Stewart-Mcghee Const. Co. v. Caddo Parish School Board

115 So. 458, 165 La. 200, 1927 La. LEXIS 1897
CourtSupreme Court of Louisiana
DecidedOctober 31, 1927
DocketNo. 28371.
StatusPublished
Cited by7 cases

This text of 115 So. 458 (Stewart-Mcghee Const. Co. v. Caddo Parish School Board) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stewart-Mcghee Const. Co. v. Caddo Parish School Board, 115 So. 458, 165 La. 200, 1927 La. LEXIS 1897 (La. 1927).

Opinion

ST. PAUL, J.

On February 11,1924, plaintiffs contracted to construct a high school for defendant for the total price of $772,133.60, and to deliver the same on February 7, 1925, “no allowance to be made for bad weather,”

Adding $5,269.88 for extras, and deducting $3,308.74 foi' certain allowances, about which there is no dispute, the net contract price amounted to $774,094.74, on account of which plaintiffs have received $753,607.83, leaving a balance due them on the contract price of $20,486.91, which they claim in this suit, and over which there is no controversy.

I.

In addition to the balance aforesaid, plaintiffs also claim: (a) $1,565 as the cost of heating the building during the course of construction,- and (b) $2,868- as the cost of relay.ing rubber tile flooring, which, “owing to the climatic and unnatural conditions prevailing at the time,” did not adhere to the cement floor of the building, and had to be relaid.

There is no merit in either of these claims ; (a) the contract does not provide that the owner should furnish heat for the building, and the evidence does not establish that it is the custom for the owner to do so; and,- in the absence of contract or custom, it was incumbent on the contractor, if heat was necessary during the course of construction, to supply that heat himself in the same way as it was incumbent on him to supply all tools, implements, machinery, and power necessary or proper for carrying out of his contract; and (b) the risk of “climatic and unnatural conditions” was that of the contractor. Picard Const. Co. v. Board of Com’rs Caddo Levee Dist., 161 La. 1002, 109 So. 816. It is not shown that the failure of the rubber tile flooring to adhere to the cement floors was in any way due to the fault of the owner.

II.

The contract provided, as above said, that the building should be completed on February 7, 1925; that the contractors should receive $150 per day for completing it in advance of that date, and should pay $150 per day for each day’s delay after that date.

It is this provision of the contract which gives rise to the real controversy in this case. The defendant contends that the building was not completed until September 1, 1925, and that plaintiffs owe it $150 per day for the 205 days intervening between February 7th and September 1st; and the plaintiffs claim that they owe nothing, (1) because the .delays were due to the fault of the defendants in not furnishing certain fixtures in time, and in not making timely application for electric current with which to test the various apparatus installed; and (2) because defendant had *203 granted them an extension of 60 days, and had led them to understand that no penalties would be claimed for any delays beyond that time, whereby plaintiffs proceeded with much less celerity than they otherwise would have used, it being then apparent that the building would not be needed until the beginning of the next school term (September).

III.

■ Our conclusion is: (a) That defendants were not responsible for the failure of plaintiffs to complete the building by February 7, 1925; (b) that plaintiffs were granted an extension of 60 days in which to complete the building, expiring April 8, 1925; (c) that plaintiffs, without any fault on the part of defendant, failed to complete and deliver the building until June 11, 1925, and are therefore liable for $150 per day for the 63 days intervening between April 8th and June 11th; and (d) that defendants led plaintiffs to believe that they would waive, and in fact did waive, all penalties from and after June 11th, when the building was substantially, though not entirely, completed, and when it was accepted by defendants.

These conclusions accord with those of the trial judge, except as to item (d). He charged the defendant with the delays from June 11th to September 1st, being 82 days. Hence his conclusion was that, although defendant owed plaintiff $20,486.91 as the balance of the contract price, yet plaintiff owed defendant $21,750 for the 145 days between April 8th and September 1st; and accordingly he gave judgment for defendant and against plaintiff for the difference, i. e., for $1,263.09. But, according to our view, defendant owes plaintiff $20,486.91, balance of contract price, whilst plaintiff owes defendant only $9,450 for 63 days’ delay between April 8th and June 11th; so that plaintiff should have judgment against defendant for the difference, i. e., $11,036.91.

IV.

The reasons for our conclusions are as follows: (a) Plaintiffs have adduced some testimony to show that their failure to complete the building by February 7th was due to the faults and delays of defendant. But this is simply an afterthought. As early as November it was apparent that plaintiffs would not finish the building on time, and the defendants had abandoned the idea of using it in February; but plaintiffs did not then complain that the fault lay with defendant. On the contrary, on January 30th, plaintiffs wrote defendant simply as follows:

“ * * * As you are not going to use the building for this term and have' none of your equipment to put in at present, we would appreciate very much if you will allow us an extension on our time, as we think you would benefit by such, knowing the conditions ás you do.”
(b) On March 10th the defendant’s architect wrote plaintiff as follows:
“This is to advise you that you will be allowed an extension of 60 days from February 7th, 1925, * * * for the completion of all interior painting. This extension applies only to painting as above stipulated.”

As the building could not be completed or delivered or used without the painting, it follows that the above extension, however worded, had the effect of extending the time for completion and delivery of the whole building. Otherwise the alleged extension would be meaningless; for the building was still incomplete in other respects, and, if plaintiffs were to be liable on that account for a penalty of $150 per day, an extension as to painting alone would have been of no use whatever.

(c) Just before the expiration of the 60 days’ extension, two things occurred which entailed an additional delay of 63 days, as aforesaid, before the building was substantially completed and ready for acceptance, to wit: (1) The rubber tile flooring was found to have been improperly laid, and had to be relaid; and (2) the subcontractor for the in *205 terior .painting defaulted, and his work was so unsatisfactory that it had all to he done over.

Some time elapsed before plaintiffs could start this work anew, and it was not until aft&r June 11th that it was satisfactorily completed. This was the chief, if not the sole, cause why the building was not substantially completed before that date, and there is nothing in the evidence tending to show that defendants contributed in any way to the delay thus occasioned, except that plaintiffs’ architect did advise the new subcontractor for the painting that he might take his time and do a good job. But this new job was not sublet until the middle of May, and would have required (and did require) more than 30 days to complete it under any circumstances.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gremillion's Heirs v. Rapides Parish Police Jury
493 So. 2d 584 (Supreme Court of Louisiana, 1986)
Klumpp v. Colonial Pipeline Co.
389 So. 2d 457 (Louisiana Court of Appeal, 1980)
Southern Construction Co. v. Housing Authority
197 So. 2d 628 (Supreme Court of Louisiana, 1967)
Pennington v. Drews
49 So. 2d 5 (Supreme Court of Louisiana, 1949)
Morris Buick Co. v. Ray
43 So. 2d 83 (Louisiana Court of Appeal, 1949)
Anchor Fireproofing Co. v. Stewart-Mcgehee Const. Co.
142 So. 783 (Supreme Court of Louisiana, 1932)
Flanders v. Motor Sales & Service, Inc.
118 So. 387 (Louisiana Court of Appeal, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
115 So. 458, 165 La. 200, 1927 La. LEXIS 1897, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stewart-mcghee-const-co-v-caddo-parish-school-board-la-1927.