Marra Constructors, Inc. v. Cleveland Metroparks System

612 N.E.2d 806, 82 Ohio App. 3d 557, 1993 Ohio App. LEXIS 15
CourtOhio Court of Appeals
DecidedJanuary 19, 1993
DocketNo. 63855.
StatusPublished
Cited by38 cases

This text of 612 N.E.2d 806 (Marra Constructors, Inc. v. Cleveland Metroparks System) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marra Constructors, Inc. v. Cleveland Metroparks System, 612 N.E.2d 806, 82 Ohio App. 3d 557, 1993 Ohio App. LEXIS 15 (Ohio Ct. App. 1993).

Opinion

Krupansky, Judge.

The appeal and cross-appeal sub judice stem from a construction contract arbitration award confirmed in part and vacated in part by the common pleas court. Defendant-appellant the Board of Park Commissioners of the Cleveland Metropolitan Park District (“Metroparks”) appeals with two assignments of error from the order of the common pleas court denying its motion to vacate the award in its entirety. Plaintiff-appellee Marra Constructors, Inc. (“Marra”) cross-appeals with four assignments of error from the order of the common pleas court vacating the arbitrator’s award of interest and the award of post-judgment interest by the common pleas court from September 10, 1991 to October 7, 1991. 1

The parties entered into a contract for certain improvements on the Chippewa Creek Ford in the Metroparks Brecksville Reservation (the “Project”) at an estimated cost of $206,500 on May 23, 1990. The Project involved driving a total of twenty-one steel piles, construction of culvert footers, installation of precast box culverts and paving a roadway surface on the structure over the creek. The Project commenced in June 1990 but encountered several delays due to improper placement of the footers, the unanticipated inspection of the steel piles following installation and inclement weather.

Project drawings prepared by Richland Engineering, Inc. (“Richland Engineering”), an independent engineer retained by Metroparks, and used by Marra contained an erroneous placement of the footers and resulted in an improper installation of the footers. Marra was likewise unable to proceed with construction of the Project while Metroparks obtained an independent *560 review of the adequacy of the pilings following their installation by Marra. The Project was ultimately completed in October 1990.

Following completion of the Project, Marra submitted the following five claims to arbitration to recover $95,233.06 in costs and expenses attributed to the delays, viz.: (1) $65,252.19 due to dimensional errors in the plans regarding the location of the footers and inspection of the steel pilings following installation; (2) $11,932.43 due to an alleged “ten year flood” occurring on September 7, 1990; (3) $10,931.53 resulting from excessive rain in July 1990; (4) $3,234.61 for additional paving costs; and (5) $3,882.30 for inspection costs. 2 Marra also requested $6,992.12 in interest on the $95,233.06 in costs and expenses for a total amount requested of $102,225.18.

The arbitrator issued a twenty-five page decision and judgment entry on September 10, 1991 after conducting a two-day hearing where the parties presented testimony from fourteen witnesses and numerous exhibits and photographs. The arbitrator found in favor of Marra on the first four of the above claims and denied the fifth claim. The arbitration award rendered judgment in favor of Marra in the total amount of $81,962.91 as follows, viz.: (1) $60,087.67 in connection with the footer plan error and pile inspection delay claim, (2) $3,093.60 on the “ten year flood” claim, (3) $9,937.75 resulting from the excessive rain in July 1990 claim, and (4) $3,234.61 on the additional paving claim, each with ten percent interest for the two-hundred-sixty-eight-day period prior to the commencement of the arbitration on July 25, 1991. The arbitration award did not grant Marra its requested ten percent profit on the disputed items and awarded a total of $81,962.91, $20,262.27 or approximately twenty percent less than the amount sought by Marra.

Marra thereafter filed an application to confirm the arbitration award in the common pleas court and Metroparks filed a motion to vacate the award. Neither party filed a verbatim transcript, statement of the evidence or other material equivalent to a recitation of all the evidence presented by the parties during the arbitration proceedings. The common pleas court conducted a hearing where the parties presented legal arguments supporting their respective motions, and subsequently granted Marra’s motion to confirm the award in part and Metropark’s motion to vacate the award in part. The order of the common pleas court confirmed the award in favor of Marra on the first four claims but vacated the arbitrator’s award of two hundred sixty-eight days’ interest on the sums awarded. The common pleas court thereafter granted *561 Marra’s motion for statutory interest on the award limited to the period from the date of the arbitration award, September 10, 1991 to October 7, 1991.

Metroparks filed a notice of appeal from the order of the common pleas court denying its motion to vacate the award in its entirety raising two assignments of error. Marra responded by filing a timely cross-appeal from the orders of the common pleas court vacating the award of interest on the sums awarded by the arbitrator and granting limited statutory post-judgment interest raising four assignments of error.

The parties first two assignments of error on appeal and cross-appeal are related and shall be discussed collectively. Appellant Metropark’s first and second assignments of error on appeal follow:

“I. The trial court erred in overruling Metroparks’ motion to vacate and granting Marra’s application to confirm the arbitration award as to claim No. 1.
“II. The trial court erred in overruling Metroparks’ motion to vacate and granting Marra’s application to confirm the arbitration award as to claim Nos. 2 and 3.”

Appellee and cross-appellant Marra’s first and second assignments of error on cross-appeal argue the contrary as follows:

“I. The arbitrator did not exceed his authority in determining that Metro-parks was responsible for delay damages arising out of either dimensional errors in drawings prepared by its engineer or delays caused by unnecessary tests.
“II. The arbitrator did not exceed his authority in awarding Marra damages for claims number two and three arising out of delays caused by a ten year flood and excessive rains.”

Metroparks contends the common pleas court erred in failing to vacate the arbitration award in its entirety under R.C. 2711.10(D), since the arbitrator exceeded his authority by disregarding contract provisions and interpreting contract provisions contrary to their “plain meaning.” Marra argues to the contrary that the common pleas court properly confirmed this portion of the award under R.C. 2711.09, since the arbitrator properly exercised his authority in rendering the award.

The parties first assignments of error relate to delay caused by errors in the Richland Engineering Project drawings indicating the improper location of the footers used to construct the roadway. The drawings indicated the distance between the faces of the footers should be twenty-four feet seven inches, whereas the distance should have been measured to the interior face of the respective culvert legs. Marra apparently placed the footers in accordance *562 with the Project drawings, which necessitated modification of the remainder of the Project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reynolds v. M/I Homes of Cent. Ohio, L.L.C.
2025 Ohio 5818 (Ohio Court of Appeals, 2025)
Nye v. DeLille Oxygen, Inc.
2021 Ohio 4364 (Ohio Court of Appeals, 2021)
City of Cleveland v. Fraternal Order Police
103 N.E.3d 235 (Court of Appeals of Ohio, Eighth District, Cuyahoga County, 2017)
Dodge v. Dodge
2017 Ohio 7087 (Ohio Court of Appeals, 2017)
Teamsters Local Union No. 436 v. Cuyahoga Cty.
2012 Ohio 5289 (Ohio Court of Appeals, 2012)
Hugenberg v. Huntington Bancshares, Inc.
2012 Ohio 3344 (Ohio Court of Appeals, 2012)
Parma v. Parma Fire Fighters Assn. Local 639
2012 Ohio 932 (Ohio Court of Appeals, 2012)
Orwell Natural Gas Co. v. PCC Airfoils, L.L.C.
937 N.E.2d 609 (Ohio Court of Appeals, 2010)
Miller v. Management Recruiters International, Inc.
906 N.E.2d 1162 (Ohio Court of Appeals, 2009)
Buchholz v. W. Chester Dental Group, Ca2007-11-292 (10-13-2008)
2008 Ohio 5299 (Ohio Court of Appeals, 2008)
Lauro v. Twinsburg, Unpublished Decision (12-12-2007)
2007 Ohio 6613 (Ohio Court of Appeals, 2007)
Wachovia Securities, Inc. v. Gangale
125 F. App'x 671 (Sixth Circuit, 2005)
Northern Ohio Sewer Contractors, Inc. v. Bradley Development Co.
825 N.E.2d 650 (Ohio Court of Appeals, 2005)
Hogue v. Sadler, Unpublished Decision (11-9-2004)
2004 Ohio 6132 (Ohio Court of Appeals, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
612 N.E.2d 806, 82 Ohio App. 3d 557, 1993 Ohio App. LEXIS 15, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marra-constructors-inc-v-cleveland-metroparks-system-ohioctapp-1993.