Middle River-Snake River Watershed District v. Dennis Drewes, Inc.

692 N.W.2d 87, 2005 Minn. App. LEXIS 180, 2005 WL 354013
CourtCourt of Appeals of Minnesota
DecidedFebruary 15, 2005
DocketA04-825
StatusPublished
Cited by6 cases

This text of 692 N.W.2d 87 (Middle River-Snake River Watershed District v. Dennis Drewes, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Middle River-Snake River Watershed District v. Dennis Drewes, Inc., 692 N.W.2d 87, 2005 Minn. App. LEXIS 180, 2005 WL 354013 (Mich. Ct. App. 2005).

Opinion

OPINION

LANSING, Judge.

In this dispute over the construction of a floodwater impoundment system, the contractor challenges two district court orders: its grant of summary judgment dismissing a counterclaim against the project engineer and its decision to cap damages. Because we find no error in the district court’s dismissal of the contractor’s counterclaim for failure to serve an expert-identification affidavit as required by Minn.Stat. § 544.42, subds. 2 and 4 (2004), we do not reach the damages issue, and we affirm.

FACTS

Middle River-Snake River Watershed District contracted with Dennis Drewes, Inc., to work on the Angus Oslo flood-impoundment project. After submitting its initial bid, Drewes inspected the project site several times and examined soil reports accompanying the project proposal. These soil reports, prepared by Midwest Testing Laboratory, indicated that the soil was “moist” and therefore ideal for construction. At the time of bidding, the site appeared undisturbed by farm operations, and the contract did not refer to ongoing farming operations.

The contract, in compliance with statutory requirements, appoints a project.engineer, J.O.R. Engineering, Inc., and describes the project engineer’s role. J.O.R. is not, however, a party to the contract. The contract sets forth specifications for the work, provisions for changed conditions, and responsibilities of the parties. It requires the contractor to achieve an overall compaction of 95% and prohibits lifts greater than twelve inches in height.

The contract explicitly addresses the work alterations and changed site conditions that relate to this litigation. If the contractor discovers a materially different site condition that affects its work, the contract requires it to provide written notice to the engineer and the other party before performing the affected work, particularly if the contract adjustment requires additional compensation. After acknowledging that the engineer shall have the right to modify specifications as circumstances may require, the contract provides that “[i]n this event, ... no change shall be made that will ... increase the total cost by more than ten percent (10%) of the total contract price.” The contract explains the engineer’s authority and responsibilities, including its involvement in developing the plan’s specifications and monitoring the site, but notes in several places that the engineer’s review of the work and specifications does not relieve Drewes of its contractual obligations.

After beginning work on the project, two independent problems arose. First, the soil was wetter than anticipated. Second, a neighboring farmer, who had a lease with the watershed district, disked the project site. The combined effect of the disking and the wet soil made it more difficult to obtain the required compaction and caused Drewes to use lifts greater than twelve inches in height. Drewes, however, did not notify either J.O.R. or the watershed district of the changed conditions before working on the affected areas.

Upon discovering that neither the compaction nor the lift heights complied with the contract’s specifications, the watershed *89 district filed a declaratory action to determine the rights and respo'nsibilities of the parties under the contract. In its answer to the complaint, Drewes asserted multiple counterclaims against the watershed district. Drewes also impleaded J.O.R. as an “additional defendant on the counterclaim,” alleging three causes of action: negligence, estoppel, and tortious interference with its contract. The watershed district moved for summary judgment on Drewes’ counterclaims. J.O.R. also moved for summary judgment because, among other reasons, Drewes failed to serve a mandatory expert-identification affidavit.

The district court initially denied J.O.R.’s and the watershed district’s summary-judgment motions, but the motions were twice renewed. In the first renewal, the watershed district grouped them with a motion in limine to cap damages. The district court granted the motion to cap damages but again denied summary judgment against Drewes. Shortly before the second renewal, Drewes and the watershed district resolved their “respective claims against each other” and stipulated to dismissal. The stipulation preserved Drewes’ claim against J.O.R. Following the second renewal, initiated by J.O.R., the district court granted summary judgment for J.O.R. for three reasons: (1) Drewes failed to comply with the expert-witness disclosure requirements in Minn.Stat. § 544.42 (2004); (2) J.O.R. owed no duty to Drewes; and (3) the alleged breach did not proximately cause the harm suffered.

The district court’s summary-judgment order, in addition to dismissing Drewes’ negligence “counterclaim” against J.O.R., also dismissed Drewes’ claim for estoppel and intentional interference with contractual relations. Drewes appeals from that part of the summary judgment dismissing his negligence claim against J.O,R. and also appeals the district court’s earlier order that capped the amount of damages that could be recovered.

■ISSUES

I. Did the district court err in dismissing the contractor’s negligence Claim against the project engineer for failure to serve an expert-identification affidavit within 180 days after initiating the professional-malpractice claim?

II. Did the district court err in granting summary judgment because it concluded the engineer owed no duty to the contractor?

ANALYSIS

On appeal from summary judgment, we consider whether genuine issues of material fact exist and whether the district court erred in its application of the law. Offerdahl v. Univ. of Minn. Hosps. & Clinics, 426 N.W.2d 425, 427 (Minn.1988). This consideration views the evidence in the light most favorable to the nonmoving party and resolves any doubts on the existence of a material-fact issue against the moving party. Fabio v. Bellomo, 504 N.W.2d 758, 761 (Minn.1993).

I

The .interpretation of a statute is a question of law that we review de novo. Lolling v. Midwest Patrol, 545 N.W.2d 372, 375 (Minn.1996). When applying a statute, courts must give effect, to its plain meaning, which takes into account the structure of the statute and the language of the specific statutory provision in the context of the statute as a whole. Glen Paul Court Neighborhood Ass’n v. Paster, 437 N.W.2d 52, 56 (Minn.1989) (reasoning that sections of statute:must be read together to give words their plain meaning); see also United States v. Jennings, 323 F.3d 263, 274-75 (4th Cir.2003) (determining *90 meaning by reference to language itself, specific context in which language is used, and broader context of statute as whole). We presume that plain and unambiguous statutory language manifests legislative intent. Lenz v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
692 N.W.2d 87, 2005 Minn. App. LEXIS 180, 2005 WL 354013, Counsel Stack Legal Research, https://law.counselstack.com/opinion/middle-river-snake-river-watershed-district-v-dennis-drewes-inc-minnctapp-2005.