Patrick J. Ruane, Inc. v. Parker

185 Cal. App. 2d 488, 8 Cal. Rptr. 379, 1960 Cal. App. LEXIS 1530
CourtCalifornia Court of Appeal
DecidedOctober 20, 1960
DocketCiv. 19083
StatusPublished
Cited by11 cases

This text of 185 Cal. App. 2d 488 (Patrick J. Ruane, Inc. v. Parker) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Patrick J. Ruane, Inc. v. Parker, 185 Cal. App. 2d 488, 8 Cal. Rptr. 379, 1960 Cal. App. LEXIS 1530 (Cal. Ct. App. 1960).

Opinion

DUNIWAY, J.

Action for breach of contract. Plaintiff had judgment and defendant appeals. Appellant Parker had the general contract for the construction of the new Hall of Justice and Records Building at Redwood City; respondent (“Ruane”) had the subcontract with Parker for the plastering. Although the judgment is for $8,272.01, with interest, no claim of error is made as to $1,204.66 thereof. Error is claimed as to $5,400, representing the cost to Parker of painting exterior stucco, and as to $1,667.35, representing the cost to Parker of patching cracked interior plaster. Parker claims that an arbitration award is determinative in his favor, as to the exterior stucco, and that, as to both items, Ruane pleaded performance, but proved only nonperformance plus an excuse for nonperformance. We have concluded that the judgment must be affirmed.

*491 The Contracts

In his subcontract, Ruane agrees to do ‘... in a workmanlike manner, as required by and in strict accord with said plans and specifications and details illustrative thereof as approved by the Contractor, and to the satisfaction, of the Contractor, all Lathing and Plastering, i.e., all work outlined in Part 1, Sections 16 and 17 of the Specifications.” Ruane also agrees “to prosecute [the work] ... in full accord with the requirements of the general construction as determined by the Contractor. ...” Parker has the right, if Ruane fails to perform, to do the work at Ruane’s expense. It is further provided that “The Sub-Contractor acknowledges familiarity with the general conditions of the aforesaid specifications and all conditions of the original contract between the Owner and Contractor and agrees to be bound thereby insofar as they are applicable to this particular work; ...” The subcontract relieves Parker of liability to Ruane for delay, but not from other liabilities.

The material portions of the general conditions of the prime contract are, as to duties of Parker to the owner, to: determine when and where materials and labor will next be needed (9c), coordinate the various types of work and inform subcontractors (9d), notify subcontractors to furnish and set their work in place (9f), safeguard the work against weather, etc. (91), provide needed heat “as necessary to protect all materials against injury from dampness and cold,” and specifically, “ [f]rom the beginning of the application of plaster and during the setting and curing period, provide sufficient heat to produce a temperature in the spaces involved not less than 50° Fahrenheit” (9n, 2), furnish, for the architect’s approval, samples of materials, including “plaster and lathing materials.” Such materials are not to be used without the architect’s approval (9r, 2 and special conditions, 13a). Subcontracts are to be approved by the architect (10a). “The Contractor shall bind every Sub-contractor, and every Subcontractor agrees to be bound by the terms of the Contract Documents to carry out their provisions insofar as applicable to their work” (10c), but there is no contractual relation between the subcontractor and the county (10d). The contractor is required to “ [d]o all necessary patching of damaged, cracked or defective plaster, leaving all plaster work in perfect condition.” (Specifications, § 17-09.)

As to the architect, the entire work is under his jurisdiction. One of his functions is to “pass upon merits of materials and *492 workmanship.’’ He is “to make written decisions in regard to all claims of the Owner or Contractor and to interpret the Contract Documents on all questions arising in connection with the execution of the work.” His decisions or interpretations are subject to arbitration (14, 14b). All material and workmanship are subject to the architect’s inspection, and he has “the right to reject defective material and workmanship” or require their correction. Bejeeted workmanship shall be satisfactorily replaced with proper material without charge (15a). Final payment to the contractor is to be made upon a certification of completion by the architect (17f, g).

The Pleadings

The complaint alleges the making of the contract in general terms only, and full performance on Euane’s part. The answer admits the contract and denies the allegation of performance. It also pleads in substance, as a separate defense, that a dispute arose as to whether the work had been completed in accordance with “the plans and specifications” and that this matter was submitted to arbitration and decided against Euane by the arbitrators. These are, on their face, sufficient pleadings (Code Civ. Proc., § 457). It is also true, however, that they successfully conceal the real issues to be tried.

The Pbetbial Obdeb

No pretrial order is included in either transcript, but the parties referred to a pretrial order at the trial. Because the pretrial order, “where inconsistent with the pleadings, controls the subsequent course of the case” (rule 8.8, Buies for the Superior Courts), and because Parker’s contentions on appeal are based in part on claimed insufficiency of the complaint in relation to the proof, we have on our own motion ordered a copy of the pretrial order made a part of the record on appeal. (Cf. the remarks of Ashburn, J., as to our status as parens patriae in Burnstein v. Zelman, 182 Cal.App.2d 1, 2-3 [5 Cal.Rptr. 829].) Unfortunately, the pretrial order contributes nothing to the clarification of the issues or to the solution of the problem relating to the pleadings presented by appellant Parker. It appears to us to be a totally useless document. (Cf. Arch Rib-Summerbell Steel Fabricators v. Lubliner, 183 Cal.App.2d 593, 595-596 [7 Cal.Rptr. 94]; Collison v. Thomas, * (Cal.App.) 6 Cal.Rptr. 911.) It quotes *493 verbatim the pretrial statements of the parties, which are no more specific than the pleadings, but does not at any point attempt to state, with any particularity or at all, the actual issues to be tried. Had the pretrial judge delved into the matter at all, he could have discovered the true nature of the controversy, settled the issues to be tried, required such amendments to the pleadings as might be required (rule 8.4(a)) and eliminated the contention as to the pleadings now pressed upon us. He did none of these things.

The Real Issue

The issues developed at the trial are these: It is conceded that Ruane did all of the work required by the contract, the controversy being only, in the instance of the exterior plaster, as to (a) whether he was bound to repair the defects that admittedly appeared, regardless of their cause, or (b), if not, whether the defects were the result of defects in his work, or (c) whether the arbitration award was conclusive against him; and, in the instance of the interior plaster, (a) whether he was bound to repair cracks that admittedly developed, regardless of their cause, or (b), if not, whether they were caused by Ruane’s faulty workmanship or by Parker’s improperly heating the building.

The Findings

Free access — add to your briefcase to read the full text and ask questions with AI

Related

TD General Co. v. Chimes Tower Investment CA2/2
California Court of Appeal, 2024
Durell v. Sharp Healthcare
183 Cal. App. 4th 1350 (California Court of Appeal, 2010)
Bencon Management & General Contracting, Inc. v. Boyer, Inc.
178 S.W.3d 198 (Court of Appeals of Texas, 2005)
Brink v. Hayes Branch Drainage District
376 N.E.2d 78 (Appellate Court of Illinois, 1978)
Delta Lines, Inc. v. International Brotherhood of Teamsters, Local 468
66 Cal. App. 3d 960 (California Court of Appeal, 1977)
Nomellini Construction Co. v. State Ex Rel. Department of Water Resources
19 Cal. App. 3d 240 (California Court of Appeal, 1971)
U. S. Industries, Inc. v. Vadnais
270 Cal. App. 2d 520 (California Court of Appeal, 1969)
Kurland v. United Pacific Insurance
251 Cal. App. 2d 112 (California Court of Appeal, 1967)
Fresno Air Service v. Wood
232 Cal. App. 2d 801 (California Court of Appeal, 1965)
Goldman v. Ecco-Phoenix Electric Corp.
396 P.2d 377 (California Supreme Court, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
185 Cal. App. 2d 488, 8 Cal. Rptr. 379, 1960 Cal. App. LEXIS 1530, Counsel Stack Legal Research, https://law.counselstack.com/opinion/patrick-j-ruane-inc-v-parker-calctapp-1960.