Northern Ohio Sewer Contractors, Inc. v. Bradley Development Co.

825 N.E.2d 650, 159 Ohio App. 3d 794, 2005 Ohio 1014
CourtOhio Court of Appeals
DecidedMarch 10, 2005
DocketNo. 84693.
StatusPublished
Cited by16 cases

This text of 825 N.E.2d 650 (Northern Ohio Sewer Contractors, Inc. v. Bradley Development Co.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northern Ohio Sewer Contractors, Inc. v. Bradley Development Co., 825 N.E.2d 650, 159 Ohio App. 3d 794, 2005 Ohio 1014 (Ohio Ct. App. 2005).

Opinion

Frank D. Celebrezze Jr., Judge.

{¶ 1} The respondents/appellants, Bradley Development Company, Inc., and Village Builders, Ltd. (collectively, “Bradley”), challenge the decision of the trial court that confirmed an arbitration award in favor of the elaimant/appellee, Northern Ohio Sewer Contractors, Inc. (“Northern”), regarding a construction- *797 contract dispute. After reviewing the record, the arguments of the parties, and the applicable law, we affirm the decision of the trial court.

{¶ 2} On March 23, 1999, Bradley and Northern entered into a contract entitled Sewer and Water Main Agreement, wherein Northern agreed to install storm sewers, sanitary sewers, and water mains for Bradley’s Village Square Condominium project in Wellington, Ohio. The contract called for the sewers and water mains to be installed in strict compliance with engineering specifications that were revised several times. The contract contained a valid and binding arbitration clause.

{¶ 3} The village engineer, Poggemeyer Design Group, Inc., was concerned that the extra weight of vehicular traffic could break the sewer pipes. In order to comply with the mandates of the village engineer, Northern was required to upgrade the storm sewer from 30 to 36 inches. Northern also claims that Bradley requested additional premium fill outside the pavement areas of the contract. These upgrades were not contemplated in the original proposal. Northern was also required to relocate a fire hydrant.

{¶ 4} A dispute arose between Northern and Bradley regarding the final cost of the contract. Northern claims that the mandatory upgrade of the storm sewer, the addition of extra premium fill, and the relocation of a fire hydrant cost it an additional $51,400 above the already agreed-to contract price. Bradley refused to pay and argues that an agreement was previously reached with Northern regarding the sewer upgrade.

{¶ 5} Bradley contends that Northern stipulated that the total cost of the upgrade would be $27,470, an increase of only $5,226 from the price stated in the original contract. Bradley further claims that the sewer upgrade cost was due to the defective workmanship of Northern in failing to properly compact and backfill under the pavement areas referred to in the contract. Bradley also claims that Northern, by the express terms of the contract, was responsible for providing premium fill regardless of the sewer upgrade.

{¶ 6} On September 14, 2001, Northern filed a demand for arbitration with the American Arbitration Association in accordance with the contract’s arbitration provision. Northern claimed that it had incurred $50,965.31 in expenses for the additional work and materials not contemplated in the original proposal with Bradley. On November 29, 2001, Bradley filed a counterclaim against Northern for $75,000, arguing that Northern had failed to perform on the contract, meet contract specifications, and exercise ordinary care in the performance of its work. Bradley argued that it had been forced to hire additional contractors in order to cure site damages caused by Northern and to fulfill Northern’s contractual obligations.

*798 {¶ 7} On March 7, 2002, an extensive arbitration hearing began that resulted in detailed awards for both Bradley and Northern. The arbitrator determined that the design engineer had increased the size of the storm sewer from 30 to 36 inches to include a larger drainage area. The design engineer had made the storm connections much too shallow, which forced the village engineer to require ductile iron storm laterals. The arbitrator awarded Northern $27,285 for premium fills for storm sewers, sanitary sewers, water mains, and laterals; $4,154 for pipe material; $7,571 for the replacement of a 30-inch sewer line; and $2,090 for an additional fire hydrant; and disallowed a claim of $1,105 for a flush-out valve. Northern was awarded a total of $41,400.

{¶ 8} The arbitrator then awarded Bradley a total of $2,560 on its counterclaims. Bradley received $460 for site cleanup costs, $1,100 for cement soil stabilization of subgrade, and $1,000 for additional premium fill that was required. The net arbitration award favored Northern and amounted to $38,540.

{¶ 9} The procedural history of this case is complex and strained. Originally, Northern filed an order to confirm the arbitration award with the Cuyahoga County Common Pleas Court on April 2, 2002. The case was subsequently transferred to the Lorain County Common Pleas Court, where Bradley filed a motion to vacate the arbitrator’s award. After various issues were resolved in Lorain County, on March 19, 2004, the case was transferred back to Cuyahoga County, where Northern filed another motion to confirm the arbitrator’s award and to consolidate cases. On April 20, 2004, the trial court granted Northern’s motion confirming the arbitrator’s award, while denying Bradley’s motion to vacate.

{¶ 10} It is from that order that Bradley brings this appeal, alleging eight assignments of error for review. 1

Standard of Review

{¶ 11} Ohio public policy encourages the resolution of disputes through arbitration. Kelm v. Kelm (1993), 68 Ohio St.3d 26, 27, 623 N.E.2d 39.

{¶ 12} It is well settled that judicial review of arbitration awards is narrowly circumscribed by R.C. 2711.10 and 2711.11. Huber Hts. v. Fraternal Order of Police (1991), 73 Ohio App.3d 68, 596 N.E.2d 571; Goodyear v. Local Union No. 200 (1975), 42 Ohio St.2d 516, 71 O.O.2d 509, 330 N.E.2d 703, paragraph two of the syllabus. A common pleas court is limited to ascertaining whether fraud, corruption, misconduct, arbitration impropriety, or evident mistake made the award unjust or unconscionable. Russo v. Chittick (1988), 48 Ohio *799 App.3d 101, 548 N.E.2d 314. The trial court has the power to vacate an arbitration award only upon certain enumerated grounds.

{¶ 13} R.C. 2711.10 provides that the trial court may vacate an arbitrator’s award if (A) the award was procured by corruption, fraud, or undue means; (B) there is evident partiality or corruption on the part of the arbitrators, or any of them; (C) the arbitrators were guilty of misconduct in refusing to postpone the hearing, upon sufficient cause shown, or in refusing to hear evidence pertinent to the controversy, or of any other misbehavior by which the rights of any party have been prejudiced; or (D) the arbitrators exceeded their powers or so imperfectly executed them that a mutual, final, and definite award upon the subject matter submitted was not made.

{¶ 14} Under R.C. 2711.10, an error of fact or law by an arbitrator does not provide a basis for vacating an arbitration award. Goodyear, 42 Ohio St.2d at 522, 71 O.O.2d 509,

Related

Colerain Twp. v. AFSCME Ohio Council 8, AFL-CIO, Local 3553
2024 Ohio 1352 (Ohio Court of Appeals, 2024)
U.S. Claims OPCO, L.L.C. v. Wells-Niklas
2023 Ohio 1169 (Ohio Court of Appeals, 2023)
Orange Twp. v. Internatl. Assn. of Fire Fighters Local 3816
2022 Ohio 2757 (Ohio Court of Appeals, 2022)
Cleveland v. Communication Workers of Am., Local 4340
2022 Ohio 2498 (Ohio Court of Appeals, 2022)
Cleveland v. Cleveland Police Patrolmen's Assn.
2016 Ohio 2635 (Ohio Court of Appeals, 2016)
N. Royalton v. Urich
2013 Ohio 2206 (Ohio Court of Appeals, 2013)
Boyd v. Spring Creek Condominium Assn., 08 Ca 00009 (5-6-2009)
2009 Ohio 2206 (Ohio Court of Appeals, 2009)
Marsh v. Deems, 07 Ca 91 (7-7-2008)
2008 Ohio 3430 (Ohio Court of Appeals, 2008)
Selby Gen. Hosp. v. Kindig, Unpublished Decision (7-17-2006)
2006 Ohio 4383 (Ohio Court of Appeals, 2006)
Manuel v. Fort Collins Newspapers, Inc.
631 P.2d 1114 (Supreme Court of Colorado, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
825 N.E.2d 650, 159 Ohio App. 3d 794, 2005 Ohio 1014, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northern-ohio-sewer-contractors-inc-v-bradley-development-co-ohioctapp-2005.