Kurland v. United Pacific Insurance

251 Cal. App. 2d 112, 59 Cal. Rptr. 258, 1967 Cal. App. LEXIS 1952
CourtCalifornia Court of Appeal
DecidedMay 17, 1967
DocketCiv. 29641
StatusPublished
Cited by6 cases

This text of 251 Cal. App. 2d 112 (Kurland v. United Pacific Insurance) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kurland v. United Pacific Insurance, 251 Cal. App. 2d 112, 59 Cal. Rptr. 258, 1967 Cal. App. LEXIS 1952 (Cal. Ct. App. 1967).

Opinion

FORD, P. J.

The plaintiff, the assignee of the owners and of the general contractor, has appealed from a judgment in favor of the defendant in an action upon a performance bond executed with respect to a subcontract for the installation of an air conditioning system in an apartment building in Las Vegas, Nevada.

The findings of fact of the trial court were in part as follows : 1. On August 1, 1957, defendant United Pacific Insurance Company executed a subcontract bond in which M.F.S., Inc., the subcontractor, was named as principal and Labby Construction and Development Company (hereinafter called Labby), the general contractor, was named as obligee. .(The terms of the bond were made a part of the findings of fact. 1 ) 2. The subcontract of May 21, 1957, related to the air conditioning work to be performed in a cooperative apartment building known as the Rexford, Inc., which was being constructed by Labby, as general contractor, for the owners, S. L. Kurland and Paul Manuel. (The terms of the subcontract were made a part of the findings of fact. 2 ) 3. The plans and specifications were prepared for the owners by an architect *115 licensed in the State of Nevada; the air conditioning system embodied in the plans and specifications was designed for the architect by an air conditioning engineer licensed in that state. 4. The proposal submitted to Labby by M.F.S., Inc. was prepared upon the basis of the air conditioning plans and specifications. 5. The equipment specified in the plans and specifications, or the substantial equivalent thereof, and all of the duet work, piping, wiring and other equipment necessary to furnish and complete the air conditioning system described in the plans and specifications were installed in a workmanlike manner in the places indicated therein. 6. The air conditioning system “was incorrectly and inadequately designed for the purpose for which it was intended, that is, the adequate cooling of said 22 unit apartment, house.” 7. M.P.S., Inc. “reasonably and in good faith believed and relied upon the plans and specifications ... as representing a system which would be adequate to cool said apartment building by thirty degrees in extreme summer conditions;” M.S.F., Inc. was never asked to redesign the system. 8. The damages incurred by plaintiff’s assignors in endeavoring to remedy the problems which arose in connection with the air conditioning system were not the proximate result of any act or failure to act on the part of M.F.S., Inc. 9. “That by reason of the facts hereinabove set forth, it was physically impossible to furnish or produce an air conditioning system sufficient to cool said apartment building by thirty degrees in extreme summer conditions by following or complying with said plans and specifications. ’ ’

The function of this court with respect to the interpretation of a written contract is set forth in Parsons v. Bristol Development Co., 62 Cal.2d 861, at page 865 [44 Cal.Rptr. 767, 402 P.2d 839] : “The interpretation of a written instrument, even though it involves what might properly be called questions of fact (see Thayer, Preliminary Treatise on Evidence, pp. 202-204), is essentially a judicial function to be exercised according to the generally accepted canons of interpretation so that the purposes of the instrument may be given effect. (See Civ. Code, §§ 1635-1661; Code Civ. Proc., §§ 1856-1866.) Extrinsic evidence is ‘ admissible to interpret the instrument, but not to give it a meaning to which it is not reasonably susceptible’ [citations], and it is the instrument itself that must be given effect. (Civ. Code, §§ 1638, 1639; Code Civ. Proc., § 1856.) It is therefore solely a judicial function to interpret a written instrument unless the in *116 terpretation turns upon the credibility of extrinsic evidence. Accordingly, ‘An appellate court is not bound by a construction of the contract based solely upon the terms of the written instrument without the aid of evidence [citations], where there is no conflict in the evidence [citations], or a determination has been made upon incompetent evidence [citation].’ (Es tate of Platt, 21 Cal.2d 343, 352 [131 P.2d 825]

Evidence extrinsic to the subcontract and the bond was properly admitted at the trial to determine the circumstances under which the parties contracted and their purpose. (Parsons v. Bristol Development Co., supra, 62 Cal.2d 861, 864-865.) In the present case the uneontradieted evidence was that the plans and specifications, including those relating to the air conditioning work, were prepared for the owners by an architect licensed by the State of Nevada. The subcontractor relied thereon in submitting his proposal or bid. The first bond submitted by the subcontractor for the air conditioning work was rejected by the general contractor because it did not contain the following language (which is contained in the second bond, upon which the present action was brought) : “System is to establish at least a 30 degree variation from outside temperature for cooling and a fifty degree variation from outside temperature for heating. ...”

The primary question to be resolved on this appeal is whether the language quoted in the preceding paragraph of this opinion, as embodied in the subcontract and in the bond, constituted a warranty or guaranty on the part of the subcontractor that the air conditioning system which the subcontractor undertook to install would in fact “establish at least a 30 degree variation from outside temperature for cooling.” As has been noted, the trial court found that the proposal submitted to the general contractor by the subcontractor was prepared upon the basis of the plans and specifications drawn by the owners’ architect; the equipment specified in those plans and specifications, or the substantial equivalent thereof, was installed and all of the work necessary to furnish and complete the air conditioning system described in those plans and specifications ivas done by the subcontractor in a workmanlike manner; but, although the subcontractor reasonably and in good faith relied upon the adequacy of the plans and specifications as a representation of a system which would cool the apartment building by thirty degrees under summer conditions, the air conditioning system “was incorrectly and in *117 adequately designed for the purpose for which it was intended, that is, the adequate cooling of said 22 unit apartment house.” Those findings of fact have substantial support in the record.

In accordance with the reasoning of Parsons v. Bristol Development Co., supra, 62 Cal.2d 861, we have made our independent determination of the meaning of the subcontract and the bond. Our conclusion is that the subcontractor did not warrant or guarantee that the system embodied in the architect’s plans and specifications would produce the desired variation from outside temperature for the cooling of the apartment building.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ponce v. Philco Construction CA4/3
California Court of Appeal, 2014
Masonite Corp. v. Pacific Gas & Electric Co.
65 Cal. App. 3d 1 (California Court of Appeal, 1976)
Seck v. Foulks
25 Cal. App. 3d 556 (California Court of Appeal, 1972)
Silva & Hill Construction Co. v. Employers Mutual Liability Insurance
19 Cal. App. 3d 914 (California Court of Appeal, 1971)
Sunbeam Construction Co. v. Fisci
2 Cal. App. 3d 181 (California Court of Appeal, 1969)
Houghton v. Kerr Glass Manufacturing Corp.
261 Cal. App. 2d 530 (California Court of Appeal, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
251 Cal. App. 2d 112, 59 Cal. Rptr. 258, 1967 Cal. App. LEXIS 1952, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kurland-v-united-pacific-insurance-calctapp-1967.