Smith v. Goff

1958 OK 100, 325 P.2d 1061, 1958 Okla. LEXIS 412
CourtSupreme Court of Oklahoma
DecidedApril 15, 1958
Docket37942
StatusPublished
Cited by17 cases

This text of 1958 OK 100 (Smith v. Goff) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smith v. Goff, 1958 OK 100, 325 P.2d 1061, 1958 Okla. LEXIS 412 (Okla. 1958).

Opinion

PER CURIAM.

The plaintiffs in error, plaintiffs below, are the owners of certain property in Norman, Oklahoma, on which they have had constructed a home. The contracts which form the basis of this action were negotiated for the purpose of constructing this home. Two agreements are involved: that between the plaintiff owners and the defendant architects, and that between the plaintiff owners and the defendant contractor who built the dwelling. We shall refer to the parties by their contractual status as owners, architects and contractor, respectively.

In August, 1950, owners and architects entered into a written contract providing for architects to furnish “complete architectural services including preliminary plans, working drawings and specifications, and periodic supervision for a residence to be built * * * ” at an “intended cost of $9,000.00 * * However, it was also provided that the “Architect does not guarantee the cost but will make any revisions in his plans made necessary by excessive costs or unavailability of materials * * Pursuant to this contract, architects furnished a plan and specifications for a residence. When bids were taken on this plan, the lowest bid received amounted to $16,000 which owners felt was more than they could afford and which resulted from including everything in the plan that owners wanted to have in their home. Architects thereupon made certain revisions in the plan and specifications, and contractor submitted a second bid of $14,000 which was likewise more than owners wanted to invest. Nevertheless, against their architects’ advice that they should wait until prices stabilized, owners desired to build a house immediately and substantially the *1063 same as the original floor plan prepared by architects. In conversations with architect and builder it was decided that such a floor plan and structural design could be constructed at a substantially lower cost by changing the specifications and using less expensive material. Thereupon, because the owners did not want to go through another war without a home of their own, the owners and contractor entered into their contract wherein it was provided that in consideration of $10,500 “The contractor shall furnish all the material (except certain specific items) and perform all the work necessary in the construction of the residence * * * in accordance with the drawings and simplified method of construction to be furnished by Bruce A. Goff, architect, and C. J. Powell, contractor.” It was also provided “that the contractor shall employ methods approved by Bruce A. Goff in order to maintain the initial effect of the building and floor plans as shown in the drawings, and at the same time, keep the cost down to the mentioned sum.” Another provision required diligent completion “in a good and workmanlike manner.” There were no exhaustive specifications compiled and attached to this agreement. Instead, certain notes were placed on a floor plan (plaintiffs’ Exhibit 6 which was introduced but is not included in the record) from which architect and contractor more or less improvised as construction proceeded so that they could meet owners’ desire for this house plan and at the same time overcome both the difficulties of monetary limitation and the material shortage produced by the Korean conflict.

After the house was completed and occupied by owners, and the contractor and architects paid, owners began to discover the items enumerated in their petition which it is alleged are defects which violate the provisions of their contracts. In substance, their petition alleges liability “jointly and severally” by architects for failing to use reasonable skill and diligence, and by contractor for failing to construct in a workmanlike manner. They also predicated liability of the defendants upon their alleged fraudulent concealment of the fact that the residence was not constructed in accordance with the plans and specifications in the contract. The case was tried to a jury. At the close of plaintiffs’ evidence, defendant contractor demurred, and this demurrer was sustained. The case proceeded to a verdict of the jury in favor of the architects. Plaintiffs appeal.

It is urged that the court erred in sustaining the contractor’s demurrer to the evidence. This position is well taken. In addition to the alleged failure to follow the plan and specifications in the construction of the house, about which we will have more to say later, liability against contractor was also predicated on a failure to build in a workmanlike manner. Respecting this phase, there was testimony of several witnesses for plaintiffs concerning the lack of quality in workmanship as displayed by several of the items alleged as defects in the completed structure. Some of these alleged defects could be explained upon other grounds than poor workmanship, but this was an issue of fact to be resolved by the jury. The defendant contractor argues that the building was accepted by the architect, the agent of the owners, and that the architect’s acceptance binds the owners in the absence of fraud or mistake. The foregoing general rule is not applicable to this action. Here, there is no contractual provision calling for acceptance by the architect or requiring that the work shall be done to his satisfaction. The rule contended for is only applicable where the contractual provisions of the construction contract make an acceptance by the architect a prerequisite. Mercantile Trust Co. v. Hensey, 205 U.S. 298, 27 S.Ct. 535, 51 L.Ed. 811, 10 Ann.Cas. 572. Whether contractor employed “methods approved by Bruce A. Goff in order to maintain the initial effect of the building” is not the same question as whether those construction methods were employed by contractor in a “good and workmanlike manner” as was likewise required by their contract. This question must be resolved *1064 by the jury. Wright v. Turner, Okl., 301 P.2d. 364.

We now proceed to a consideration of the judgment in favor of the architects. Much of plaintiffs’ argument is bottomed on an assumption that the written specifications first promulgated by architect were those to be used in the construction. This assumption is contrary to the architects’ contract and the contract under which the house was built. The first provided that architect would revise specifications to reduce excessive costs if necessary, and the second provided for a $10,500 price and “drawings and simplified method of construction to be furnished.” (Emphasis supplied.) The court properly excluded the original specifications, for they were not incorporated in the construction contract; and, as the undisputed evidence disclosed, they were not used by architect in the construction because the property could not be built under them within an amount the owners could afford to pay. The specifications used in the construction, it is obvious from the testimony, were not the same as the original specifications because it was necessary that materials be purchased and used according to their availability and cost.

With the foregoing factual situation in mind the various assignments of error may be disposed ' of more briefly. So far as plaintiffs’ action is based upon the allegations of fraud, it lacks evidentiary support.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cruet v. Carroll, No. X06-Cv-00-0166704s (Nov. 27, 2001)
2001 Conn. Super. Ct. 15941-jq (Connecticut Superior Court, 2001)
Howard v. Usiak
775 A.2d 909 (Supreme Court of Vermont, 2001)
Boren v. Thompson & Associates
2000 OK 3 (Supreme Court of Oklahoma, 2000)
Greenhaven Corp. v. Hutchcraft & Associates, Inc.
463 N.E.2d 283 (Indiana Court of Appeals, 1984)
Waggoner v. W & W STEEL CO.
1982 OK 141 (Supreme Court of Oklahoma, 1982)
Keel v. Titan Construction Corp.
1981 OK 148 (Supreme Court of Oklahoma, 1981)
Miller v. City of Broken Arrow
660 F.2d 450 (Tenth Circuit, 1981)
Southern, School Buildings, Inc. v. Loew Electric, Inc.
407 N.E.2d 240 (Indiana Court of Appeals, 1980)
City of Mounds View v. Walijarvi
263 N.W.2d 420 (Supreme Court of Minnesota, 1978)
P.E.A.C.E. Corp. v. Oklahoma Natural Gas Co.
1977 OK 151 (Supreme Court of Oklahoma, 1977)
Dentco Investment Co. v. Oklahoma Natural Gas Co.
1976 OK CIV APP 44 (Court of Civil Appeals of Oklahoma, 1976)
City of Eveleth v. Ruble
225 N.W.2d 521 (Supreme Court of Minnesota, 1974)
Rigsby v. Brighton Engineering Company
464 S.W.2d 279 (Court of Appeals of Kentucky (pre-1976), 1970)
Telak v. Maszczenski
237 A.2d 434 (Court of Appeals of Maryland, 1968)
Wills v. Black and West, Architects
1959 OK 162 (Supreme Court of Oklahoma, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
1958 OK 100, 325 P.2d 1061, 1958 Okla. LEXIS 412, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smith-v-goff-okla-1958.