Shell v. Schmidt

330 P.2d 817, 164 Cal. App. 2d 350, 76 A.L.R. 2d 792, 1958 Cal. App. LEXIS 1617
CourtCalifornia Court of Appeal
DecidedOctober 20, 1958
DocketCiv. 17407
StatusPublished
Cited by28 cases

This text of 330 P.2d 817 (Shell v. Schmidt) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shell v. Schmidt, 330 P.2d 817, 164 Cal. App. 2d 350, 76 A.L.R. 2d 792, 1958 Cal. App. LEXIS 1617 (Cal. Ct. App. 1958).

Opinion

ST. CLAIR, J. pro tem. *

Defendant appeals from a judgment against him in the amount of $47,400 in favor of the 24 plaintiffs.

The defendant is a builder-contractor. Plaintiffs are third party beneficiaries of a contract between the defendant and the United States Government and sue for a breach thereof.

Plaintiffs, 12 couples, bought similar houses in a tract built by defendant. The complaint originally alleged causes of action for fraudulent misrepresentation and breach of contract. On a prior appeal, the court held that the causes of action for fraudulent misrepresentation were not proved as to nine couples, but that causes for breach of contract were established for all. The judgments were “reversed with instructions to the trial court to retry the issue of damages only, and when such damages have been ascertained, to enter judgments in favor of respondents in the amounts so fixed.” (Shell v. Schmidt, 126 Cal.App.2d 279, 294 [272 P.2d 82].)

At the second trial plaintiffs waived their separate and individual causes of action for fraud and went to trial on a single cause of action by all plaintiffs, as third party beneficiaries, for breach of contract.

There was and is some difference of opinion as to what the law of the case is, as decided by the first opinion. All parties agreed, however, that it is the law of the ease that defendant breached the contract. The principal problem was the choice of the applicable measure of damages.

The first opinion established the measure of damages, in the general words of Civil Code, section 3300, and the trial court here quite properly instructed in those words. However, that did not answer the refinement thereof raised by the defendant.

At this trial it was the theory of the plaintiffs that the proper measure of damages was what will hereafter be re *352 ferred to as the cost theory, i.e., the cost of making the work conform to the contract. The defendant vigorously advanced what will hereafter be referred to as the value theory, i.e., the measure of damages is the difference between the value of the structure as planned and its value as built.

Before examining the contentions of the parties, a review of the record at the second trial is necessary; first, to look at certain offers of proof made by the defendant and, secondly, to determine if the defendant was in fact precluded from proving parts of his offer and the resultant effect, on defendant’s position, of the proof he made.

The principal items of deviation from the specifications that constituted the admitted breach of the contract were: (1) the exterior walls had no wood sheathing and consisted of construction paper covered with chicken wire and thereon an application of stucco; (2) the installation of one floor furnace of 35,000 B.T.U. capacity instead of two furnaces of 30,000 B.T.TJ. capacity each; and (3) the use of sheet rock with taped joints for the interior walls instead of gypsum lath and plaster.

In the first opinion the court said: “All testified that their homes were not only underheated, but that, because of the inadequate exterior walls, they became damp and cold, and that mold and mildew grew on the back room walls. The evidence is ample and substantial to the effect that largely because of the inadequate exterior walls, and partly because of the inadequate heating equipment, the plaintiffs were made quite uncomfortable, and did not receive a house of the quality and type called for by the plans and specifications.” (126 Cal.App.2d supra, 279, at 284.)

Plaintiffs advance this as the law of the case. Defendant disagrees.

Plaintiffs, without objection, at the second trial testified at length to the same facts. Some testified to the inferences referred to by the court. Certainly the defendant had in mind such inferences as he put in evidence to rebut them.

In addition to the above, plaintiffs put in experts who testified as to the cost of correcting the major breaches of the contract.

At the end of the plaintiffs’ case the defendant made several offers of proof. The offers were formalized twice, in chambers, and there was a great deal of discussion concerning them. The following would appear to be a fair statement of what the defendant offered to prove.

*353 As to the Three Breaches

1. Exterior wood sheathing. Defendant made every effort to obtain sheathing but was unable to do so. None was available. Experts would testify that the type of construction used (somewhat exotically known as bellyband type of construction) and the manner in which it was done was equally as good as wood sheathing, in fact, it was better because, at the time only green lumber was available and its shrinking would crack the stucco. Experts would say that the dampness was not a result of using bellyband construction instead of wood sheathing; it is a matter of atmosphere, a condition caused by the manner in which the houses were vented; it is a humidity problem that arises from many factors.

2. Interior walls. Defendant made every effort to obtain plastering labor and materials essential to plastering the walls but was unable to obtain the same. The wall board that was substituted for the plaster is equally as good and can be used under the applicable F.H.A. regulations.

3. The furnace. Defendant provided what he had been advised was a better heating system than the one called for in the contract. One floor type of 50,000 B.T.U. capacity is preferable for heating a house to two 30,000 B.T.U. capacity wall type furnaces. Defendant was able to put in the floor type furnace because he had put in the much better conventional type of foundation rather than the slab type called for in the specifications.

As to the Measure of Damages

Willfullness.

1. There was no willfullness or intentional action on defendant’s part in making the first two omissions in question. He was compelled to complete the houses the way he did because of the shortages of labor and material. Defendant orally reported his inability to get materials to F.H.A. and was orally authorized to go ahead with what he could get. (Exhibit A attached to plaintiffs’ complaint, a copy of application by defendant to F.H.A. for increase in selling price; this application showed some of the changes.)

2. Substantial performance. The houses, as built, are superior to the houses called for in the specifications, are of better construction and built on a better foundation.

3. Value. The houses as built were more valuable than the houses called for in the specifications. Certain of the plaintiffs *354 sold their houses at a higher price than was paid the defendant for them.

Defendant’s Evidence at the Second Trial

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Montara Owners Ass'n v. La Noue Development, LLC
317 P.3d 257 (Court of Appeals of Oregon, 2013)
First National Bank of Omaha v. Centennial Park, LLC
303 P.3d 705 (Court of Appeals of Kansas, 2013)
Cashman Equipment Corp. v. United States Fire Insurance
368 F. App'x 288 (Third Circuit, 2010)
MURRAY'S IRON WORKS, INC. v. Boyce
71 Cal. Rptr. 3d 317 (California Court of Appeal, 2008)
Harrison v. McMillan
828 So. 2d 756 (Mississippi Supreme Court, 2002)
Neil R. Harrison v. Fred L. McMillan
Mississippi Supreme Court, 1998
Mitchell v. Madison Enterprises, Inc., No. Cv 90 57188 S (May 21, 1997)
1997 Conn. Super. Ct. 5815 (Connecticut Superior Court, 1997)
Andrulis v. Levin Construction Corp.
628 A.2d 197 (Court of Appeals of Maryland, 1993)
Commercial Cabinet Co. v. Mort Wallin of Lake Tahoe, Inc.
737 P.2d 515 (Nevada Supreme Court, 1987)
Kangas v. Trust
441 N.E.2d 1271 (Appellate Court of Illinois, 1982)
Louison v. Yohanan
117 Cal. App. 3d 258 (California Court of Appeal, 1981)
Gerodetti v. Broadacres, Inc.
363 So. 2d 265 (Mississippi Supreme Court, 1978)
Tolstoy Constructor Co. v. Minter
78 Cal. App. 3d 665 (California Court of Appeal, 1978)
Glendale Federal Savings & Loan Ass'n v. Marina View Heights Development Co.
66 Cal. App. 3d 101 (California Court of Appeal, 1977)
LoBue v. State ex rel. Department of Highways
554 P.2d 258 (Nevada Supreme Court, 1976)
LoBue v. STATE, DEPARTMENT OF HIGHWAYS
554 P.2d 258 (Nevada Supreme Court, 1976)
Jones v. Kvistad
19 Cal. App. 3d 836 (California Court of Appeal, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
330 P.2d 817, 164 Cal. App. 2d 350, 76 A.L.R. 2d 792, 1958 Cal. App. LEXIS 1617, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shell-v-schmidt-calctapp-1958.