Los Angeles Unified School Dist. v. Great American Ins. Co.

163 Cal. App. 4th 944, 78 Cal. Rptr. 3d 99, 2008 Cal. App. LEXIS 840
CourtCalifornia Court of Appeal
DecidedJune 5, 2008
DocketB189133
StatusPublished

This text of 163 Cal. App. 4th 944 (Los Angeles Unified School Dist. v. Great American Ins. Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Los Angeles Unified School Dist. v. Great American Ins. Co., 163 Cal. App. 4th 944, 78 Cal. Rptr. 3d 99, 2008 Cal. App. LEXIS 840 (Cal. Ct. App. 2008).

Opinion

163 Cal.App.4th 944 (2008)

LOS ANGELES UNIFIED SCHOOL DISTRICT, Plaintiff and Respondent,
v.
GREAT AMERICAN INSURANCE COMPANY et al., Defendants and Appellants.

No. B189133.

Court of Appeals of California, Second District, Division Two.

June 5, 2008.

*947 Wilson Elser Moskowitz Edelman & Dicker, John J. Immordino and Susannah M. Dudley for Defendant and Appellant Great American Insurance Company.

Monteleone & McCrory, Joseph A. Miller and Leighton T. Brown II for Defendant and Appellant Hayward Construction Company, Inc.

Bergman & Dacey, Inc., Gregory M. Bergman, John P. Dacey and Jorge J. Luna for Plaintiff and Respondent.

OPINION

CHAVEZ, J.

In this consolidated appeal, defendants and appellants Hayward Construction Company, Inc. (Hayward), and Great American Insurance Company (Great American) (collectively, appellants) appeal from a final judgment entered after the trial court granted a motion for summary adjudication and motion for judgment on the pleadings in favor of plaintiff and respondent Los Angeles Unified School District (District), and entered dispositive rulings in favor of the District on remaining legal issues. Appellants also appeal from the trial court's award of attorney fees. We reverse the judgment and reverse the attorney fee award.

FACTUAL BACKGROUND

1. The Project

The Queen Anne Place school project (the project) involved construction of a new elementary school in Los Angeles. In March 1996, following competitive bids required by law, the District contracted with Lewis Jorge Construction Management, Inc. (Lewis Jorge), to construct the project for approximately $10.1 million. By late 1998, the District became dissatisfied with Lewis *948 Jorge, and on February 9, 1999, the District declared Lewis Jorge to be in material breach and default. At that time, Lewis Jorge claimed it had completed work totaling $9.4 million, or approximately 93 percent of the original contract price.[1]

On April 27, 1999, the District's governing board adopted a declaration of emergency pursuant to Public Contract Code section 20113,[2] which allowed the District to enter into a contract to complete the project without advertising for or inviting bids. The District then sought completion cost proposals from other general contractors. Completion of the project required correction of certain work performed by Lewis Jorge. To assist potential contractors, the District created a "pre-punch list" that identified the remaining work and work to be corrected. The District received cost estimates from three general contractors, including Hayward, and ultimately selected Hayward to complete the project.

2. The Completion Agreement Between Hayward and the District

In June 1999, Hayward and the District entered into a completion contract for the project (completion agreement). Paragraph 8 of the completion agreement states that the contract "can be generally described as `a cost plus percentage fee (10%) with a guaranteed maximum,'" pursuant to which the District agreed to pay Hayward for cost of work, labor, and actual costs, plus a fee of 10 percent calculated as a markup on the actual costs incurred. Paragraph 11 states: "Contractor guarantees that the maximum amount payable by the District for the Cost of the Work plus the Contractor's Fee described in Paragraph 10 will not exceed Four Million Five Hundred Thousand Dollars ($4,500,000.00)."

In paragraph 15, the parties agreed that the scope of Hayward's work included the items listed on the pre-punch list. That paragraph states: "The Contractor's obligation to complete the work in accordance with this Completion Agreement and the Contract Documents shall include the responsibility to correct deficiencies in the work performed by the former contractor, without limitation, as noted on the current correction list issued by the District."

The "correction list" referred to in this paragraph consists of a 22-page pre-punch list prepared by the District's architect, and an 86-page pre-punch list prepared by the District's inspectors. The final entry on the architect's pre-punch list states: "Corrections or comments made in regard to the *949 pre-punch list during this review do not relieve the Contractor from compliance with the requirements of the drawings and specifications. This review is only for General Conformance with the design concept of this project and general compliance with the information given in the Contract Documents. The Contractor is responsible for confirming all quantities, dimensions and techniques of construction; coordinating all work with that of all other trades and performing his work in a safe, acceptable and satisfactory manner."

Each page of the pre-punch list prepared by the District's inspectors contains the following caption: "This is a courtesy pre-punch list and should not be taken as a final inspection punch list. This is not the punch list of minor corrective items made at the final inspection."

After Hayward and the District executed the completion agreement, Great American issued a performance bond for $4.5 million that guaranteed Hayward's performance of the contract.

3. Hayward's Work and the District's Advance of Sums Exceeding $4.5 Million

Not long after Hayward commenced work, a dispute arose between Hayward and the District concerning work that was not listed in either of the pre-punch lists. This work included correcting defects in the stucco work and subsurface defects in the bathroom tile work. In December 1999, Hayward advised the District that many unforeseen conditions made it necessary to increase the contract price beyond $4.5 million. In May 2000, the board of education allocated $3 million to complete the project. After the board's action, the District issued a purchase order for $2 million to complete the project. Payment was made to Hayward under an express reservation of rights, which stated that "the advancing of costs to [Hayward is] without prejudice to all of the District's rights to recover the monies advanced against all responsible parties, including [Hayward] and its surety company if appropriate."

In early February 2001, the parties met to discuss the payments. On February 16, 2001, the District wrote Hayward a letter explaining the District's position that cost of the work in excess of $4.5 million, plus certain change orders, were Hayward's contractual responsibility. The District demanded that Hayward and its surety, Great American, return more than $1 million the District paid to Hayward over and above the $4.5 million contract price. Hayward and Great American refused, and in March 2001 the District commenced this action.

*950 PROCEDURAL BACKGROUND

1. The Complaint

The District's complaint alleged breach of contract, breach of performance bond, and declaratory relief. The District sought a declaration that the completion agreement required Hayward to "complete construction of the Queen Anne Place Elementary School Project, including all deficiencies existing in the Project at the time [Hayward] commenced work thereat whether such deficiencies were latent or patent," and that Hayward "agreed to so perform, all for the guaranteed maximum price payable by the District of $4,500,000.00." Hayward and Great American filed answers to the complaint, and Hayward cross-complained for breach of contract, rescission, and declaratory relief.[3]

2. The District's Motion for Summary Adjudication

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jasper Construction, Inc. v. Foothill Junior College District
91 Cal. App. 3d 1 (California Court of Appeal, 1979)
BMW of North America, Inc. v. New Motor Vehicle Board
162 Cal. App. 3d 980 (California Court of Appeal, 1984)
Welch v. State of California
139 Cal. App. 3d 546 (California Court of Appeal, 1983)
Shore v. Central Contra Costa Sanitary District
208 Cal. App. 2d 465 (California Court of Appeal, 1962)
City of Cypress v. New Amsterdam Casualty Co.
259 Cal. App. 2d 219 (California Court of Appeal, 1968)
Oceanside 84, Ltd. v. Fidelity Federal Bank
56 Cal. App. 4th 1441 (California Court of Appeal, 1997)
ASP Properties Group, L.P. v. Fard, Inc.
35 Cal. Rptr. 3d 343 (California Court of Appeal, 2005)
Save Sunset Strip Coalition v. City of West Hollywood
105 Cal. Rptr. 2d 172 (California Court of Appeal, 2001)
Marshall v. Pasadena Unified School District
15 Cal. Rptr. 3d 344 (California Court of Appeal, 2004)
Fiol v. Doellstedt
50 Cal. App. 4th 1318 (California Court of Appeal, 1996)
Thompson Pacific Construction Inc. v. City of Sunnyvale
66 Cal. Rptr. 3d 175 (California Court of Appeal, 2007)
Alling v. Universal Manufacturing Corp.
5 Cal. App. 4th 1412 (California Court of Appeal, 1992)
Wolf v. Superior Court
8 Cal. Rptr. 3d 649 (California Court of Appeal, 2004)
Winet v. Price
4 Cal. App. 4th 1159 (California Court of Appeal, 1992)
Kashani v. TSANN KUEN CHINA ENTERPRISE CO.
13 Cal. Rptr. 3d 174 (California Court of Appeal, 2004)
Kids' Universe v. In2labs
116 Cal. Rptr. 2d 158 (California Court of Appeal, 2002)
Aguilar v. Atlantic Richfield Co.
24 P.3d 493 (California Supreme Court, 2001)
Amelco Electric v. City of Thousand Oaks
38 P.3d 1120 (California Supreme Court, 2002)
Garvey School District v. Paul
194 P. 711 (California Court of Appeal, 1920)
Kapsimallis v. Allstate Insurance
104 Cal. App. 4th 667 (California Court of Appeal, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
163 Cal. App. 4th 944, 78 Cal. Rptr. 3d 99, 2008 Cal. App. LEXIS 840, Counsel Stack Legal Research, https://law.counselstack.com/opinion/los-angeles-unified-school-dist-v-great-american-i-calctapp-2008.