Jasper Construction, Inc. v. Foothill Junior College District

91 Cal. App. 3d 1, 153 Cal. Rptr. 767, 1979 Cal. App. LEXIS 1548
CourtCalifornia Court of Appeal
DecidedMarch 27, 1979
DocketCiv. 41646
StatusPublished
Cited by22 cases

This text of 91 Cal. App. 3d 1 (Jasper Construction, Inc. v. Foothill Junior College District) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jasper Construction, Inc. v. Foothill Junior College District, 91 Cal. App. 3d 1, 153 Cal. Rptr. 767, 1979 Cal. App. LEXIS 1548 (Cal. Ct. App. 1979).

Opinion

Opinion

DRUMMOND, J. *

Defendant-appellant Foothill Junior College District of Santa Clara County (hereafter Foothill) appeals from a judgment in Santa Clara County Superior Court following a jury verdict awarding plaintiff-respondent Jasper Construction Company (hereafter Jasper) $742,133.96 upon its complaint for damages for breach of contract stemming from alleged defects in plans and specifications for the construction of a junior college auditorium.

Jasper cross-appeals from that portion of the judgment denying it prejudgment interest.

The focus of controversy in this case is the construction of the Calvin C. Flint Center for the Performing Arts, located on the De Anza Community *6 College campus in Santa Clara. Jasper 1 was the general contractor for this project and Foothill the owner for whom the project was constructed. In addition to suing Foothill, Jasper sued Kump, Masten & Hurd, a joint venture consisting of two separate architectural firms (hereafter referred to as the architects) who designed and supervised the project. The essence of Jasper’s claim was that as the result of inadequate and defective plans and specifications for the construction of the project and negligence in administering it, Jasper suffered delays and extra expenses for which he sought recovery in damages.

Under the terms of the contract signed on May 17, 1968, Jasper was to be paid $3,307,403 and was required to complete the project within 600 calendar days or by January 7, 1970. Jasper agreed to pay as liquidated damages, the sum of $400 for each calendar ,day that the project was delayed.

Jasper received extensions of 155 days from Foothill, which would have made the completion date June 11, 1970. Requests totalling 223 days of extension were denied. Notice of completion was not in fact filed until June 10, 1971, or 363 days beyond the original completion date. Foothill thus withheld $145,200 in liquidated damages on account of the delay.

Jasper’s major claim for damages at trial was that the plans and specifications prepared by the architects were defective since they did not reveal that he was required to pour concrete by using a different method than the customary one he had anticipated when preparing his bid. The contract between the parties specified:

“11. Construction Joints

(A) Location and details of construction joints shall be as indicated on the structural drawings, or as approved by the Architect. Relate required vertical joints in walls to joints in finish. In general, approved joints shall be located to least impair the strength of the structure.” Jasper stated that the location of the construction joints was not shown on the architect’s drawings, but that certain structural drawings indicated to him that the steel was from floor-to-floor and that therefore the concrete would be poured from floor-to-floor. He stated that he began pouring the *7 basement from floor-to-floor but that the architects then informed him to keep the pour joints in a straight horizontal line from wall-to-wall. Jasper objected to this “horizontal” method of pouring as he alleged that it left him with a lot of wooden concrete forms he could not use. At trial, Jasper claimed that having to use this different method of pouring cost him $500,000 in “extra material and extra labor,” as distinguished from delay.

Foothill, in addition to denying liability under Jasper’s claim, instituted a cross-complaint praying for $145,200 against Jasper as the result of his alleged breach of contract in delaying completion of the project. The figure was based on the $400 per day liquidated damage figure multiplied by the 363 additional days it took to complete the project.

The case went to the jury on theories of breach of implied warranty and breach of contract against Foothill and professional malpractice against the architects. The jury was instructed that if Foothill was responsible for some delay in completing the project, it could not recover under the liquidated damages provision, but could recover any actual damages for delays caused by Jasper.

The juiy returned a general verdict in favor of Jasper and against Foothill in the sum of $742,133.96. It rendered a verdict in favor of Foothill on its cross-complaint against Jasper in the sum of $12,054.30. The jury found against the architects in the sum of $25,200 ($36,000 reduced by 30 percent, the proportion of contributory negligence of Jasper). The architects do not appeal. We discuss some of the major assignments of error.

Implied Warranty Instructions

At the request of Jasper, the trial court instructed the jury as follows: “When a public entity, such as Defendant Foothill District in this case, issues plans and specifications to a contractor, such as Plaintiff Jasper in this case, the District impliedly warrants that the plans and specifications are free from defect, are complete and will, if followed by the contractor, result in construction of the project intended.” Foothill contends that this instruction constituted prejudicial error because it (1) permitted the jury to find Foothill liable in the absence of any evidence of misrepresentation or intentional concealment, contraiy to law and (2) held Foothill strictly liable for the errors and omissions of the architects, even though the architects were independent contractors and were *8 themselves held only to a standard of ordinary negligence. The first of these contentions has merit.

The correct rule applicable to the instant case was stated by the Supreme Court in Souza & McCue Constr. Co. v. Superior Court (1962) 57 Cal.2d 508, 510 [20 Cal.Rptr. 634, 370 P.2d 338]: “A contractor of public works who, acting reasonably, is misled by incorrect plans and specifications issued by the public authorities as the basis for bids and who, as a result, submits a bid which is lower than he would have otherwise made may recover in a contract action for extra work or expenses necessitated by the conditions being other than as represented. (E.g., United States v. Spearin, 248 U.S. 132, 136-137 [39 S.Ct. 59, 63 L.Ed. 166]; Christie v. United States, 237 U.S. 234, 239-242 [35 S.Ct. 565, 59 L.Ed. 933]; McCree & Co. v. State, 253 Minn. 295 [91 N.W.2d 713, 721-722]; see Gogo v. Los Angeles etc. Flood Control Dist., 45 Cal.App.2d 334, 341 [114 P.2d 65]; 43 Am.Jur. 852; Annotation 76 A.L.R. 268.)” The Supreme Court went on to explain that “[t]his rule is mainly based on the theory that the furnishing of misleading plans and specifications by the public body constitutes a breach of implied warranty of their correctness.” (Id., at pp. 510-511.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DeLuca v. State Fish Co.
217 Cal. App. 4th 671 (California Court of Appeal, 2013)
Los Angeles Unified School District v. Great American Insurance
234 P.3d 490 (California Supreme Court, 2010)
Coito v. Superior Court
182 Cal. App. 4th 758 (California Court of Appeal, 2010)
Los Angeles Unified School Dist. v. Great American Ins. Co.
163 Cal. App. 4th 944 (California Court of Appeal, 2008)
Thompson Pacific Construction Inc. v. City of Sunnyvale
66 Cal. Rptr. 3d 175 (California Court of Appeal, 2007)
Stop Loss Insurance Brokers, Inc. v. Brown & Toland Medical Group
49 Cal. Rptr. 3d 609 (California Court of Appeal, 2006)
Bohm v. Horsley Co. (In Re Groggel)
333 B.R. 261 (W.D. Pennsylvania, 2005)
Amelco Electric v. City of Thousand Oaks
98 Cal. Rptr. 2d 159 (California Court of Appeal, 2000)
Cook v. Oklahoma Board of Public Affairs
1987 OK 22 (Supreme Court of Oklahoma, 1987)
Baldwin v. National Safe Depository Corp.
697 P.2d 587 (Court of Appeals of Washington, 1985)
National Steel Products Co. v. Superior Court
164 Cal. App. 3d 476 (California Court of Appeal, 1985)
Vrgora v. Los Angeles Unified School District
152 Cal. App. 3d 1178 (California Court of Appeal, 1984)
Welch v. State of California
139 Cal. App. 3d 546 (California Court of Appeal, 1983)
Westinghouse Electric Corp. v. County of Los Angeles
129 Cal. App. 3d 771 (California Court of Appeal, 1982)
Keith v. Burzynski
621 P.2d 247 (Wyoming Supreme Court, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
91 Cal. App. 3d 1, 153 Cal. Rptr. 767, 1979 Cal. App. LEXIS 1548, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jasper-construction-inc-v-foothill-junior-college-district-calctapp-1979.