Knutson, Justice.

This is an appeal from an order of the court denying a motion of plaintiff and third-party defendant for amended findings or a new trial.

In 1952, defendants, who are husband and wife, acquired a tract of land in St. Paul for $5,500. They hired one James H. Speckmann to prepare plans and specifications for a single-family residence on this land. Speckmann was not a registered architect or engineer but had considerable practical experience in preparing plans and specifications for houses of this type. Thereafter a contract was let to plaintiff, a corporation with offices in St. Paul, for the construction of the house according to the plans and specifications prepared by Speck-[492]*492mann. The original contract price was $41,000, which later was raised to $43,996.52 as a result of changes made during the course of construction. Among other things, the contract contained the following provisions:

“1. Contractor agrees to erect upon said lot a home for the owners in accordance with the plans, specifications and working drawings prepared by James H. Speckman, 802 St. Paul Building, St. Paul, Minnesota, which plans and specifications are dated May 28, 1952 and bear the number 5209, and to that end will provide all materials and all labor necessary to complete said structure in accordance with said plans, specifications and working drawings, and Contractor further agrees to do everything required by the general conditions set forth in the specifications and plans, and to perform all of said work in a first class workmanlike manner. Contractor further agrees that the work under this contract will be started as soon as possible and practicable; that the work will be prosecuted diligently to completion without any delay on the part of the contractor; and that the work will be substantially completed on June 1, 1953.
“6. The parties agree that the plans and specifications hereinbe-fore referred to are a part of this contract the same as if incorporated at length herein.”

The specifications, among other things, provided:

“1. General Conditions Of The Contract # * # #
“Unless otherwise specified, all materials shall be new and all work-1 manship shall be of the first best quality.
íjí # # 5j<
“The Contractor shall provide and maintain protection of all of his| work from damage and shall protect the Owner’s property from injury or loss during the execution of the Contract. * * *
sjt jJ: s}s #
“2. Grading:
“(A) On all sides of the building, the Contractor shall bring thd finish grades to the lines shown on the drawings. All finish grades [493]*493shall slope away from the building to the natural grades, the topsoil being used for this purpose.
“13. Carpenter Work:
“(A) The Contractor shall provide all necessary labor and materials and perform all carpenter work of every nature whatsoever to be done. He shall lay out all work and be responsible for all measurements, and keep a competent foreman in charge at all times. All work shall be done in a first-class workmanlike manner, level, straight, plumb, and true, and in strict accordance with plans and specifications. Any discrepancies or errors that may be found on the plans, or in the specifications, shall be reported immediately to the Owner or Architect for correction. Under no circumstances shall an advantage be taken of said discrepancies or errors.
Ht * H< H*
“24. Extras Or Credits:
“(A) Any deviation from these specifications or plans involving an extra charge or credit must be agreed to in writing between the contracting parties before the change is made. The Contractor shall not take advantage of any discrepancies found. If any discrepancies are found they shall be referred to the Owner or Architect for correction immediately and in no case shall the Contractor proceed in doubt.”

During the course of construction, defendants paid plaintiff the sum of $38,738.58 to apply upon the contract, leaving a balance of $5,257.94. During the course of the trial, certain adjustments were conceded so that plaintiff contends that the actual balance due under the contract is $5,197.94.

Construction on the house was commenced on January 8, 1953. On January 12, 1953, plaintiff, as principal, and third-party defendant, Anchor Casualty Company, as surety, executed a construction bond with the usual conditions guaranteeing the performance of the contract according to its terms.

The house was so far completed that defendants were able to move into it on June 23, 1953. Defendant Victor Toushin, for a number of years, has acquired a great deal of model railroad equipment. As a hobby he has built much additional equipment, all according to scale. [494]*494This equipment was moved into the basement of the house a few days prior to occupancy thereof by defendants, and much of it, packed in paper cartons, was left on the floor of the basement or on tables. During the night of June 23 and the morning of June 24, there occurred a heavy rainstorm. A great deal of water entered the basement, apparently through two windows which had been left partly open, causing a flooding of the floor to a depth of from four to six inches. As a result, much of the model railroad equipment was ruined beyond repair or was so damaged that it is of little value. The record does not disclose whether plaintiff or defendants were responsible for leaving the windows open.

Plaintiff commenced this action to recover the balance due on the contract. Defendants claim that the house was not constructed properly according to the plans and specifications under which the contract was let to plaintiff. One of their main claims is that a steel post in the basement, which supports a beam on which the floor joists rest, was too low and that as a result there was a deflection in the level of the floor and that other parts of the house, including the roof, following this same deflection, sagged noticeably. They contend also that the yard was not graded to the proper slope, as a result of which the water ran into the basement causing much damage to the model railroad equipment.

The case was tried to the court without a jury. The court awarded damages to defendants on their counterclaim in the sum of $20,000 for failure to construct the house properly and $2,000 for damage to the model railroad equipment. Offset against this allowance was the sum of $5,075.94, which the court found was due on the contract, leaving a balance due defendants on their counterclaim of $16,924.06.

The questions presented here are: (1) Does the evidence sufficiently support the court’s finding that damage to the model railroad equipment was due to plaintiff’s negligent failure to grade the yard to the proper slope according to the contract? (2) Does the evidence support the court’s finding that the house was improperly constructed? (3) Was the proper measure of damages applied? (4) Does the evidence sustain the amount of damages awarded to defendants?

The first issue presents only a question of fact. It is defendants’ [495]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Joseph
636 N.W.2d 322 (Supreme Court of Minnesota, 2001)
Schneberger v. Apache Corp.
1994 OK 117 (Supreme Court of Oklahoma, 1994)
Rands v. Forest Lake Lumber Mart, Inc.
402 N.W.2d 565 (Court of Appeals of Minnesota, 1987)
Fudally v. Ching Johnson Builders, Inc.
360 N.W.2d 436 (Court of Appeals of Minnesota, 1985)
Elk River Enterprises, Inc. v. Adams
357 N.W.2d 139 (Court of Appeals of Minnesota, 1984)
Julian Johnson Construction Corp. v. Parranto
352 N.W.2d 808 (Court of Appeals of Minnesota, 1984)
Vreeman v. Davis
348 N.W.2d 756 (Supreme Court of Minnesota, 1984)
Subsurfco, Inc. v. B-Y Water District
337 N.W.2d 448 (South Dakota Supreme Court, 1983)
Northern Farm Supply, Inc. v. Sprecher
307 N.W.2d 870 (South Dakota Supreme Court, 1981)
Hunt Bros. Construction, Inc. v. Wolcott
580 P.2d 418 (Idaho Supreme Court, 1978)
A. F. Conner & Sons, Inc. v. Tri-County Water Supply Corp.
541 S.W.2d 856 (Court of Appeals of Texas, 1976)
City of Eveleth v. Ruble
225 N.W.2d 521 (Supreme Court of Minnesota, 1974)
Northern Petrochemical Co. v. Thorsen & Thorshov, Inc.
211 N.W.2d 159 (Supreme Court of Minnesota, 1973)
Jackson v. Buesgens
186 N.W.2d 184 (Supreme Court of Minnesota, 1971)
County of Tarrant v. Butcher & Sweeney Construction Co.
443 S.W.2d 302 (Court of Appeals of Texas, 1969)
Marshall v. Marvin H. Anderson Construction Co.
167 N.W.2d 724 (Supreme Court of Minnesota, 1969)
Breza v. Thaldorf
149 N.W.2d 276 (Supreme Court of Minnesota, 1967)
Crea v. Hall
122 N.W.2d 610 (Supreme Court of Minnesota, 1963)
Prodger v. Zell
113 N.W.2d 168 (Supreme Court of Minnesota, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
85 N.W.2d 273, 250 Minn. 490, 1957 Minn. LEXIS 653, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hp-droher-sons-v-toushin-minn-1957.