City of Eveleth v. Ruble

225 N.W.2d 521, 302 Minn. 249, 1974 Minn. LEXIS 1180
CourtSupreme Court of Minnesota
DecidedDecember 6, 1974
Docket44336
StatusPublished
Cited by36 cases

This text of 225 N.W.2d 521 (City of Eveleth v. Ruble) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Eveleth v. Ruble, 225 N.W.2d 521, 302 Minn. 249, 1974 Minn. LEXIS 1180 (Mich. 1974).

Opinion

Sheran, Chief Justice.

Appeal from an order of the St. Louis County District Court denying the motion of defendants-appellants for amended findings and conclusions or a new trial and from the judgment then entered.

Plaintiffs-respondents, the City of Eveleth and the Public Utilities Corporation of Eveleth (hereinafter called the City), sued to recover damages from defendants-appellants, Earl Ruble, Jerome Miller, Earl H. Ruble & Associates, and Ruble and Kaple, Inc. (hereinafter called the Engineer), for alleged negligence and breach of contract in the design of a new water treatment plant. 1 The significant issue raised by the appeal is whether the *252 evidence justifies so much of the award in plaintiffs’ favor as is based on (a) an allowance of damages in the amount of approximately $23,500 for failure to design an intake system adequate to meet the anticipated requirements of the City, and (b) an allowance of damages in the amount of $9,500 for failure to specify and provide for pumping equipment designed in such a way as to eliminate destructive pressures in the distribution lines of the City’s water system.

The factual background begins in 1962 when the City, persuaded that its system of diverting water from St. Mary’s Lake for treatment, storage, and use was inadequate for current and anticipated needs, retained the Engineer to furnish an engineering report and preliminary plans for a water treatment facility to replace the one then in operation. By the terms of the agreement, the Engineer was obligated to prepare and complete plans and specifications, estimates of cost, and the contract documents. It agreed “to assist the owner in obtaining compliance with the contract documents” but did not “guarantee the performance of the contract by the contractor.” It was to afford what is termed “resident construction observation.”

The specifications were prepared. Bids were let. On May 12, 1964, the construction contract for the planned facility was executed. On April 29, 1968, the plant became operational.

After operation of the new facility commenced, performance was found to be unsatisfactory in a number of respects, including these two: (1) The intake capacity of the water treatment plant proved to be inadequate; (2) pressures in the cast-iron distribution lines leading from the water treatment plant to users and to storage facilities apparently caused some of the leaded joints in the line to give way. The allowances for damages made by the trial court because of these deficiencies require a statement of the principles of law which apply in an action such as this one against a professional engineer for errors and omissions and an *253 assessment of the evidence presented at trial considered in light of these principles.

The Legal Principles

These legal principles are applicable to the issues to be considered :

(1) One who undertakes to render professional services is under a duty to the person for whom the service is to be performed to exercise such care, skill, and diligence as men in that profession ordinarily exercise under like circumstances. 2

*254 (2) The circumstances to be considered in determining the standard of care, skill, and diligence to be required in this case include the terms of the employment agreement, the nature of the problem which the supplier of the service represented himself as being competent to solve, and the effect reasonably to be anticipated from the proposed remedies upon the balance of the system. 3

(3) Ordinarily, a determination that the care, skill, and diligence exercised by a professional engaged in furnishing skilled services for compensation was less than that normally possessed and exercised by members of that profession in good standing and that the damage sustained resulted from the *255 variance requires expert testimony to establish the prevailing standard and the consequences of departure from it in the case under consideration. 4

(4) There are some situations in which a trier of fact may, without the aid of expert testimony, find damages to have been caused by the failure of a professional to exercise reasonable care, skill, and diligence. If the solution proposed by the professional is one which the professional would not have proposed had he been fully informed as to the facts of the problem with which he was dealing, and if it is clear that the failure of the professional to ascertain the facts before recommending a solution to the problem was an omission inconsistent with the professional obligation assumed, a finding of negligence may be made without the benefit of precise scientific opinion testimony. If it is clear without resort to expert opinion that this error or omission on the part of the professional resulted in damage, and if the causation can be established, and if the damage can be measured by *256 persons of ordinary learning and understanding, the opinions of experts are not needed. 5

In the ease before us, except for broad generalizations of the obvious, there is an absence of the definitive expert testimony required by the general rule. The responsibilities of the trier of fact would have been less burdensome if the findings of negligence made in this case had been based upon expert opinion. But since we do not find it in the record, we deal with the question of whether the findings of negligently caused damages can be sustained without it, the standards for review being as stated in In re Estate of Balafas, 293 Minn. 94, 198 N. W. 2d 260 (1972). 6

I. Intake Capacity

We believe that the trial court was justified in finding, without the aid of expert testimony, that the Engineer’s errors and omissions constituted negligence and resulted in an inadequate intake capacity, to the City’s damage in the amount of approximately $23,500.

By the terms of the October 1962 agreement between the Engineer and the City, the Engineer was obligated to analyze the piping, valving, and structural characteristics of the existing plant so as to establish desirable changes to provide effective sanitary and economic operation and to determine a more suit *257 able means for increasing water plant output of properly treated water. The Engineer knew, or had reason to know, that the City was motivated to expend substantial sums for a new water plant in order to increase the intake capacity of the works to a level of approximately 2,500 gallons per minute. Being aware of the City’s expectations as to the intake capacity of the new plant, the Engineer recommended that the then existing system, whereby the City’s water supply was diverted from St.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mci Commc'ns, Inc. v. Maverick Cutting & Breaking LLC
374 F. Supp. 3d 789 (D. Maine, 2019)
Valley Paving, Inc. v. Stanley Consultants, Inc.
Court of Appeals of Minnesota, 2016
Superior Edge, Inc. v. Monsanto Co.
44 F. Supp. 3d 890 (D. Minnesota, 2014)
Minnesota Pipe & Equipment Co. v. Ameron International Corp.
938 F. Supp. 2d 862 (D. Minnesota, 2013)
Ferris & Salter, P.C. v. Thomson Reuters Corp.
889 F. Supp. 2d 1149 (D. Minnesota, 2012)
Ferris & Salter, P.C. v. Thomson Reuters Corp.
819 F. Supp. 2d 667 (E.D. Michigan, 2011)
Pond Hollow Homeowners Ass'n v. Ryland Group, Inc.
779 N.W.2d 920 (Court of Appeals of Minnesota, 2010)
Middle River-Snake River Watershed District v. Dennis Drewes, Inc.
692 N.W.2d 87 (Court of Appeals of Minnesota, 2005)
Blatz v. Allina Health System
622 N.W.2d 376 (Court of Appeals of Minnesota, 2001)
Minnesota Forest Products, Inc. v. Ligna MacHinery, Inc.
17 F. Supp. 2d 892 (D. Minnesota, 1998)
Minneapolis Employees Retirement Fund v. Allison-Williams Co.
519 N.W.2d 176 (Supreme Court of Minnesota, 1994)
Center Ct. Assoc. v. maitland/strauss Behr, No. Cv-86-252381 (May 4, 1994)
1994 Conn. Super. Ct. 4792 (Connecticut Superior Court, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
225 N.W.2d 521, 302 Minn. 249, 1974 Minn. LEXIS 1180, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-eveleth-v-ruble-minn-1974.