Garvey School District v. Paul

194 P. 711, 50 Cal. App. 75, 1920 Cal. App. LEXIS 82
CourtCalifornia Court of Appeal
DecidedNovember 20, 1920
DocketCiv. No. 3435.
StatusPublished
Cited by4 cases

This text of 194 P. 711 (Garvey School District v. Paul) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Garvey School District v. Paul, 194 P. 711, 50 Cal. App. 75, 1920 Cal. App. LEXIS 82 (Cal. Ct. App. 1920).

Opinion

CONREY, P. J.

This is an action on the contractor’s bond given to the owner as security for the faithful performance of a contract made with the plaintiff school district by one B. H. Paul for the erection of a school building. The plaintiffs appeal from the judgment entered in favor of defendants.

*76 The powers and duties of trustees of common school districts are, among others, the following: “To let all contracts involving an expenditure of more than two hundred dollars for work to he done or for materials or supplies to be furnished . . . , to the lowest responsible bidder who will give such security as the board may require or else to reject all bids; . . . For the purpose of securing bids the board must publish a notice calling for bids, stating the work to be done or materials or supplies to be furnished, and the time when and the place where the bids will be opened, at least once a week for two weeks in some daily or weekly newspaper published in the county, ...” (Pol. Code, sec. 1617, subd. 20.) The Paul contract was let in the manner required by law. It was dated August 18, 1915, and by its terms the contractor was allowed 105 working days from that date within which to complete the contract. In other words, the work was to be finished about the middle of December, 1915. It was provided in paragraph 6 of the contract that “should the contractor at any time during the progress of said works, refuse or neglect to supply a sufficiency of materials or workmen, the owner shall have the power to provide materials and workmen (after three days’ notice in writing given) to finish the said works, and the reasonable expenses thereof shall be deducted from the amount of said contract price.” The bond was executed by defendant Southwestern Surety Insurance Company. The other defendant company is an insurance company which later assumed the liabilities of the Southwestern Company. It was provided in the bond that the principal contract was therein expressly referred to and made part thereof.

The findings state “that on or about the sixteenth day of October, 1915, the contractor, B. H. Paul, ceased work on said building, and thereafter continuously and at all times up to about the twelfth day of January, 1916, failed to furnish labor and material to carry out said contract.” In fact, he never did anything further on the contract, unless it be held that work done after the date last mentioned, or some part of it, was done by the school district in his behalf. On November 1, November 4, and November 22, 1915, the school district gave to the contractor and to the Southwestern Insurance Company three-day notices framed in ae *77 cordance with said clause 6 of the contract. The parties notified did nothing in response to those notices, and the school district did not then furnish any materials or cause any work to be done on the building. Again, on the eighth day of January, 1916, the school district gave to the same parties a fourth notice in like form as before. Thereupon the school district, on the twelfth day of January, 1916, with the knowledge and consent of the contractor, took entire charge of the work and after said time furnished all of the necessary materials and workmen and caused the work of completing the school building to be carried on, and from and after that time the contractor took no part under the contract in the construction of the building, and all of the contracts let for labor and materials were let in the name of the school district and by the school district. Prior to the sixteenth day of October, 1915, the contractor had earned and had been paid the first and second installments of the contract price and there remained unexpended of the contract price the sum of $20,535. The contractor remained .in charge of the premises until the twelfth day of January, 1916.

On the fourteenth day of January, 1916, the Southwestern Surety Insurance Company offered in writing to the school district that it would furnish all the necessary material and workmen to complete the contract and would fully and faithfully perform the conditions thereof, and demanded that it be permitted to complete the contract. This offer was refused by the school district, which at that time had taken charge of the work. Between the twelfth day of January and the twenty-first day of June, 1916, the school district expended in carrying on the work for the completion of said building the sum of $20,535, which was the reasonable value of all the material and workmen thus furnished. On June 21, 1916, the school district notified the contractor and said surety company that there had been expended on the school building the sum last mentioned, in addition to the sum previously paid to the contractor and that the building was not completed, and the school district requested and demanded that the contractor and said surety company proceed to complete the work in accordance with the contract. This the contractor and surety company wholly neglected and failed to do. There *78 after the school district completed the building in accordance with the original plans and specifications, at an additional expense of $3,996.99, to recover which amount, together with certain alleged special damages, this action has been prosecuted.

The work done between the twelfth day of January, 1916, and the twenty-first day of June, 1916, whereby said sum of $20,535 was expended, was done by the school district without any publications calling for bids or specifying the time and place where bids were opened; in other words, without any attempt to let contracts in the manner described in the section of the Political Code to which we have referred.

Upon the facts found, judgment should have been rendered in favor of the plaintiff, unless the judgment should be affirmed for one of two reasons which on this appeal are relied upon by the respondents. These contentions are that the judgment should be affirmed, (1) for the reason that the school district made expenditures in excess of the statutory amount without advertising for bids as required by law; (2) for the reason that the surety company offered to perform the contract and fulfill all the obligations thereof.

It is contended by respondents that their first proposition is sustained by five decisions of the supreme court of this state. Dougherty v. Foley, 32 Cal. 403, and Meuser v. Risdon, 36 Cal. 239, are street assessment cases in which it was held that where a contractor failed to enter upon the contract or had abandoned the work, it was necessary for the municipality to re-advertise for bids. But the statute under which the proceedings in those cases had been conducted in terms provided that there must be a re-advertisement for bids under the circumstances stated. In this respect they are different from the statute in question in this case, inasmuch as said section of the Political Code is silent on the subject of re-advertisement for bids or reletting of contracts. In Reams v. Cooley, 171 Cal. 150, [Ann. Cas. 1917A, 1260, 152 Pac. 293], and Matthews v. Town of Livermore, 156 Cal. 294, [104 Pac.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Los Angeles Unified School Dist. v. Great American Ins. Co.
163 Cal. App. 4th 944 (California Court of Appeal, 2008)
Electrical Electronic Control, Inc. v. Los Angeles Unified School District
24 Cal. Rptr. 3d 316 (California Court of Appeal, 2005)
Shore v. Central Contra Costa Sanitary District
208 Cal. App. 2d 465 (California Court of Appeal, 1962)
H. G. Fenton Material Co. v. Noble
15 P.2d 884 (California Court of Appeal, 1932)

Cite This Page — Counsel Stack

Bluebook (online)
194 P. 711, 50 Cal. App. 75, 1920 Cal. App. LEXIS 82, Counsel Stack Legal Research, https://law.counselstack.com/opinion/garvey-school-district-v-paul-calctapp-1920.