Lake Superior Center Authority v. Hammel, Green & Abrahamson, Inc.

715 N.W.2d 458, 2006 Minn. App. LEXIS 83, 2006 WL 1529209
CourtCourt of Appeals of Minnesota
DecidedJune 6, 2006
DocketA05-800, A05-1533
StatusPublished
Cited by30 cases

This text of 715 N.W.2d 458 (Lake Superior Center Authority v. Hammel, Green & Abrahamson, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lake Superior Center Authority v. Hammel, Green & Abrahamson, Inc., 715 N.W.2d 458, 2006 Minn. App. LEXIS 83, 2006 WL 1529209 (Mich. Ct. App. 2006).

Opinion

OPINION

KALITOWSKI, Judge.

In this appeal following a trial regarding alleged defects in the design of a large exhibit tank in an aquarium, appellants contend that the district court erred by (1) *466 denying their motion for new trial; (2) denying their motion for judgment notwithstanding the verdict; (3) denying their motion to amend the pleadings; and (4) awarding respondents excessive expert-witness fees. By notice of review, respondent architect argues that the district court erred by (1) failing to dismiss appellants’ complaint for failure to timely serve an expert-review affidavit; (2) denying motions for summary judgment and directed verdict; (3) granting a partial stay of enforcement of the judgment of costs and disbursements; and (4) denying its request for daily transcript fees. Respondent tank designer also argues that the district court erred by denying the motion for summary judgment. We affirm the district court in all respects.

FACTS

Appellant Lake Superior Center Authority (Authority) is a public corporation formed by an act of the legislature in 1990. Appellant Lake Superior Center (Center) is a nonprofit corporation formed to develop and obtain funding for the Great Lakes Aquarium in Duluth, Minnesota. In June 1997, Authority and respondent Hammel, Green and Abrahamson, Inc. (HGA) entered into an architectural contract in which HGA agreed to provide lead architectural, design, and engineering services relating to the construction of the aquarium. HGA contracted with respondent Rutherford and Chekene, Inc. (R & C), a California design firm, to consult on the project and provide design services for the project’s exhibit tanks.

Authority also contracted with the following parties: (1) Koosman Project Management Services (Koosman) to serve as the owner’s agent; (2) Adolfson <& Peterson, Inc./Johnson-Wilson Construction Management, Inc. (A & P/JW) to serve as construction manager on the project; (3) Marcy Construction Company (Marcy) to serve as the project’s concrete contractor; and (4) Krech/Ojard and Associates, P.A. (K/O) to provide architectural and engineering inspection services on the project. Marcy contracted with Duluth Ready Mix (DRM) and Concrete Restorers (CR) to provide labor and materials. Center retained American Engineering and Testing, Inc. (AET) to provide two different services on the project, engineering inspection and concrete mix design. And HGA contracted with Melander, Melander and Schilling (MMS) to provide consulting services.

Construction began on the project in December 1998. In October 1999, the project encountered substantial problems with the concrete poured for the walls of the Isle Royal Tank, the largest exhibit tank in the aquarium. Repair of the defective walls required significant additional labor and expenditures, but the aquarium eventually opened on July 29, 2000.

In March 2001, Marcy brought an arbitration claim against Authority to recover expenses it incurred as a result of repair work on the Isle Royal Tank. Authority counterclaimed, alleging that Marcy owed it damages for inadequate and defective work. In January 2002, Marcy and Authority settled their claim by entering into a Pierringer agreement. Under the agreement, Authority tendered payment to Marcy and agreed to settle, release, and discharge its claims against Marcy. Authority also agreed to indemnify and hold Marcy harmless for any claims for contribution or indemnity made by others jointly liable with Marcy for damages.

On May 3, 2002, appellants filed a complaint against HGA asserting, among other things, claims of negligence, vicarious liability, and contribution and indemnity. Appellants argued that HGA was negligent in providing project design and specifica *467 tions that led to defects in the Isle Royal Tank and was vicariously liable for the actions of its subconsultants. HGA also filed a third-party complaint against other parties involved in construction of the tank, including R & C, MMS, A & P/JW, Koosman, AET, and K/O.

On August 6, 2002, appellants served their affidavit certifying expert review. On August 9, 2002, appellants filed an application to waive and/or extend the time limits for certification of expert review under Minn.Stat. § 544.42. The district court held that the affidavit served on August 6 was timely. HGA moved to dismiss appellants’ complaint for failure to abide by the time limits for certification of expert review, but the district court denied the motion. Both this court and the Minnesota Supreme Court denied HGA’s subsequent petitions for review of the district court’s denial of the motion to dismiss.

In spring of 2003, R & C and HGA moved for summary judgment, asserting that the statute of limitations set out in Minn.Stat. § 541.051 barred appellants’ claims. The district court denied the motion for summary judgment.

In October 2003, appellants amended their complaint to add R & C as a defendant, arguing that R & C was also liable due to its inadequate and defective project specifications. R & C denied the claims and brought counterclaims, cross-claims against HGA, and third-party claims against Marcy, DRM, K/O, AET, A & P/JW, and CR.

In April 2004, HGA and R & C entered into a settlement, defense, and indemnity agreement. Under the settlement, HGA agreed to release its claims against R & C and to hold R & C harmless to the extent of HGA’s insurance policy. The agreement stated that it was a Pierringer release as approved and interpreted by Pierringer v. Hoger, 21 Wis.2d 182, 124 N.W.2d 106 (1963), and Frey v. Snelgrove, 269 N.W.2d 918 (Minn.1978).

By May 2004, HGA and R & C had both asserted claims against Marcy. Marcy moved for summary judgment based on its settlement with Authority. The district court granted Marcy’s motion, dismissing HGA’s and R & C’s claims against Marcy because appellants had an obligation to indemnify Marcy under their settlement. On May 13, 2004, HGA and R & C jointly made a rule 68 offer of settlement to appellants for $1,000,000, which was rejected by appellants.

During July and August of 2004, HGA entered into settlement agreements with K/O, AET, and A & P/JW and moved to dismiss its claims against the settling parties. The district court dismissed the settling parties with prejudice, stating that the dismissal did not preclude appellants from asserting any claims against the dismissed parties, subject to applicable rules of law and procedure.

The trial began with voir dire on August 31, 2004, and lasted almost two months. At the close of appellants’ case, the remaining defendants, HGA, R & C, and third-party defendant MMS, moved for directed verdict. The court granted the motion regarding MMS and denied it regarding HGA and R & C.

The jury returned its special verdict on October 23, 2004. The jury found that (1) respondents HGA and R & C were not negligent; (2) K/O, A &

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Linda A. Trampusch v. Truck Insurance Exchange
Court of Appeals of Minnesota, 2026
Fiorito v. United States
D. Minnesota, 2023
Firkus v. Harms
914 N.W.2d 414 (Court of Appeals of Minnesota, 2018)
Pagliaroni v. Mastic Home Exteriors, Inc.
310 F. Supp. 3d 274 (District of Columbia, 2018)
Eric N. Nerland v. Kristy Lee Marie Barsch
Court of Appeals of Minnesota, 2016
Dustin Ray George Dittmar v. George Andrew Karels
Court of Appeals of Minnesota, 2016
Jean A. Swanson v. Summit Orthopedics, Ltd.
Court of Appeals of Minnesota, 2016
Franklin C. Olson v. Rustic Bar, Inc.
Court of Appeals of Minnesota, 2015
Mohrman & Kaardal, P.A. v. Gene Rechtzigel
Court of Appeals of Minnesota, 2015
O'Brien v. Dombeck
823 N.W.2d 895 (Court of Appeals of Minnesota, 2012)
TC/American Monorail, Inc. v. Custom Conveyor Corp.
822 N.W.2d 812 (Court of Appeals of Minnesota, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
715 N.W.2d 458, 2006 Minn. App. LEXIS 83, 2006 WL 1529209, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lake-superior-center-authority-v-hammel-green-abrahamson-inc-minnctapp-2006.