Keith v. Burzynski

621 P.2d 247, 1980 Wyo. LEXIS 331
CourtWyoming Supreme Court
DecidedDecember 23, 1980
Docket5335
StatusPublished
Cited by3 cases

This text of 621 P.2d 247 (Keith v. Burzynski) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Keith v. Burzynski, 621 P.2d 247, 1980 Wyo. LEXIS 331 (Wyo. 1980).

Opinion

ROSE, Justice.

A utility contractor and a land developer entered into a construction contract, according to the terms of which the contractor was to be liable for liquidated damages at the rate of $150.00 per day for construction delay. Construction was, in fact, delayed for 83 days, and it is undisputed that at least 18 days of this delay were chargeable to the land developer. The trial court apportioned the fault for failure to timely complete the work and assessed liquidated damages in the sum of $9,750.00 against the contractor for 65 days of the delay. Appellant contractor argues that where both parties contribute to the delay, liquidated damages—even if adjusted to reflect proportionate fault—are inappropriate. Appellant also argues that the trial court erred in determining that it was at fault in any respect. We cannot agree with appellant’s position and will affirm.

THE FACTS AND CONTENTIONS

The contract provided for defendant-appellant Keith, d/b/a Keithco, to “perform all the sanitary sewer, water main and services, earth work, utilities trenching, and manhole construction work heretofore ordered” by the developer, plaintiff-appellee Burzynski. Work was to be commenced on August 22, 1977, and completed within 33 consecutive calendar days. Thus, the parties had agreed upon a September 24 deadline. The trial court made the following findings of fact:

“2. The defendant completed substantially all of the work by December 15, 1977. The defendant was justified in stopping work at that time as he had not been paid in full for work completed and the remaining work could not be accomplished, through no fault of the defendant. The defendant’s work on manholes could not reasonably be completed until the paving, to be done by others, was finished. The paving was not completed until 1978. Also, the weather was too cold for completion of the pipe testing work, a factor partly due to delays attributable to the plaintiff because of a lack of materials which were to have been supplied by the plaintiff and inadequate staking done by the plaintiff’s representative.
“3. The amount of time consumed by the defendant in excess of the thirty-three day limit was eighty-three days. Eighteen days of the delay are excused as being the plaintiff’s responsibility because of staking and material problems, *249 leaving sixty-five days unexcused at $150.00 a day or $9,750.00 as liquidated damages for the plaintiff.” 1

The appellant argues that the appellee was to provide the materials and that the appellee’s tardy provision of materials caused all of the delay. Indeed, the appellant testified to various delays caused by reason of appellee’s failure to timely provide materials and this testimony explains the trial judge’s finding that the appellee was responsible for 18 days of the delay. It is undisputed that certain fire hydrants were not furnished by the appellee until December 12. Appellant argues that the hydrants were necessary to test the water system and the appellee’s failure to provide them on time makes the appellee liable for virtually all, or indeed all, of the delay.

Appellant also makes the argument that since the appellee breached the contract by providing the materials late, it must forfeit its entitlement to liquidated damages. Appellant further claims that there were many other instances of appellee-caused delay which the appellant did not deem necessary to prove at trial because of its belief that if the owner causes some delay, the contractor will not be liable for liquidated damages.

Appellee has not cross-appealed his denial of liquidated damages for 18 days. He apparently concedes fault for that portion of the delay but argues that the trial court was legally correct in its approach to apportioning blame for the delay. He also argues that the failure to timely provide the fire hydrants did not interfere with sub-, stantial completion of the work since the hydrants were “bolt-on” equipment.

Liquidated Delay Damages Where Both Parties Have Contributed to the Delay

Since there is no serious dispute that the appellee caused at least some of the delay, we have directed our attention first to the issue of whether the delay caused by the appellee disentitles him to collect any liquidated delay damages from the appellant for any delay which the appellant may have caused.

Our review of the law persuades us that 5 Williston on Contracts, Third Edition § 789, pp. 764-766, correctly states the general rule:

“Where both parties are in fault a party who has contributed to the breach cannot recover a sum stipulated as liquidated damages, even though performance of the contract is continued, and the other party thereafter is at fault: ...”

The author goes on, however, to notice an exception where he says:

“In building contracts, there is often inserted a provision giving the architect power to certify an extension of time in certain cases, by virtue of which the effect of a delay caused by the owner operates merely as an extension of the time for performance, and a new time is substituted for the old. In that event though the owner causes delay the builder is liable in liquidated damages, but the period of delay caused by the owner is deducted from the total delay. Unless the contract contains such a provision the delay due to each party will not generally be apportioned.”

The exception discussed in Williston is based in large part on two United States Supreme Court decisions. In United States v. United Engineering and Contracting *250 Company, 234 U.S. 236, 34 S.Ct. 843, 58 L.Ed. 1294 (1914), the government sought liquidated delay damages on a construction project which was initially delayed through the sole fault of the United States. Supplemental contracts were entered into. The supplemental contracts did not provide for liquidated delay damages, but the government relied on the liquidated delay damage provisions of the original contract to argue a claim for damages for subsequent delay by the contractor. In affirming the Court of Claims’ decision against the government, the Supreme Court said:

“ ‘. .. If a man agrees to do something by a particular day or in default to pay a sum of money as liquidated damages, the other party to the contract must not do anything to prevent him from doing the thing contracted for within the specified time.’
“The same rule was followed with approval by the New York Court of Appeals in a well considered case, Mosler Safe Co. v. Maiden Lane S. D. Co., 199 N.Y. 479 [93 N.E. 81], in which it was held that, even where both parties are responsible for the delays beyond the fixed time, the obligation for liquidated damages is annulled, and in the absence of a provision substituting another date it cannot be revived, and the recovery for subsequent delays must be for actual loss proved to have been sustained.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brashear v. Richardson Constr., Inc.
10 P.3d 1115 (Wyoming Supreme Court, 2000)
John Burk, P.C. v. Burzynski
672 P.2d 419 (Wyoming Supreme Court, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
621 P.2d 247, 1980 Wyo. LEXIS 331, Counsel Stack Legal Research, https://law.counselstack.com/opinion/keith-v-burzynski-wyo-1980.