Bellwether Enterprise Real Estate Capital v. Jaye

CourtDistrict Court, E.D. Louisiana
DecidedJune 10, 2020
Docket2:19-cv-10351
StatusUnknown

This text of Bellwether Enterprise Real Estate Capital v. Jaye (Bellwether Enterprise Real Estate Capital v. Jaye) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bellwether Enterprise Real Estate Capital v. Jaye, (E.D. La. 2020).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF LOUISIANA

BELLWETHER ENTERPRISE REAL ESTATE CAPITAL CIVIL ACTION

v. NO. 19-10351 c/w 19-130581

CHRISTOPHER JAYE, ET AL. SECTION “F”

ORDER AND REASONS Before the Court are cross-motions for summary judgment. For the reasons that follow, the motions of Christopher Jaye, Kristi Morgan, and Mirus New Orleans are GRANTED and the motion of Bellwether Enterprise Real Estate Capital is DENIED. Background This contract dispute arises from a project to build affordable housing in New Orleans East and concerns, principally, a stipulated damages provision in a contract between borrowers and their lender. The borrowers say the provision is unenforceable under a Louisiana law allowing courts to modify stipulated damages that are “so manifestly unreasonable as to be contrary to public policy.” LA. CIV. CODE art. 2012. The Court agrees.

1 This Order applies to both consolidated cases. Christopher Jaye and Kristi Morgan own a real estate development company called Mirus New Orleans. That company owns the Village of Versailles project——the first affordable housing

development built in New Orleans East after Hurricane Katrina. To fund the Village of Versailles project, Jaye, Morgan, and Mirus obtained a $31,552,100 commercial mortgage loan from Bellwether. The loan is insured by the United States Department of Housing and Urban Development and memorialized in a mortgage note and a building loan agreement. Under the building loan agreement, Bellwether disbursed loan proceeds upon receipt of “draw requests” from Mirus. After funding each draw, Bellwether sold GNMA mortgage- backed securities in the amount of the draw to Lancaster Pollard,

an investment company. Pivotal to the project was one date——August 31, 2018. By then, two events should have occurred: completion of construction and final endorsement. Final endorsement is when HUD approves a loan for insurance; to ensure that it occurred on time, and as a condition of the loan, Jaye, Morgan, and Mirus entered into an extension-fee agreement with Bellwether. That agreement required the borrowers to pay Bellwether a monthly “extension fee” if final endorsement did not occur by August 31, 2018: 1. Extension Fees. (a) Obligor agrees that in the event that Final Endorsement has not occurred on or before August 31, 2018, Obligor shall be liable and obligated to pay to Lender a monthly extension fee (the “Extension Fee”) equal to (i) 1/8th of one percent (0.125%) of the original face amount of the FHA Mortgage Note for each “monthly Period” (as defined below) or portion thereof, commencing on September 1, 2018 and continuing through November 31, 2018 then increasing to (ii) 1/4th of one percent (0.25%) of the original face amount of the FHA Mortgage Note for each Monthly Period or portion thereof, commencing on December 1, 2018 and continuing until Final Endorsement. In the event that Final Endorsement shall not theretofore have occurred, Obligor shall be obligated to pay each such monthly Extension Fee in advance, fifteen (15) days prior to the commencement of the applicable Monthly Period; provided that Lender shall refund the last such monthly Extension Fee to Obligor in the event that Final Endorsement shall occur prior to the commencement of the applicable Monthly Period. Thereafter, there shall be no refund of the monthly Extension Fee. As used herein [sic] “Monthly Period” shall mean a period starting on the first day of a month and ending on the last day of that month. This extension-fee agreement, Bellwether maintains, compensates it for the losses it would suffer if final endorsement did not occur by August 31, 2018. Those losses would allegedly result from Bellwether’s trade agreement with its investor, Lancaster Pollard. Under that trade agreement, Bellwether had to pay Lancaster Pollard a fee of $39,440.13——which equates to 0.125% of the delivery amount of the $31,552,100 loan——for each month final endorsement was delayed. Delay ensued. The parties dispute the reason: Bellwether points to a lawsuit the general contractor brought against Mirus and others; the borrowers highlight Bellwether’s alleged negligence in impeding the selection of a project management agent. Whatever the reason for the delay, it is undisputed that the general contractor on the project, Broadmoor, LLC, sued Mirus, Bellwether, and others in September 2018. See Eastern District of

Louisiana Civil Action No. 18-9064. And it is undisputed that Broadmoor’s lawsuit complicated the final-endorsement process; the Federal Housing Administration Multifamily Program Closing Guide (HUD Guide), which governs the closing of HUD-insured loans, illustrates how. Section 1.17(A) of the HUD Guide contemplates delays caused by disputes between a borrower and a contractor, like the litigation involving Mirus and Broadmoor: A. Disputes. Occasionally, Borrower and the general contractor may have disputes regarding change orders, the quality or cost of the construction work, or the timing of payments therefore [sic]. This may delay final closing. If Borrower and the general contractor enter into arbitration, litigation, or both, the delay may be excessive. It may be impossible to reach agreement in order to complete final closing. Such delays may cause Lender and Borrower to ask HUD to finally endorse the Note even without the full participation of the general contractor, because the cost of continuing to incur extension or other fees and Lender’s need to convert the underlying financing of the mortgage loan to permanent status. Section. 1.17(B) of the HUD Guide contains a procedure for final endorsement despite such litigation: B. Closing Without General Contractor. If both the HUB Director and HUD Closing Attorney, each in his or her own discretion, agree, the parties may proceed to final closing without the participation of the general contractor if the following conditions are met: 1. Cost certification must have been satisfactorily completed by all parties required [sic] subject to this requirement. 2. The remaining mortgage loan proceeds must be placed in escrow pending the outcome of the dispute. 3. The title company must issue affirmative title insurance coverage over any liens that are in place related to the dispute. 4. There must be a mechanism in place for eventual resolution of the dispute or termination of the escrow that is satisfactory to HUD, such as litigation that does not involve HUD. So, for the loan to proceed to final endorsement despite the Broadmoor litigation, all of the requirements set out in Section 1.17(B) had to be met. The parties dispute whether those conditions could have been met, but they agree that final endorsement did not occur by way of Section 1.17(B). The Broadmoor litigation settled in March 2019, and final endorsement occurred around the same time. As that dispute resolved, another emerged. Because final endorsement did not occur by August 31, 2018, Bellwether invoked the extension-fee agreement and demanded fees from Jaye, Morgan, and Mirus. Bellwether said the borrowers owed $39,441 per period for the monthly periods beginning on September 1 and October 1 and $78,881 per period for the monthly periods beginning on November 1, December 1, January 1, February 1, and March 1. Bellwether received a fraction of what it claimed: the borrowers made just two $39,441 payments, for the monthly periods beginning September 1 and October 1. The borrowers declined to pay the $354,965 in

extension fees that allegedly accrued during the monthly periods from November 1 to March 1. So Bellwether sued. In its one-count complaint, filed in May 2019, Bellwether alleged that Jaye and Morgan breached the extension-fee agreement by failing to pay $354,965 in extension fees. For reasons unexplained, Bellwether did not sue Mirus——the company owned by Jaye and Morgan and also bound by the extension-fee agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

King v. Dogan
31 F.3d 344 (Fifth Circuit, 1994)
Brown v. City of Houston, TX
337 F.3d 539 (Fifth Circuit, 2003)
Audler v. CBC Innovis Inc.
519 F.3d 239 (Fifth Circuit, 2008)
Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
Klaxon Co. v. Stentor Electric Manufacturing Co.
313 U.S. 487 (Supreme Court, 1941)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Robert Antoine v. First Student, Incorporated
713 F.3d 824 (Fifth Circuit, 2013)
Philippi v. Viguerie
606 So. 2d 577 (Louisiana Court of Appeal, 1992)
Lama v. Manale
50 So. 2d 15 (Supreme Court of Louisiana, 1950)
John Jay Esthetic Salon, Inc. v. Woods
377 So. 2d 1363 (Louisiana Court of Appeal, 1979)
Plaquemines Parish v. RIVER/ROAD CONST.
828 So. 2d 16 (Louisiana Court of Appeal, 2002)
Whitehall Oil Company v. Boagni
217 So. 2d 707 (Louisiana Court of Appeal, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
Bellwether Enterprise Real Estate Capital v. Jaye, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bellwether-enterprise-real-estate-capital-v-jaye-laed-2020.