Nomellini Construction Co. v. State Ex Rel. Department of Water Resources

19 Cal. App. 3d 240, 96 Cal. Rptr. 682, 1971 Cal. App. LEXIS 1274
CourtCalifornia Court of Appeal
DecidedAugust 12, 1971
DocketCiv. 12614
StatusPublished
Cited by13 cases

This text of 19 Cal. App. 3d 240 (Nomellini Construction Co. v. State Ex Rel. Department of Water Resources) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nomellini Construction Co. v. State Ex Rel. Department of Water Resources, 19 Cal. App. 3d 240, 96 Cal. Rptr. 682, 1971 Cal. App. LEXIS 1274 (Cal. Ct. App. 1971).

Opinion

Opinion

PIERCE, P. J.

Nomellini Construction Co. (Nomellini) had a contract with the State of California, acting through the Department of Water Resources (Department), to construct 50 portable houses to be placed on concrete foundations. By the terms of the contract the houses could either be constructed off-site or on-site. If built off-site they were to be transported to the site, placed upon the foundations (also to be built by Nomellini) and assembled and completed ready for occupancy. The contract included full plans, specifications and other contract documents. In compliance with Government Code section 14376 the contract provided a time period for completion and for liquidated damages for unexcused late completion, viz., work was to begin within 30 days after notice and completed within 105 days. Nomellini agreed to pay the Department as liquidated damages $10 per house per day for each calendar day’s delay. Notice to proceed was given July 9, 1963. The completion date, therefore, was scheduled for October 22, 1963. The houses were not completed according to schedule. They were completed as to various houses between January 15 and March 27, 1964, a total “overrun” of 6,840 house days.

The contract contained extension provisions hereinafter to be noted. A claim was duly filed for the amounts withheld. Suit was brought by Nomellini and a judgment recovered for $44,000 plus interest, the full amount sued for. The Department has appealed.

Several issues have been presented on appeal. Only two need be discussed: (1) Was Nomellini or the Department or both responsible for delays attendant to the approval of certain shop drawings? (2) If some of the delay was the responsibility of each party, was the Department properly deprived of all liquidated damages?

The factual basis of Nomellini’s claim was extensions claimed to have been earned but not allowed. 1 Certain extensions had been granted by the *243 Department. The division engineer found that a plywood strike had delayed construction by 2,440 house days and therefore reduced the total days for which liquidated damages were exacted to 4,400 house days. Nomellini had also sought an extension claiming it had had to design or redesign the houses to make them portable, that it had done so by means of shop drawings and that the Department had delayed Nomellini by failing to approve such drawings in time to allow it to perform within the contract period. The division engineer denied that claim, his decision was appealed to a chief engineer, a board of review for construction contract claims of the Department held an informal hearing and the claims were denied by the chief engineer “because the delays experienced by [Nomellini] were not attributable to acts or omissions of the Department. ...”

Other facts will be discussed in connection with the issues.

Responsibility for Shop Drawings

The law required and the evidence showed that the houses in the plans and specifications upon which Nomellini had bid and as contained in the contract between the parties were designed as portable. (Gov. Code, §§ 14270, 14272.) These documents were complete. Nomellini could have constructed the houses according to them and would have been entitled to its contract prifce—had'the plans and specifications been complied with —even though the houses in fact turned out not to be portable. (Patrick J. Ruane, Inc. v. Parker (1960) 185 Cal.App.2d 488, 498 [8 Cal.Rptr. 379]; see also Mannix v. Tryon (1907) 152 Cal. 31, 40-41 [91 P. 983].)

Under section 14, subdivision (a) (1), of the contract between the parties it was stated that the drawings showed the general methods of assembling and joining, disassembling and separation of the units. Shop drawings detailing the methods of accomplishing this were to be prepared by the contractor. These methods were enumerated precisely in the documents furnished Nomellini. Only in the case of alterations desired by Nomellini was there any necessity of special approval by the Department of plans therefor.

The contract contained a provision for substitute methods. At its option *244 Nomellini might present detail drawings for alternate methods. It did so. It desired to substitute “stress skin” for “open beam assembly.” The Department permitted the changes. It was known to Nomellini when it took the contract providing for completion of all work by October 22, 1963, that any substitute methods would be permissive and required approval. There was no provision in the contract for extensions of time under those circumstances.

The trial court made a finding that final approval of plaintiff’s submitted drawings did not occur until November 1, 1963, and that this was occasioned by the Department’s act. The contract, therefore, it was found, could not have been completed on the schedule date, October 22, 1963. That sounds as though the Department had caused a delay (and the trial court so concluded), but we find nothing in the record to support that conclusion. The greater portion of Nomellini’s shop drawings had been submitted previously and had been approved long before October 22. The only shop drawings which were,not approved prior to the completion date were the permissive detail drawings which Nomellini elected to submit and thereafter resubmit for an alternate method of taking care of the portability feature because that substitute method would save the contractor money. As to these, all were acted upon by the Department within the time limit as expressed in the contract or earlier. Thus Nomellini and not the Department was responsible for these delays.

We have mentioned above that the Department allowed an extension of time for the delay caused by a certain plywood workers’ strike. It is stated that there were other delays. Other contractors did not complete certain streets on time. But the record establishes that those delays in no way contributed to Nomellini’s “overrun.”

Apportionment of Fault in the Award of Liquidated Damages

Government Code section 14376 2 requires that in every contract for public work there shall be a provision specifying a date for the completion of the work and further specifying liquidated damages to be deducted from the payments due in the event of late completion. This contract contained the required provision. As stated above, it also contained *245 a provision for extensions of time for delays which were not the fault of the contractor. (See fn. 2.) We have also shown that the Department disallowed certain claims of Nomellini for extensions. We have been unable to find in the record any instances in which the Department was wrong. Assuming arguendo contrary to our holding that there were delays which the Department should have allowed, they were delays which the trial court would have been obligated to apportion.

The controlling law is found in the decision of the United States Supreme Court in Robinson v. United States, 261 U.S. 486 [67 L.Ed. 760, 43 S.Ct 420].

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stop Loss Insurance Brokers, Inc. v. Brown & Toland Medical Group
49 Cal. Rptr. 3d 609 (California Court of Appeal, 2006)
R.P. Wallace, Inc. v. United States
63 Fed. Cl. 402 (Federal Claims, 2004)
Calumet Construction Corp. v. Metropolitan Sanitary District
533 N.E.2d 453 (Appellate Court of Illinois, 1988)
Vrgora v. Los Angeles Unified School District
152 Cal. App. 3d 1178 (California Court of Appeal, 1984)
Westinghouse Electric Corp. v. County of Los Angeles
129 Cal. App. 3d 771 (California Court of Appeal, 1982)
Jasper Construction, Inc. v. Foothill Junior College District
91 Cal. App. 3d 1 (California Court of Appeal, 1979)
Buckley & Co., Inc. v. State
356 A.2d 56 (New Jersey Superior Court App Division, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
19 Cal. App. 3d 240, 96 Cal. Rptr. 682, 1971 Cal. App. LEXIS 1274, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nomellini-construction-co-v-state-ex-rel-department-of-water-resources-calctapp-1971.