction Co. v. Housing Authority of Opelousas

189 So. 2d 454, 1966 La. App. LEXIS 4680
CourtLouisiana Court of Appeal
DecidedAugust 3, 1966
DocketNo. 1777
StatusPublished
Cited by9 cases

This text of 189 So. 2d 454 (Southern Construction Co. v. Housing Authority of Opelousas) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Construction Co. v. Housing Authority of Opelousas, 189 So. 2d 454, 1966 La. App. LEXIS 4680 (La. Ct. App. 1966).

Opinions

FRUGÉ, Judge.

This is a suit by Southern Construction Company (hereinafter referred to as “contractor”) against the Housing Authority of the City of Opelousas, Louisiana (hereinafter referred to as “Housing Authority”), for payment of an amount allegedly due under a building contract between said parties. The trial court awarded judgment in favor of plaintiff for $7,160.00. Both parties have appealed from said judgment. Defendant contends that the trial court was in error in awarding judgment in favor of plaintiff, whereas plaintiff contends that the trial court was in error in refusing to award legal interest on the principal amount and in refusing to assess all court costs against defendant.

The factual situation giving rise to the instant action is as follows: On November 29, 1960, the Housing Authority entered into a contract with plaintiff contractor for the construction of forty low-rent housing units in the City of Opelousas, Louisiana. The time allowed for completion of the contract was 320 calendar days from the above date, or to October 14, 1961. The contract provided for liquidated damages in the amount of $40.00 per day (actually $1.00 per unit) to be paid by the contractor to the Housing Authority for each day that the project required in excess of the specified time limit. Claiming that the contractor exceeded said time limit by 179 days, the Housing Authority withheld $7,160.00 from the agreed contract price as liquidated damages. This is the amount which is in dispute.

Plaintiff contractor claims that it is entitled to the entire contract price since the project was completed and accepted. Said contractor denies that it failed to timely complete the project and alleges, alternatively, that if the completion was not timely, said contractor was never placed in default as is required by law for the collection of damages.

We believe that the present jurisprudence of this state is correctly summarized in Brooks v. Neyrey, La.App. 4 Cir., 167 So.2d 400, as follows:

“It is well settled that a contractor’s failure to complete a building contract within the time specified in the contract constitutes merely a passive breach thereof and that a putting in default is a condi[456]*456tion precedent to the recovery of liquidated damages for the contractor’s delay in completion unless by the terms of the contract a putting in default is waived or unless by stipulation in the contract or by the nature and circumstances of the agreement time is of the essence thereof, or unless a putting in default is excused by some act of the obligor which would render it a vain and useless thing, (citations omitted).”

See also Godchaux v. Hyde, 126 La. 187, 52 So. 269; Gulotta v. Swinney, La.App. 1 Cir., 143 So.2d 775; Binnings Construction Co. v. Louisiana Life Ins. Co., La.App. 4 Cir., 139 So.2d 561; Comment: “The Putting in Default as a Prerequisite to Suit in Louisiana,” 1 Loyola Law Review 127.

The contract involved herein does not waive the putting in default nor stipulate that time is of the essence. However, recent cases dealing with the question presented herein have indicated that when the contract states a specific completion date and provides for stipulated damages if the project is not completed by said date, it is presumed that time is of the essence and, therefore, no putting in default is required. See Brooks v. Neyrey, supra; Binnings Construction Co. v. Louisiana Life Ins. Co., supra. In fact, in at least two cases the courts have not found it expedient to discuss the hypo-technical concept of “putting in default” when said contractual conditions prevail. See Wilson v. Peak, 210 La. 969, 28 So.2d 677; Meaux v. Southern Construction Corp., La.App. 3 Cir., 159 So.2d 156.

While, as stated above, time is generally of the essence in cases of this nature, we have determined that under the unique situation presented herein, time was not of the essence and a putting in default was necessary. The contract in question provided:

“If the work is delayed by any act or neglect by the local authority or its representatives, or by changes in the work, or by strikes, fire, freight embargoes, unusually severe weather, or by unforeseeable causes beyond the control and without the fault of the contractor, then, if the contractor shall within ten days from the beginning of such delay notify the contracting officer of the cause and extent thereof, the Local Authority, subject to verification of the facts and to approval by the PHA, shall extend the time for completing the work.”

In compliance with the above provision, the contractor presented a number of requests for time extensions to the Housing Authority. The number of requests is in dispute, the contractor claiming to have submitted forty-one requests ranging from two day extension requests to thirty day extension requests, and the Housing Authority admitting receipt of only twelve requests. The record shows that said requests for time extensions were not considered until after the project was completed. The project herein was completed 214 days after the original set completion day. The Housing Authority, after consulting the daily reports of its inspectors, allowed the contractor an extension of thirty-five days and computed liquidated damages using the figure of 179 days. Since the contractor had no way of knowing which requests for time extensions would be accepted and which would be rejected, it certainly did not know the date the Housing Authority would commence assessing the stipulated damages ($40.00 per day). Under these circumstances, we are of the opinion that time was not of the essence and that if the Housing Authority desired to assess the stipulated damages, the burden was upon it to put the contractor in default. The factual situation herein presents a sound basis for applying the doctrine of “putting in default.”

In answer to the Housing Authority’s contention that it actually put the contractor in default, we need only state that the record does not indicate that the contractor was ever informed which requests for time extensions would be granted or upon what date the Housing Authority would start [457]*457assessing liquidated damages until after the project was finally completed. The Housing Authority’s contention that putting in default would have been a “vain and futile act” is also without merit, since the contractor might well have increased the number of workmen and worked on the weekends, etc., if it had known that liquidated damages in the amount of $40.00 per day were being assessed against it.

For the foregoing reasons we are of the opinion that the plaintiff contractor is entitled to recover the $7,160.00 withheld by the Housing Authority. Plaintiff contractor further contends that it is entitled to legal interest on the judgment and that all court costs should have been assessed to the Housing Authority. The trial court refused to allow interest on the judgment and assessed only those costs provided by LSA-R.S. 13:4521 against the Housing Authority.

Until the case of Pittman Const. Co. v. Housing Auth. of New Orleans, La.App. 4 Cir., 169 So.2d 122, (writs refused), the jurisprudence of this State had consistently been that, in absence of a specific statute, interest could not be assessed against the State or its agencies in matters arising ex contractu. See State ex rel. Anderson v. Walker, 233 La. 687, 98 So.2d 153; Jefferson Lake Sulphur Co. v. State, 213 La. 1, 34 So.2d 331; Hamberlin v. Tangipahoa Parish School Board, 210 La.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Castillo v. Montelepre, Inc.
999 F.2d 931 (Fifth Circuit, 1993)
Opinion Number
Louisiana Attorney General Reports, 1993
Herrin v. Perry
215 So. 2d 177 (Louisiana Court of Appeal, 1968)
Louisiana Paving Co. v. Louisiana Department of Highways
205 So. 2d 445 (Louisiana Court of Appeal, 1967)
Southern Construction Co. v. Housing Authority
197 So. 2d 628 (Supreme Court of Louisiana, 1967)
Freeman v. Department of Highways
197 So. 2d 188 (Louisiana Court of Appeal, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
189 So. 2d 454, 1966 La. App. LEXIS 4680, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-construction-co-v-housing-authority-of-opelousas-lactapp-1966.