Southern Construction Co. v. Housing Authority

197 So. 2d 628, 250 La. 569, 1967 La. LEXIS 2743
CourtSupreme Court of Louisiana
DecidedMarch 27, 1967
Docket48401, 48402
StatusPublished
Cited by24 cases

This text of 197 So. 2d 628 (Southern Construction Co. v. Housing Authority) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Construction Co. v. Housing Authority, 197 So. 2d 628, 250 La. 569, 1967 La. LEXIS 2743 (La. 1967).

Opinion

SANDERS, Justice.

Southern Construction Company sued the Housing Authority of the City of Opelousas for the balance due it under a building contract, together with legal interest and court costs. The Housing Authority denied liability, asserting it had withheld $7,160.00 of the contract price as “liquidated damages” for failure to timely ■complete the work, as stipulated in the contract.

The district court awarded plaintiff judgment for $7,160.00, but denied legal interest and restricted defendant’s court cost liability to the stenographer’s fee as provided by LSA-R.S. 13:4521. Both parties appealed. The Court of Appeal affirmed. See 189 So.2d 454. On application of both parties, we granted certiorari to review the Court of Appeal judgment. 249 La. 752, 753, 190 So.2d 913.

Motion to Dismiss Appeal

At the time of oral argument in the Court of Appeal, Southern moved to dismiss Housing Authority’s appeal because of its failure to file an appeal bond. This motion stands at the threshold of the case.

When the law requires an appeal bond, no appeal is perfected until the bond has been filed. In the absence of an appeal bond, the jurisdiction of the Court of Appeal never attaches. LSA-C.C.P. Art. 2088; Orrell v. Southern Farm Bureau Casualty Ins. Co., 248 La. 576, 180 So.2d 710. Such an appeal may be formally dismissed, though the appellee’s motion is filed after the return date for the appeal. LSA-C.C.P. Arts. 2161 and 2162; Orrell v. Southern Farm Bureau Casualty Ins. Co., supra; Britt v. Brocato, La.App., 170 So.2d 516, cert. denied 247 La. 618, 172 So.2d 701.

Housing Authority asserts that the law exempts it, as a public body, from furnishing an appeal bond.

LSA-R.S. 13:4581 provides:

“State, parish and municipal boards or commissions exercising public power and functions shall not be required to furnish any appeal bond; or any other bond whatsoever in any judicial proceedings instituted by or brought against them.”

The Housing Authority of the City of Opelousas was created pursuant to LSA-R.S. 40 :381 et seq., known as the *577 Housing Authorities Law. The function of The Housing Authority is to relieve slum or blighted areas through the construction of low-rent housing. See State ex rel. Porterie v. Housing Authority of New Orleans, 190 La. 710, 182 So. 725. Such an authority is a corporate public body. LSA-R.S. 40:391. The Housing Authority must be classified, as a public board, within the meaning of the above statute. Hence, the statute exempts the Authority from furnishing an appeal bond.

We conclude, as did the Court of Appeal, that the appeal should be maintained.

On The Merits

The questions presented on the merits relate to the liability of Southern, the contractor, for “liquidated damages” under the contract and the liability of Housing Authority for legal interest and costs of courts.

The facts are these: On November 29, 1960, the Housing Authority contracted with Southern for the construction of forty low-rent housing units in Opelousas. The contract allowed Southern 320 calendar days, or to October 14, 1961, to complete the work.

The contract provided for time extensions and “liquidated damages” as follows:

“If the work is delayed by any act or neglect by the local authority or its representatives, or by changes in the work, or by strikes, fire, freight embargoes, unusually severe weather, or by unforeseeable causes beyond the control and without the fault of the contractor, then, if the contractor shall within ten days from the beginning of such delay notify the contracting officer of the cause and extent thereof, the Local Authority, subject to verification of the facts and to approval by the. PHA, shall extend the time for completing the work.”
******
“If the contractor fails to complete the work within the time specified in the Special Conditions, plus any extension of time granted by the Local Authority pursuant to the foregoing provisions, then the contractor shall pay to the Local Authority as fixed, agreed, and liquidated damages (it being impossible to determine the actual damages occasioned by the delay) for each calendar day of delay, until the work is completed, the amount set forth in the Special Conditions, and the contractor and his sureties shall be liable for the amount thereof.”

In the special conditions, the ' contract fixed the “liquidated damages” at the rate of $40.00 per day, computed on the basis of $1 for each housing unit.

Having filed requests for extensions under the foregoing contract provision, Southern completed the work on May 16, 1962, two hundred and fourteen days after the original completion date.

*579 After the project was completed, the Housing Authority acted on the various requests for extensions and granted 35 days. It notified the contractor of the extension and at the same time of the withholding of “liquidated damages” from the contract price in the sum of $7,160.00 for the remaining 179 days overrun. The contractor’s suit followed.

Southern asserts it is entitled to the full contract price since the housing units were completed within the 322 days extension allowable from 39 requests filed by it. Alternatively, if completion overran the allowable extension, the Housing Authority never put it in default as required by law for collection of delay damages.

Housing Authority contends the completion was delayed 179 days beyond the term of the contract. The contractor timely filed only twelve extension requests, justifying an extension of 35 days; the remaining requests were neither timely filed nor validly based. It further contends that a putting in default was unnecessary to collect the stipulated damages in the present case. But if such be required, the evidence sufficiently establishes a putting in default.

We have examined the additional extensions claimed by the contractor. The contract required that all extension requests be made within ten days from the beginning of the delay. The contract also limited the grounds for extension. From the evidence, we are convinced the position of the Housing Authority is correct: the disputed requests were untimely and lacked a valid basis under the contract.

The prime question is whether a putting in default is a prerequisite to the collection of “liquidated damages” under the contract.

Under the Louisiana Civil Code, the building contract is classified as a contract to do. LSA-C.C. Arts. 1883, 1926. The “liquidated damages” provision is classified as a penal clause for delay. LSA-C.C. Arts. 2117, 2125. Such a penal clause is designed to fix the measure of damages in advance and to constrain the timely performance of the principal obligation. LSA-C.C. Arts. 1934(5), 2117, 2125; 25 Tul.L. Rev. 407, 408. No showing of pecuniary or other actual damage is required to enforce the clause. Stewart-McGhee Construction Co. v. Caddo Parish School Board, 165 La. 200, 115 So. 458.

The following Civil Code Articles govern the default issue as framed by the present case:

Article 1931.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Utley-James of La., Inc. v. State, Div. of Admin.
671 So. 2d 473 (Louisiana Court of Appeal, 1995)
Tarver v. Bailey
633 So. 2d 347 (Louisiana Court of Appeal, 1993)
O & M Construction, Inc. v. State, Division of Administration
576 So. 2d 1030 (Louisiana Court of Appeal, 1991)
O & M CONST. v. State, Div. of Admin.
576 So. 2d 1030 (Louisiana Court of Appeal, 1991)
Texaco, Inc. v. Louisiana Land & Exploration Co.
113 B.R. 924 (M.D. Louisiana, 1990)
Johnson v. Southern University
551 So. 2d 1348 (Louisiana Court of Appeal, 1989)
North Central Utilities, Inc. v. East Columbia Water District
497 So. 2d 326 (Louisiana Court of Appeal, 1986)
Gremillion's Heirs v. Rapides Parish Police Jury
493 So. 2d 584 (Supreme Court of Louisiana, 1986)
Southwood Development Corp. v. Thomas Supply, Inc.
469 So. 2d 417 (Louisiana Court of Appeal, 1985)
Carr v. STATE THROUGH DEPT. OF HEALTH & HUMAN RES.
451 So. 2d 1282 (Louisiana Court of Appeal, 1984)
Bray v. Arthur Treacher's Fish & Chips, Inc.
409 So. 2d 1274 (Louisiana Court of Appeal, 1982)
Klumpp v. Colonial Pipeline Co.
389 So. 2d 457 (Louisiana Court of Appeal, 1980)
Southern Hardware Co. v. Honeywell Information
373 So. 2d 738 (Louisiana Court of Appeal, 1979)
Watts v. Town of Homer
301 So. 2d 729 (Louisiana Court of Appeal, 1974)
Swan v. Clover Farm Creamery, Inc.
311 So. 2d 285 (Louisiana Court of Appeal, 1974)
Malone v. Malone
282 So. 2d 119 (Supreme Court of Louisiana, 1973)
Lebrane v. Lewis
280 So. 2d 572 (Louisiana Court of Appeal, 1973)
Carona v. Webster
270 So. 2d 609 (Louisiana Court of Appeal, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
197 So. 2d 628, 250 La. 569, 1967 La. LEXIS 2743, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-construction-co-v-housing-authority-la-1967.