Ford Hull-Mar Nursing Home, Inc. v. Marr, Knapp, Crawfis & Associates, Inc.

740 N.E.2d 729, 138 Ohio App. 3d 174, 2000 Ohio App. LEXIS 2782
CourtOhio Court of Appeals
DecidedJune 22, 2000
DocketCase No. 98 JE 7.
StatusPublished
Cited by25 cases

This text of 740 N.E.2d 729 (Ford Hull-Mar Nursing Home, Inc. v. Marr, Knapp, Crawfis & Associates, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ford Hull-Mar Nursing Home, Inc. v. Marr, Knapp, Crawfis & Associates, Inc., 740 N.E.2d 729, 138 Ohio App. 3d 174, 2000 Ohio App. LEXIS 2782 (Ohio Ct. App. 2000).

Opinion

Waite, Judge.

This timely appeal arises from the decision of the Jefferson County Court of Common Pleas dismissing appellant’s complaint and affirming an arbitrator’s ruling in favor of appellee. For all of the following reasons, this Court affirms the judgment of the trial court.

Ford Hull-Mar Nursing Home, Inc. (“appellant”) is a nursing home located near Yorkville, Ohio, in Jefferson County. After being cited by the Ohio Department of Health for several violations pertaining to, among other things, resident room sizes, appellant began investigating the possibility of renovating its *176 facility. After receiving a brochure from the architectural firm of Marr, Knapp, Crawfis, & Associates, Inc. (“appellee”), representatives of appellant and appellee met sometime in 1990, to further discuss the proposed renovation project. As a result of this meeting, appellee provided appellant with preliminary drawings of the project. These drawings estimated that the cost of construction as designed would range between $361,000 and $409,000.

The Ohio Department of Health regulates the construction and renovation of nursing homes through the certificate of need (“CON”) process. R.C. 3702.51; Ohio Adm. Code 3701-12-232. In order to renovate a nursing home, a party must apply and be approved for a CON. Id. The application requires a detailed description of the project, preliminary architectural drawings and the estimated cost of the project. The ultimate cost of the project may not exceed ten percent of the estimated cost reflected in the CON without facing substantial fines from the Department of Health. Id.

Using the preliminary drawings and cost estimates provided by appellee, appellant applied for, and on June 18, 1992, received, a CON for the proposed project to renovate the nursing home for $471,960.47. The preliminary drawings, estimated costs and the CON were for a ten room, 6,000 square foot, single addition to the existing structure.

After receiving the CON, appellant entered into a written contract with appellee for architectural services on July 22,1992. The contract was a standardized form entitled, “A.I.A. Document B141, Standard Form Agreement Between Owner and Architect.” Of particular relevance to this appeal is Article 7, which provides:

“7.1 Claims, disputes or other matters in question between the parties to this Agreement arising out of or relating to this Agreement or breach thereof shall be subject to and decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association currently in effect unless the parties mutually agree otherwise.
“7.4 The award rendered by the arbitrator or arbitrators shall be final, and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof.”

The events subsequent to the execution of the contract are hotly disputed by the parties. Appellee argues that appellant expanded the scope of the project and directed appellee to begin work on the schematics for a thirty-one bed addition to the existing facility. Appellee maintains that it complied with this directive and to that end provided the schematics and a construction cost estimate of $1.2 million. The record reflects that appellant paid appellee’s invoice for this service. Appellee further maintains that it was unaware of the existence *177 of the CON cost limitations. After various cost adjustments, bidding, and rebidding, this aspect of the project was completed. Appellant was presented with another invoice from appellee for $105,025.28 for this service. Appellee argues that appellant was unable to obtain financing for the project and used this an excuse for refusing to pay appellee’s invoice. As a result of appellant’s refusal to pay, appellee filed a demand for arbitration pursuant to the terms of the parties’ contract, seeking compensation in the amount of $129,147.90.

Appellant’s version of events is markedly different. Appellant argues that it never authorized an expansion of the original project. Appellant maintains that it relied on appellee’s purported expertise in the area of health care facility renovations and that it was unaware of the consequences of any significant deviation from. the limitations contained in the CON. As a result of the unauthorized expansion, appellant alleges that it faced financial penalties from the Department of Health, lost profits, and incurred other damages. Accordingly, appellant answered the demand for arbitration with a counterclaim for breach of contract, negligence, and professional malpractice.

Arbitration commenced on June 25, 1996, and proceeded over a four-day period. Both parties called witnesses and submitted voluminous records and other documents in support of their respective claims and defenses. Appellee sought recovery of its invoice amount of $129,147.90 plus interest, while appellant demanded $500,000 in damages and recision of the contract. On December 26, 1996, the arbitrator issued its decision, awarding appellee $81,000 plus costs.

Upon receipt of the arbitrator’s award, appellant filed an application in the Jefferson County Court of Common Pleas, seeking to vacate and/or modify the arbitration award. This matter was assigned case No. 97-CV-14. On May 5, 1997, appellant also filed a complaint against appellee in the Jefferson County Court of Common Pleas under ease No. 97-CV-269, asserting essentially the same allegations as those contained in its counterclaim in arbitration. Appellee filed a motion to confirm the arbitration award on April 28, 1997. On November 25, 1997, the trial court consolidated the two cases, confirmed the arbitration award and dismissed appellant’s complaint with prejudice. It is this judgment of the trial court that forms the basis of the present appeal.

In its first assignment of error, appellant argues:

“The lower court erred to the prejudice of appellant in overruling its application to vacate or modify the arbitration award and in confirming the arbitration award.”

At the onset, this court must observe that appellant’s argument in support of this assignment of error is based entirely upon the premise that appellee breached the contract at issue here, was negligent in its performance and *178 fraudulently induced appellant to enter into the contract. Further, appellant assumes that the arbitrator erred by not reaching these conclusions and that the trial court erred in confirming the arbitrator’s decision. This argument includes comprehensive citations to relevant portions of the transcripts of the arbitration hearing and numerous references to exhibits entered into evidence before the arbitrator. Read as a whole, appellant is arguing that the arbitrator’s decision finding appellant liable to appellee for $81,000 was against the manifest weight of the evidence.

Appellant’s argument, however, ignores the fact that this case is procedurally distinct from the usual appellate review of judgments from a lower court of law. Rather, this matter presents an appeal of an award pursuant to binding arbitration proceedings contemplated in the language of the contract each of the parties voluntarily entered into.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Muldowney v. Portage Cty., Ohio Board of Cty. Commissioners
2018 Ohio 2579 (Ohio Court of Appeals, 2018)
Short v. Resource Title Agency, Inc.
2014 Ohio 830 (Ohio Court of Appeals, 2014)
Fia Card Services v. Young, 08 Ca 22 (4-27-2009)
2009 Ohio 2008 (Ohio Court of Appeals, 2009)
Fia Card Services v. Wood, 08-Je-13 (3-24-2009)
2009 Ohio 1513 (Ohio Court of Appeals, 2009)
Lauro v. Twinsburg, Unpublished Decision (12-12-2007)
2007 Ohio 6613 (Ohio Court of Appeals, 2007)
New Par v. Misuraca, 06ca009060 (6-29-2007)
2007 Ohio 3300 (Ohio Court of Appeals, 2007)
Bennett v. Sunnywood Land Dev., 06ca0089-M (5-7-2007)
2007 Ohio 2154 (Ohio Court of Appeals, 2007)
Lowe v. Oster Homes, Unpublished Decision (9-25-2006)
2006 Ohio 4927 (Ohio Court of Appeals, 2006)
Bowden v. Weickert, Unpublished Decision (2-3-2006)
2006 Ohio 471 (Ohio Court of Appeals, 2006)
Handel's Ent., Inc. v. Wood, Unpublished Decision (12-22-2005)
2005 Ohio 6922 (Ohio Court of Appeals, 2005)
Wachovia Securities, Inc. v. Gangale
125 F. App'x 671 (Sixth Circuit, 2005)
Northern Ohio Sewer Contractors, Inc. v. Bradley Development Co.
825 N.E.2d 650 (Ohio Court of Appeals, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
740 N.E.2d 729, 138 Ohio App. 3d 174, 2000 Ohio App. LEXIS 2782, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ford-hull-mar-nursing-home-inc-v-marr-knapp-crawfis-associates-inc-ohioctapp-2000.