Mci Commc'ns, Inc. v. Maverick Cutting & Breaking LLC

374 F. Supp. 3d 789
CourtDistrict Court, D. Maine
DecidedMarch 12, 2019
DocketCivil No. 17-1117 (JRT/SER)
StatusPublished
Cited by4 cases

This text of 374 F. Supp. 3d 789 (Mci Commc'ns, Inc. v. Maverick Cutting & Breaking LLC) is published on Counsel Stack Legal Research, covering District Court, D. Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mci Commc'ns, Inc. v. Maverick Cutting & Breaking LLC, 374 F. Supp. 3d 789 (D. Me. 2019).

Opinion

JOHN R. TUNHEIM, Chief Judge

Plaintiffs MCI Communications Services, Inc. and MCImetro Access Transmission Services, LLC (collectively "MCI") bring an action for trespass, negligence, and statutory liability as an excavator against Maverick Cutting and Breaking LLC ("Maverick"), who severed two of MCI's fiber-optic telecommunications cables while performing concrete saw cutting at an intersection. MCI seeks damages for repair costs and loss of use.

Maverick now moves for summary judgment on all of MCI's claims and on loss-of-use damages. Maverick also seeks to exclude portions of MCI expert Ron Peterson's testimony, all of MCI expert Peter Tooley's testimony, and evidence of the rental cost of substitute cables. MCI seeks *795to exclude Maverick expert Steven Hamilton's testimony.

The Court will grant Maverick's Motion for Summary Judgment in part and deny it in part. The Court will find that MCI is not entitled to loss of use damages and that no genuine disputes of material fact remain as to trespass or as to negligence based on contractual duties or a saw cutter industry standard of care. However, the Court will find that a genuine dispute of material fact remains as to whether Maverick was engaged in excavation under Minnesota statute and the common law. As such, a jury must determine whether Maverick is liable as an excavator under Minnesota statute or in negligence based on an excavator industry standard of care.

The Court will grant Maverick's Motion in Limine in part and deny it in part. The Court will preclude Peterson's testimony on contract interpretation, what Brooks did when installing the Cables, and saw cutter industry standards of care. The Court will also preclude Tooley's testimony and evidence of rental cost of substitute cables because both are irrelevant given the Court's ruling on loss-of-use damages.

The Court will grant MCI's Motion in Limine in part and deny it in part. The Court will preclude Hamilton from testifying as to saw cutter industry standards of care.

BACKGROUND

I. FACTUAL BACKGROUND

In the spring of 2015, the City of St. Paul (the "City") began construction on a public works project (the "Project") to maintain and improve several bridges.

A. The Players

Brent Christensen, a civil engineer, was the City's manager of the Project. (See First Aff. of Rachel Beauchamp ("1st Beauchamp Aff.") ¶ 3, Ex. A ("Christensen Aff.") ¶¶ 1-2, 5, July 5, 2018, Docket No. 38.) The City hired TKDA to design the Project and provide professional engineering services for the Project. (Id. ¶ 6.) TKDA was responsible for compiling information regarding utilities that might be impacted by the Project and coordinating solutions to identified conflicts. (1st Beauchamp Aff. ¶ 4, Ex. B ("Quanbeck Aff.") ¶¶ 1, 3.)

Kraemer North America, LLC, ("Kraemer") was the general contractor on the Project. (1st Beauchamp Aff. ¶ 8, Ex. F ("Rosenberry Dep.") at 14-15.) Kraemer hired Bolander & Sons ("Bolander") for excavating and demolition, which included pavement removal and grading for new roadway pavements. (Beauchamp Aff. ¶ 9, Ex. G ("Caroon Dep.") at 8.)

Bolander hired Maverick via oral contract to perform saw cutting for the project. (Id. at 6.) Bolander told Maverick where to cut and how deep to cut. (Id. ) Maverick performs about 90% of Bolander's concrete saw cutting work. (Id. at 5.) According to Bolander, Maverick's work involved only saw cutting, did not involve pavement removal or grading, and did not involve excavating. (Id. at 8.) Maverick asserts that its only job was to cut where Bolander directed and that it did not deal with utilities or their location. (1st Beauchamp Aff. ¶ 13, Ex. K ("Lewis Dep.") at 4, 11.)

MCI is a telecommunications company that owns and operates underground fiber optic telecommunications cables in and under various streets in the City. (Compl. ¶¶ 9-10, Apr. 11, 2017, Docket No. 1.)1

*796MCI owned the Cables that Maverick cut. Brooks Fiber Communications ("Brooks"), MCI's predecessor-in-interest, originally installed the Cables in 1997 or 1998. (See Decl. of James J. Proszek ("Proszek Decl.") ¶ 4, Ex. 1 ("As-Builts"), July 26, 2018, Docket No. 48; Proszek Decl. ¶ 5, Ex. 2 ("1st RFA") at 10.)

B. The Preparations

On April 26, 2013, TKDA sent a Gopher State One Call ("GSOC") ticket requesting utility maps in the Project area. (Quanbeck Aff. ¶ 5.) MCI produced an internal document indicating "Action Taken" in response to TKDA's request related to the intersection of Kellogg and Wabasha (the "Intersection") on May 1, 2013. (1st Beauchamp Aff. ¶ 5, Ex. C; Proszek Decl. ¶ 10, Ex. 7 at 7-9.) MCI alleges that it sent "as-builts"2 of the Intersection but produced no records to show that TKDA received them. (Proszek Decl. ¶ 10, Ex. 7 at 7-9; see also 1st Beauchamp Aff. ¶ 6, Ex. D ("Wilfong Dep.") at 42-43.) TKDA has no record of receiving anything and the GSOC ticket of utility owner responses shows MCI had not responded as of May 20, 2013. (Quanbeck Aff. ¶ 6.)

On January 16, 2014, TKDA invited MCI to attend a utility coordination meeting. (Id. ¶ 9.) The invitation referenced the Project area and attached drawings, which showed the Intersection. (Id. ) MCI did not attend the meeting. (Id. ¶ 10.)

On March 25, 2015, Bolander submitted a GSOC request for a "meet and locate" on March 31, 2015, for "road construction" at the Intersection. (1st Beauchamp Aff. ¶ 10, Ex. H at 3.) The request expired April 14, 2015, at 9:00 a.m. and the duration of the work was listed as 6 months. (Id. ) MCI locator Vince Johnson performed the meet and locate, marking the approximate horizontal locations of MCI's underground cables. (1st Beauchamp Aff. ¶ 11, Ex. I ("Johnson Dep.") at 8.)

Johnson testified that MCI has as-builts available to internal locators that they can refer to if they "have a question about where the line might possibly run...." (Id. at 3-4.) He testified that as-builts might give a depth location or estimate "if the depth features [of the cables] are unusual...." (Id. at 3.) But Johnson testified that he typically only consults as-builts when locating in an area with which he is unfamiliar. (Id. at 5.) He further testified that the "receiver" used by locators to find the cables can give you a "very, very general idea of depth." (Id. at 6.) The depth measurement setting must be separately turned on, but taking such a measurement does not cost anything. (Id. ) Johnson testified that locators do not usually give depth readings to contractors because they do not want contractors to rely on them. (Id. ) There is no evidence that Maverick or Bolander asked Johnson for depth information or that Johnson was required to mark depth under Minnesota law. See Minn. Stat. § 216D.04, subd. 3 (2018).

MCI asserts that the contracts between the City and Kraemer and between Kraemer and Bolander required that all subcontractors comply with all the requirements of the City's specifications and drawings for the Project. (Proszek Decl. ¶ 12, Ex.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
374 F. Supp. 3d 789, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mci-commcns-inc-v-maverick-cutting-breaking-llc-med-2019.