Burgess Mining & Construction Corp. v. City of Bessemer

312 So. 2d 24, 294 Ala. 74, 1975 Ala. LEXIS 1146
CourtSupreme Court of Alabama
DecidedMarch 6, 1975
DocketSC 688
StatusPublished
Cited by4 cases

This text of 312 So. 2d 24 (Burgess Mining & Construction Corp. v. City of Bessemer) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Burgess Mining & Construction Corp. v. City of Bessemer, 312 So. 2d 24, 294 Ala. 74, 1975 Ala. LEXIS 1146 (Ala. 1975).

Opinion

HEFLIN, Chief Justice.

Appellant-plaintiff Burgess Mining & Construction Corp. (Contractor) appeals from a judgment rendered in favor of the appellee-defendant City of Bessemer, Alabama, (City) on three counts of a complaint on which the Contractor sought to recover from the City the sum of $35,550.-94 for performing additional work under a contract to construct an airport for the City.

On November 25, 1969, the City entered into a contract with A. E. Burgess Company, Inc. (whose name was later changed to Burgess Mining & Construction Corporation) for the construction of an airport on a unit-o f-work basis to be performed at a unit price, the total of which was estimated to be $571,221.40. The case was submitted to the trial court on the contract between the parties and other documents agreed to in open court without any oral testimony. By agreement of the parties, judgment was awarded the Contractor on Counts 3 through 5 in the sum of $2,938.00 plus interest. The trial court found against the Contractor on Counts 1, 2, and 6, as last amended, which claimed damages for breach of contract and for work and labor done. The trial court overruled the Contractor’s motion for a new trial. The appeal before this court is pursuant to Rule 26 of the Revised Rules of Practice in the Supreme Court (abridgment of record by agreement rule) with the record being composed of an agreed statement of evidence and facts along with three documentary exhibits.

The review on this appeal is limited to the Contractor’s claim of $35,550.94 plus interest, which is the subject of Counts 1, 2, and 6 of the complaint as amended. The parties have agreed that the basis for this claim involves only matters dealing with the construction of the sub-base course of the runway of the airport. During construction of the sub-base course, it became necessary for the Contractor to obtain materials (sand-clay, sand-clay gravel, disintegrated granite, top-soil, and bonding and blending filler) from places outside the project area to bring it up to the specifications. The amount to which the Contractor was entitled is not disputed. The only issue is whether the Contractor is entitled to recover the cost of this outside material.

*76 The Contractor contends that the City-warranted and provided in the contractual documents that the Contractor had the right to use excavated material on the project site to build the sub-base course for the runway, and that there were sufficient materials at the project site to build it according to the specifications. The Contractor asserts that such warranties and provisions were breached when the material in the project area did not comply with the specifications and it was required to obtain material from sources outside the project area.

The Contractor further asserts that its Exhibit 3, a single sheet entitled “Mechanical Analysis and Classification of Representative Examples,” contained positive statements that there was sub-base material in the project area of a quality and quantity sufficient to meet the specifications for the sub-base course. This exhibit appeared to represent a mechanical analysis of soil material obtained by borings in the project area as well as a classification of representative soil samples. At the bottom of this exhibit appear handwritten figures and words which the Contractor refers to as “calculations.” The Contractor further contends that these “calculations” showed that 7,123 cubic yards of material were required to build the sub-base course, and that 110,000 cubic yards of material on the project site met the specifications and were available for this purpose. The Contractor’s position is that in the contractual documents, which included Exhibit 3, there were positive assertions that should be interpreted to mean “if you use the material in the project area for the sub-base course, it will meet the specifications and sufficient material is available at the project site.” In addition to the alleged positive statements in the said Exhibit 3 that there was sub-base material of sufficient quantity and quality in the project area, the Contractor asserts that there were certain special provisions added to the contract which supported its position. Such provisions are as follows:

“The Contractor may secure topsoil and subbase material from within the project limits * * *
* * Hí * * *
“At the direction of the Engineer, certain designated zones of the cuts, or material sources to be excavated, which afford the more suitable soils for subgrade under paved areas, shall be reserved
******
“The Contractor may obtain this material from within the construction limits of the project. * * * ”

The Contractor further asserts that the word “may” in these provisions should be construed as “shall” or “must” since this was the intention of the parties. While the normal use of the word “may” connotes a permissive character, the word can on occasion have a mandatory nature. Whether a permissive or mandatory construction is applicable depends on the apparent intention as gathered from the context, considering the whole instrument in which it is used. See 57 C.J.S. at p. 456.

The City, for one of its answers to the Contractor’s position, points out that Section 20-04 of the standard specifications provided:

“The bidder is required to examine carefully the site of the proposed work, the proposal, plans, and specifications, and contract forms. He shall satisfy himself as to the character, quality, and quantities of work to be performed, materials to be furnished, and as to the requirements of these specifications, special provisions, and contract. The submission of a proposal shall be prima facie evidence that the bidder has made such an examination.
“Any information shown on the plans as to the soil or material borings or tests of existing materials is for the convenience *77 of the contractor. The information is not guaranteed, and no claims for extra work or damages will be considered, if it is found during construction that the actual soil or material conditions vary from those indicated by the borings.”

The Contractor asserts in reply that when plans and specifications are furnished by an owner which show positively that the owner’s analysis of earth borings in the project area meets the specifications, then a Contractor is not required to make investigations or tests to determine whether material meets the specifications for the construction. A number of federal cases, including United States Supreme Court decisions and decisions of the Court of Claims, are cited in support this position. United States v. Spearin, 248 U.S. 132, 39 S.Ct. 59, 63 L.Ed. 166 (1918), is one of the cases cited by the Contractor. In that case an unforeseen hazard appeared while the work was being performed according to the plans and specifications, resulting in the Contractor’s refusal to proceed further unless the government paid him to remove the hazard. The government refused to pay and cancelled the contract. The Court awarded- the Contractor the amount due for work completed plus the profit he would have earned had he completed the work. In reaching this conclusion, the Court said:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Regions Bank v. BP P.L.C.
200 So. 3d 1 (Supreme Court of Alabama, 2016)
RLS Associates, LLC. v. United Bank of Kuwait PLC.
380 F.3d 704 (Second Circuit, 2004)
Lawrence v. Farm Credit System Capital Corp.
761 P.2d 640 (Wyoming Supreme Court, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
312 So. 2d 24, 294 Ala. 74, 1975 Ala. LEXIS 1146, Counsel Stack Legal Research, https://law.counselstack.com/opinion/burgess-mining-construction-corp-v-city-of-bessemer-ala-1975.