F. M. Gabler, Inc. v. Evans Laboratories, Inc.

129 Misc. 911, 223 N.Y.S. 408, 1927 N.Y. Misc. LEXIS 958
CourtNew York Supreme Court
DecidedJune 30, 1927
StatusPublished

This text of 129 Misc. 911 (F. M. Gabler, Inc. v. Evans Laboratories, Inc.) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
F. M. Gabler, Inc. v. Evans Laboratories, Inc., 129 Misc. 911, 223 N.Y.S. 408, 1927 N.Y. Misc. LEXIS 958 (N.Y. Super. Ct. 1927).

Opinion

Levy, J.

Plaintiff was employed by the defendant National Evans Motion Picture Film Laboratories, Inc., to install certain fire safety devices in its laboratories under a written contract for a total price of $1,530, the work to be paid for upon completion of the job. Before the work was finished a fire destroyed defend[912]*912ant’s plant. Thereafter plaintiff sent a bill for $1,185 claiming a pro rata payment on the following basis: For materials installed, $475; for materials taken to defendant’s premises, but not installed, $340; for materials ready to be supplied, but not delivered to or installed upon defendant’s plant, $370. In the action brought for the amount of the bill, the jury rendered a verdict for the full amount in favor of the plaintiff, together with $100 interest. The appeal is taken by the defendant named, the action against Evans Laboratories, Inc., having been discontinued. Three important questions arise upon the issues: (1) Was the defendant at all hable upon plaintiff’s failure to complete an entire contract? (2) If plaintiff was entitled to any compensation, was the amount to be limited to the value of the material actually installed upon the building? (3) Was the allowance of interest proper?

The genera] rule is well established that where one contracts to build an entire structure upon the land of another, and it is destroyed by fire before completion, he is not only unable to collect any compensation for what he has done, but unless he replaces the building he is hable for damages for non-performance. (Tompkins v. Dudley, 25 N. Y. 272.) In that case the owners of the land were also allowed to recover back moneys they had advanced on the contract. The situation here, however, is different, it being well settled that when work is to be done under a contract on a chattel or building which is not wholly the property of the contractor, or for which he is not solely accountable, as where repairs are to be made on the property of another, the agreement on both sides is upon the implied condition that the chattel or building shall continue in existence, and the destruction of it without the fault of either of the parties will excuse performance of the contract, and leave no right of recovery of damages in favor of either against the other. Taylor v. Caldwell, 3 B. & S. 826. * * * Dexter v. Norton, 47 N. Y. 62. Walker v. Tucker, 70 Ill. 527. In such cases, from the very nature of the agreement as applied to the subject matter, it is manifest that, while nothing is expressly said about it, the parties contemplated the continued existence of that to which the contract relates. The implied condition is a part of the contract, as if it were written into it, and by its terms the contract is not to be performed if the subject matter of it is destroyed, without the fault of either of the parties, before the time for complete performance has arrived.” (Butterfield v. Byron, 153 Mass. 517, 519.)

In commenting upon this principle, Judge Vann said, in Dolan v. Rodgers (149 N. Y. 489, 494): “ The effect of the rule is to excuse both parties from further performance of the contract without [913]*913giving to either the right to recover damages for the part not performed. * * * In England the rule seems to go no farther in its effect than to reheve both parties from any obligation under an entire contract, with reference either to the future or the past. In this country, however, there may be a pro rata recovery for part performance by the one party, at least where what has been done is of benefit to the other. (Jones v. Judd, 4 N. Y. 412; Cleary v. Sohier, 120 Mass. 210; Butterfield v. Byron, 153 Mass. 517; Cook v. McCabe, 53 Wis. 250, 258; Schwartz v. Saunders, 46 Ill. 18; Hollis v. Chapman, 36 Tex. 1; Niblo v. Binsse, 1 Keyes, 476.)”

In the Niblo case plaintiff’s assignor agreed to install certain steam engines and heating apparatus upon the hotel of defendant’s testator. When the work was about nine-tenths completed the building was destroyed by fire. The court allowed compensation for the pro rata work done, less payments which had already been made to the contractors. Recovery was permitted on this principle: “ If one party agrees with another to do work upon his house, or other building, the law implies that the employer is to have the building in existence upon which the work contracted for may be done. It is necessarily a part of the contract on the part of such employer, whether it is specified in it in terms or not. Here the defendant’s testator failed to provide and keep the building till the work could be completed, and thus, and thus only, was performance prevented.

“It is nothing whatever to the case to say that the building was not destroyed through his agency or fault. That fact is no test of the liability in an action like this. It would not excuse or shield the defendants from liability even were the action to recover as damages the profits which might have been made on that part of the work the performance of which was prevented. The destruction was not caused by the act of God, as appears by the facts found; and a default from any other cause will not excuse nonperformance.” (Niblo v. Binsse, supra, 479.)

The language of the last paragraph is perhaps too sweeping and not in accord with later authority. It is undoubtedly true that the pro rata value of the work was properly allowed. It is also true that the element of profit on the portion completed is an allowable item, but not profits on the uncompleted portion. As was said in Hayes v. Gross (9 App. Div. 12, 16; affd., on the opinion below, 162 N. Y. 610): “ We think Niblo v. Binsse, upon which the learned referee relied, was correctly decided, but, with due respect, we submit that the decision was placed upon untenable ground. The court said that it placed its decision upon the ground [914]*914that the contractor was prevented from performing his contract by the default of the owner in failing to keep on hand and in readiness the building in which the work was to be done, and that the owner was in default whether the building was destroyed with or without fault on his part. The case shows that the building was destroyed without fault of either owner or contractor. If the defendant was without fault in the destruction of his building, it is difficult to see how he was in default for not keeping it on hand.

“ In the Niblo case, as in the one under review, we think the destruction of the building prevented and excused the defendant from keeping it on hand, and that neither party could recover damages of the other upon account of the breach of the contract thereby caused.”

The court, therefore, granted to the plaintiff the value of the labor and material actually furnished, together with his proportionate profit up to the time of the fire. It refused, however, to allow for materials which he had procured in order to place them in or upon the building, but which he had not actually so placed at the time of the fire. These items were eliminated, because they had not been added to the building, and, therefore, did not become defendant’s property. That case is urged to sustain defendant’s contention that it is liable neither for materials never taken to its premises, nor perhaps for such as were placed there, but not installed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tompkins v. . Dudley
25 N.Y. 272 (New York Court of Appeals, 1862)
Dolan v. . Rodgers
44 N.E. 167 (New York Court of Appeals, 1896)
Mansfield v. . N.Y.C. H.R.R.R. Co.
21 N.E. 735 (New York Court of Appeals, 1889)
Prager v. New Jersey Fidelity & Plate Glass Insurance Co. of Newark
156 N.E. 76 (New York Court of Appeals, 1927)
Excelsior Terra Cotta Co. v. . Harde
73 N.E. 494 (New York Court of Appeals, 1905)
Hayes v. . Gross
57 N.E. 1125 (New York Court of Appeals, 1900)
Dexter v. . Norton
47 N.Y. 62 (New York Court of Appeals, 1871)
Cook v. McCabe
10 N.W. 507 (Wisconsin Supreme Court, 1881)
Hollis v. Chapman
36 Tex. 1 (Texas Supreme Court, 1872)
Hayes v. Gross
9 A.D. 12 (Appellate Division of the Supreme Court of New York, 1896)
H. G. Vogel Co. v. Reinhardt
171 A.D. 907 (Appellate Division of the Supreme Court of New York, 1915)
H. G. Vogel Co. v. Reinhardt
91 Misc. 60 (Appellate Terms of the Supreme Court of New York, 1915)
Van Rensselaer v. Jewett
2 N.Y. 135 (New York Court of Appeals, 1849)
Jones v. Judd
4 N.Y. 412 (New York Court of Appeals, 1850)
Niblo v. Binsse
1 Keyes 476 (New York Court of Appeals, 1864)
Cleary v. Sohier
120 Mass. 210 (Massachusetts Supreme Judicial Court, 1876)
Butterfield v. Byron
12 L.R.A. 571 (Massachusetts Supreme Judicial Court, 1891)
Young v. City of Chicopee
72 N.E. 63 (Massachusetts Supreme Judicial Court, 1904)
Schwartz v. Saunders
46 Ill. 18 (Illinois Supreme Court, 1867)
Walker v. Tucker
70 Ill. 527 (Illinois Supreme Court, 1873)

Cite This Page — Counsel Stack

Bluebook (online)
129 Misc. 911, 223 N.Y.S. 408, 1927 N.Y. Misc. LEXIS 958, Counsel Stack Legal Research, https://law.counselstack.com/opinion/f-m-gabler-inc-v-evans-laboratories-inc-nysupct-1927.