Ressler v. Nielsen

76 N.W.2d 157, 1956 N.D. LEXIS 111
CourtNorth Dakota Supreme Court
DecidedMarch 29, 1956
Docket7525
StatusPublished
Cited by11 cases

This text of 76 N.W.2d 157 (Ressler v. Nielsen) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ressler v. Nielsen, 76 N.W.2d 157, 1956 N.D. LEXIS 111 (N.D. 1956).

Opinions

SATHRE, Judge.

The plaintiff brings this action against the defendant to recover commissions claimed to be earned for the preparation of plans and specifications and supervision of the construction of a building belonging to the defendant located at Bismarck, North Dakota, known as the Admiral Hotel. The complaint alleges that the plaintiff is an architect and during the month of April 1948 he entered into an oral agreement with the defendant by the terms of which the plaintiff agreed to draw plans and specifications for a hotel building known as the Admiral Hotel located on lot 19, block 44, original plat of the City of Bismarck, North Dakota, and to supervise the construction of said building, and that plaintiff’s commission was to be 5% of the cost of the building. After the work of supervision and construction had continued for some time the parties entered into another oral agreement whereby it was agreed that thereafter the defendant would take over supervision of the construction of the building and that from there on the commission of the plaintiff as architect should be reduced to 3% of the remaining cost of the construction. The complaint alleges that during the time that plaintiff supervised the building there was expended thereon the total sum of $16,250. It is then alleged that the remaining cost of the building was $62,000, and that the plaintiff was entitled to 3% commission upon said sum. The complaint then alleges that the said amount has not been paid except the sum of $500 and that there is still due and owing to the plaintiff the sum of $2,172.

Plaintiff then demands judgment for said amount and that he be adjudged and decreed to have a lien upon the said building described in the complaint which lien was to be junior and inferior to the mortgage to the defendant First Federal Savings & Loan Association and that it be decreed that said premises be sold by the sheriff of said Burleigh County according to law and that from the proceeds of said sale and after deducting costs and expenses the plaintiff be paid the amount aforesaid and that he may become a purchaser at any such sale.

The answer denies generally the allegations in plaintiff’s complaint. It alleges that [159]*159after certain material had been ordered, it became apparent that the plaintiff was not qualified to supervise the construction of the building; that the parties then entered into an oral agreement or contract whereby the plaintiff was to receive only 3% commission for his services for drawing suitable plans and specifications; that the total cost of such building was $70,000, and that the plaintiff’s fees for services, if such services had been competently performed, would have been $2,100; that the defendant has paid $500 upon the claim of the plaintiff.

As a further answer and by way of counterclaim it is alleged that the drawings, plans and specifications prepared by the plaintiff were carelessly, negligently and incompetently drawn and prepared; that the defendant in relying upon plaintiff’s representation was greatly damaged in the construction of his building, all because of the negligence, incompetence and lack of knowledge and skill of plaintiff in preparing and drawing the plans and specifications for the building. The answer then alleges the following items of damages as a counterclaim:

The dimensions of the elevator pit were not specified, and that it became necessary to dig a pit by hand at an additional cost to defendant in the sum of $551.

That the specifications placed certain water pipes in the ventilating system causing them to freeze and burst at a replacement cost to defendant of $1,000.

That certain copper steam pipes were laid under the cement floor in the basement of the building and that some of said pipes became leaky, and that defendant has been advised that said pipes have to be abandoned or new pipes installed at a cost of $1,200.

That the window grates for the basement windows did not fit, and that the cost of repairing same will be $100.

That the radiators in the lobby of the hotel were placed near the plate glass windows so that the cold on the outside and the heat on the inside caused said windows to bréale resulting in damage to defendant in the sum of $546.

That the electrician followed plaintiff’s plans and specifications in placing the lights in the hall of the building in wrong places, requiring defendant to relocate them at a cost of $200.

That plaintiff had made incorrect measurements of certain granite blocks, making it necessary for defendant to make two trips to St. Cloud, Minnesota, for the purpose of. recutting said granite blocks at a cost of $200.

That the total of said items is in the sum of $3,597 which defendant claims as a counterclaim.

Plaintiff’s reply to the defendant’s counterclaim denies expressly any negligence or lack of competence on his part in any way in drawing the plans and specifications or in the supervision of said building, and denies specifically that the defendant suffered any loss or damage whatsoever due to plaintiff’s fault, negligence or incompetence or carelessness.

The case was tried in the district court of Burleigh County, North Dakota, before the Hon. Geo. Thom, Jr., district judge, without a jury. The district court found for the plaintiff and held that there were two oral contracts; that the parties first agreed that the plaintiff was to be paid a commission of 5% on the cost of the building as compensation for drawing the plans and specifications and supervising the construction thereof. The parties then entered into a second oral agreement or contract whereby it was agreed that the defendant himself would supervise the construction and that the plaintiff was to be allowed 3% commission on the remainder of the cost of the building. The district court found that while the plaintiff was supervising the construction of the building there was expended thereon the sum of $9,707 for which the plaintiff was entitled to a commission of 5%. That trial court further found that the remainder of the cost of the building, the construction of which was supervised by the defendant [160]*160himself, was in the sum of $60,292 for which the plaintiff was allowed a commission of 3%. The total amount of commission earned by the plaintiff under said oral agreement was the sum of $2,294 of which $500 had been paid, leaving a balance due the plaintiff in the sum of $1,794. The district court disallowed the items of the counterclaim of the defendant, except the item of cutting of the granite blocks for which it allowed the defendant the sum of $100 leaving a balance due the plaintiff of $1,694.

It is stipulated by the parties that the plaintiff had duly filed a mechanic’s lien for the amount claimed to be due from the defendant and a copy thereof was admitted in evidence as plaintiff’s exhibit 5.

Judgment was entered in favor of the plaintiff in the sum of $1,694 and interest and for foreclosure of plaintiff’s mechanic’s lien upon lot 19, block 44, original plat of the City ,of Bismarck, North Dakota, but said judgment was made subordinate to the mortgage of the defendant First Federal Savings & Loan Association of Bismarck, North Dakota. The defendant appealed from the judgment and demanded a trial de novo.

It is undisputed that plaintiff is an architect and that he had studied architectural engineering at the agricultural college at Fargo, North Dakota, for three years and that the last year he was there was in 1904. He then went to St.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
76 N.W.2d 157, 1956 N.D. LEXIS 111, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ressler-v-nielsen-nd-1956.