Condon-Cunningham, Inc. v. Day

258 N.E.2d 264, 22 Ohio Misc. 71, 51 Ohio Op. 2d 144, 1969 Ohio Misc. LEXIS 234
CourtCuyahoga County Common Pleas Court
DecidedDecember 15, 1969
DocketNo. 853345
StatusPublished
Cited by16 cases

This text of 258 N.E.2d 264 (Condon-Cunningham, Inc. v. Day) is published on Counsel Stack Legal Research, covering Cuyahoga County Common Pleas Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Condon-Cunningham, Inc. v. Day, 258 N.E.2d 264, 22 Ohio Misc. 71, 51 Ohio Op. 2d 144, 1969 Ohio Misc. LEXIS 234 (Ohio Super. Ct. 1969).

Opinion

McMahon, J.

On March. 29, 1962, Condon-Cunning-ham, Inc., and M. F. Yelotta & Sons, Inc., a joint venture (hereinafter referred to as plaintiffs), entered into a contract with William P. Day, Henry W. Speeth and Frank M. Gorman, constituting the Board of County Commissioners (hereinafter referred to as defendant), to make certain highway improvements in Cuyahoga County, involving among other things the construction, improvement and partial relocation of Roekside Road from Brecks-ville Road to Turney Road.

The Agreement, Proposal and Contract Bond for this project (Plffs’ Ex. 1) states what was incorporated by reference into the Contract (at Notice Sheet No. 2):

“The approved plans (Plffs’ Exs. 2, 2A, 2B) together with any special specifications for this project (Plffs’ Ex. 1) as well as the construction and material specifications (Plffs’ Ex. 3) together with the general clause and covenants in effect at the time the contract is entered into will also be incorporated by reference as fully and completely as if bound in the contract and made a part, thereof.” (Parentheses and contents thereof added.)

In addition to the above referred to items specifically made a part of the contract, Soil and Foundation Investigation Reports (Jewell Report) for this project were made available as a source of supplementary information. These reports are summarized as Soils — General Notes (Plffs’ Ex. 1 between the proposal and special specifications) with said summary containing the following statements:

“In addition to the soil profile there are on file * * * copies of Soil and Foundation Investigation Reports for this project.
“The S. & F. I. R. were prepared as a guide for design features incorporated in the project.
“The information contained in these reports is available for review by the contractor. The reports are not a part of the contract but are available as a source of supplementary information.”

Soil profiles (Plffs’ Exs. 4 and 5) were also made available to plaintiffs. Plffs’ Ex. 5 contains the following note.

[73]*73“The information shown by this subgrade profile was secured for the use of the County of Cuyahoga and is not to bo construed as a part of the plans governing the construction of the project.”

Plaintiffs state in their first cause of action that they prepared and submitted their bid for this project in reliance upon facts as set forth in the Proposals, Plans and Specifications prepared or caused to be prepared by the defendant and made available to prospective bidders for the purpose of preparing and influencing their bids. Plaintiffs further state that during the progress of the work required by the contract plaintiffs discovered certain misstatements of facts in the Proposals, Plans and Specifications, all of which were either known or should have been known by defendant: i. e. (1) as to the quality and quantity of materials to be excavated within the right-of-way; (2) that defendant had not made reasonable and sufficient soil tests and geological studies of the right-of-way areas. As a result of the material misstatements of fact plaintiffs were required to waste certain material as unsuitable, shown as suitable, and to replace said wasted material. Defendant admits the preparing of the Proposals, Plans and Specifications but denies all other material allegations.

Plaintiffs for their second cause of action restate the statements made under their first cause of action and ask for relief on the theory of breach of contract, in that:

(1) defendant failed to provide plaintiffs with suitable and sufficient material for placement within the embankment ;

(2) defendant failed to provide plaintiffs with borrow area when defendant knew or should have known that the called for excavation was unsuitable and insufficient to complete the embankment;

(3) defendant made arbitrary, etc., demands upon plaintiffs during the performance of the work. Plaintiffs further state that they elected not to rescind the contract, but chose to complete their performance under protest. Defendant generally denies these allegations.

For their third cause of action plaintiffs state they were required to perform certain excavation work in addition [74]*74to that contemplated by the. parties and set forth in the contract, and that they have not been compensated for additional material furnished in connection therewith. Defendants admit that plaintiffs were in some instances instructed to remove soft subgrade and to replace the area so excavated with suitable material, but further state that plaintiff was fully compensated for all excavation and all replacement material furnished in connection therewith.

For their fourth cause of action plaintiffs state that subsequent to the execution of the contract but prior to the time plaintiffs were authorized to proceed, third parties removed over 15,000 cubic yards of material from the Kaiser-Nelson Cut. Plaintiffs further state that it was in the contemplation of the parties that the plaintiffs would have the right to use this material on the job. Plaintiffs claim they had to bring in material from outside the right-of-way sources to make up the amount removed.

Defendant admits the removal and that it took place prior to the time plaintiffs were authorized to proceed but state further that the plans did not guarantee that the same conditions would be present when plaintiffs would be advised to proceed, that the plaintiffs at the time of commencing work knew said material had been removed but made no claim or protest, and that the removal of material was not essential to nor approved for completion of the contract.

Plaintiffs, as a fifth cause of action, state that they have fully performed and completed their part of the contract and that the defendant has accepted said work as being satisfactory; that a final estimate of the amount due plaintiffs was arrived at but that said amount is being withheld by the defendant until plaintiffs release defendant from any and all claims and demands arising out of the contract; that this demand is arbitrary, etc., and the refusal by defendant constitutes a breach of contract; that plaintiffs are entitled to said $35,000, plus interest. Defendant generally denies plaintiffs’ claim under the fifth cause of action.

[75]*75We will treat causes of action 1 and 2 as one cause of action as each one asks for the same damages and deals with the same matters.

The first cause of action seems to sound in tort and the second cause of action sounds in contract which is the one which seems more logical to the court.

The principal issue here is whether the contractors could rely upon information given to them and also other information made available to them concerning the moisture content of the soil found in the Kaiser-Nelson Cut. This information was gained through borings made by a Columbus engineer by the name of Jewell, who made these borings for and on behalf of Cuyahoga County in connection with this project.

As to plaintiffs’ first and second cause of action, the statement most directly in question is located under the first Rockside Road heading on page 4 of the “Soils-General Notes”:

‘ ‘ The stiff to very stiff silty clay deposits were generally at or just above the optimum moisture content.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Absher Construction Co. v. Kent School District No. 415
890 P.2d 1071 (Court of Appeals of Washington, 1995)
Marra Constructors, Inc. v. Cleveland Metroparks System
612 N.E.2d 806 (Ohio Court of Appeals, 1993)
Midwest Dredging Co. v. McAninch Corp.
424 N.W.2d 216 (Supreme Court of Iowa, 1988)
Thatcher Engineering Corp. v. Bihlman
473 N.E.2d 1022 (Indiana Court of Appeals, 1985)
Berkel & Co. Contractors v. Providence Hosp.
454 So. 2d 496 (Supreme Court of Alabama, 1984)
Mayor of Columbus v. Clark-Dietz & Associates-Engineers, Inc.
550 F. Supp. 610 (N.D. Mississippi, 1982)
S & M Constructors, Inc. v. City of Columbus
434 N.E.2d 1349 (Ohio Supreme Court, 1982)
Raymond International, Inc. v. Baltimore County
412 A.2d 1296 (Court of Special Appeals of Maryland, 1980)
Joseph F. Trionfo & Sons, Inc. v. BD. OF EDUC. OF HARFORD CTY.
395 A.2d 1207 (Court of Special Appeals of Maryland, 1979)
Jacksonville Port Auth. v. Parkhill-Goodloe Co.
362 So. 2d 1009 (District Court of Appeal of Florida, 1978)
Robert E. McKee, Inc. v. City of Atlanta
414 F. Supp. 957 (N.D. Georgia, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
258 N.E.2d 264, 22 Ohio Misc. 71, 51 Ohio Op. 2d 144, 1969 Ohio Misc. LEXIS 234, Counsel Stack Legal Research, https://law.counselstack.com/opinion/condon-cunningham-inc-v-day-ohctcomplcuyaho-1969.