C. Graham Pembroke, Plaintiffs-Appellees-Cross v. Gulf Oil Corporation, Defendant-Appellant-Cross (Two Cases)

454 F.2d 606
CourtCourt of Appeals for the Fifth Circuit
DecidedJanuary 24, 1972
Docket71-1241
StatusPublished
Cited by9 cases

This text of 454 F.2d 606 (C. Graham Pembroke, Plaintiffs-Appellees-Cross v. Gulf Oil Corporation, Defendant-Appellant-Cross (Two Cases)) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C. Graham Pembroke, Plaintiffs-Appellees-Cross v. Gulf Oil Corporation, Defendant-Appellant-Cross (Two Cases), 454 F.2d 606 (5th Cir. 1972).

Opinion

THORNBERRY, Circuit Judge:

Gulf in the instant case appeals from a judgment of the district court entered in Pembroke’s favor for $248,657.00. Liability was based on Gulf’s breach of contract in flooding Pembroke’s land in excess of certain contract rights granted. Finding Gulf to have hit home on but one of its points in this appeal, which is as water-logged as Gulf’s right of way, we affirm in part and reverse in part.

The facts, as found by the district court and supported by substantial evidence, are as follows. In 1963, Pembroke granted to Gulf a right of way 100 feet in width across two adjoining tracts of land, designated as Tracts A and B, 1 “for the purpose of constructing, maintaining and operating four pipe lines.” Also granted was the right to dredge a canal within each right of way not to exceed 45 feet in width in which to lay the pipelines. The parties further agreed, under Article XI of the contract:

If the Grantee fails to carry out . . every obligation agreed to by it herein . . . this right of way shall terminate upon Grantee’s failure to correct any non-compliance within sixty (60) days from date of written notice by Grantor of such non-compliance.

In the event this right of way is terminated for any reason

(a) Grantee, within ten (10) days after receipt of written request to so do, shall furnish to Grantor ... a full and complete release of any and all of its rights and claims granted by this right of way or arising from, under or by virtue of this right of way; and,

*609 (b) Grantee shall . . . within ninety (90) days of written request of Grantor, remove its pipe lines, and replace the dams made hereunder, to the extent directed by Grantor.

In addition to any and all rights which Grantor may have by law to enforce this agreement or for damages (Grantor hereby specifically reserving same), Grantee agrees and guarantees that in the event it fails to comply with Clause (a) or Clause (b), or both, set forth in the foregoing paragraph, it will pay to Grantor as liquidated damages for the mere delay in complying with said clause or clauses;

(1) $100.00 (One Hundred Dollars) per day, counting from the date of the cause of the termination until compliance with the pertinent clause or clauses has been accomplished ;

(2) Legal interest on said liquidated damages counting from the date of the cause of termination until paid;

(3) All court costs necessary to enforce the provisions hereof; and,

(4) Reasonable attorney’s fees of not less than $5,000.00 (Five Thousand Dollars). 8

Prior to January, 1964, Gulf dredged the original canal and completed laying two pipelines. On October 29, 1964, Pembroke notified Gulf that the canal was being widened by boat traffic, that various no trespassing signs were down, and that certain dams were in need of repair. Pembroke demanded that the latter two conditions be corrected. At this time, it is undisputed that the canal in question had reached a width of over 90 feet. Gulf met Pembroke’s demands at a cost of over $27,000.00. Gulf thereafter completed laying a third pipeline in December, 1965.

On April 24, 1967, Pembroke notified Gulf that it was their understanding that the width of the canal on Tract A was in excess of 100 feet. Pembroke made demand under the terms of Article XI that Gulf reduce the width of the canal to no wider than 45 feet. On May 15, 1967, the notice was made applicable to Tract B.

Gulf did not correct the alleged deficiency within 60 days, as required. Pembroke thereafter, on July 18, 1967, issued a termination notice in compliance with Article XI, ordering Gulf to remove its pipelines within 90 days and to furnish a release of all obligations within 10 days. Gulf refused all such demands, and suit was filed on September 3, 1969, to require removal of the pipelines and to obtain actual and liquidated damages, and attorneys fees. 2 3

At the times suit was filed, it was undisputed that Tracts A and B were covered by 22 and 15 acres of water, respectively, including 11.1849 acres on Tract A and 7.1898 acres on Tract B which would not have been covered had the water been confined within the original 45 foot canal. On Tract A, 2.09 acres of water lay completely outside the 100-foot right of way. The average width of the water-covered area was *610 111.53 feet on Tract A and 89.60 feet on Tract B. 4

Gulf first contends, incredible as it may seem, that it has not breached the contract. In order to come to this conclusion, Gulf analogizes the agreement in question to the grant of a servitude —an unspecified grant for a specified purpose. 5 Gulf contends that at a minimum, in order to dredge a canal and lay its pipelines, it was necessary to construct a canal at least 11 feet deep and to make a box cut of sufficient width (38 feet) to permit flotation of barges through the entire length of the premises. Gulf’s actions in excavating the canal across the premises and in laying its pipelines would, under this theory, fully comply with the terms of the contract and, more particularly, with the purposes for which they were executed. If loss or damage to the premises resulted by reason of Gulf’s exercise of these rights, Gulf argues that Pembroke is restricted to recovery of damages for its actual loss.

The easy answer to this contention is that Gulf, knowing full well the implications of its necessary use, should have bargained for a wider right of way. Although it is generally conceded that the grantee of a servitude is entitled to do all that is reasonably necessary for a full and proper enjoyment of the rights granted him under the servitude, 6 the extent of the servitude may be fixed by the terms of the contract. 7 The parties here have clearly limited the servitude to construction of a canal not in excess of 45 feet in width.

Gulf first dredged the canal at a width of 45 feet and a depth of 8 feet. Pembroke’s property is located in marshy coastal terrain and is subject to tidal overflow. The marshy terrain through which the canal was dredged was unstable to the extent that for each foot dredged vertically there would eventually be lateral subsidence of each bank so as to increase the width at a rate of 2.75 to 3 feet for each foot of vertical depth dredged. All dredging was evidently confined within the original 45 foot grant. Gulf found it necessary to dredge the canal 8 feet deep in order to accommodate the draft of the dredges and the pipe laying barges, and an extra 3 feet to bury the pipelines. Gulf knew full well that the banks of the canal would slide into the water under such conditions. As part of the original project, Gulf made a second excavation to maintain a depth of 8 feet. As a result of this second excavation and further piling soil on the unstable banks, along with the resulting sliding action, water covered an area more than 45 feet wide when the first project was completed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Little Bell, LLC v. Centerpoint Energy, Inc.
838 F. Supp. 2d 522 (W.D. Louisiana, 2012)
Wells Fargo Bank, N.A. v. Jones
391 B.R. 577 (E.D. Louisiana, 2008)
Leeber v. Deltona Corp.
546 A.2d 452 (Supreme Judicial Court of Maine, 1988)
Klumpp v. Colonial Pipeline Co.
389 So. 2d 457 (Louisiana Court of Appeal, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
454 F.2d 606, Counsel Stack Legal Research, https://law.counselstack.com/opinion/c-graham-pembroke-plaintiffs-appellees-cross-v-gulf-oil-corporation-ca5-1972.