Arbitration Demand of 200 Levee Drive Associates, Ltd. v. Bor-Son Building Corp.

441 N.W.2d 560, 1989 Minn. App. LEXIS 695, 1989 WL 61470
CourtCourt of Appeals of Minnesota
DecidedJune 13, 1989
DocketC5-89-6
StatusPublished
Cited by10 cases

This text of 441 N.W.2d 560 (Arbitration Demand of 200 Levee Drive Associates, Ltd. v. Bor-Son Building Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arbitration Demand of 200 Levee Drive Associates, Ltd. v. Bor-Son Building Corp., 441 N.W.2d 560, 1989 Minn. App. LEXIS 695, 1989 WL 61470 (Mich. Ct. App. 1989).

Opinion

OPINION

HUSPENI, Judge.

200 Levee Drive Associates, Ltd. appeals from a trial court order staying arbitration due to an untimely demand. We affirm in part and remand.

FACTS

In January 1980, the parties entered into a standard construction contract for the erection of an apartment building. Appellant 200 Levee Drive Associates, Ltd. (Levee) was the developer and respondent Bor-Son Building Corporation (Bor-Son) was the general contractor on the project. The contract required the parties to arbitrate their disputes and incorporated the terms of the American Institute of Architects (AIA) General Conditions, Form A-201 (1976). The incorporated general conditions contained the following:

7.9.2 Notice of the demand for arbitration shall be filed in writing with the' other party to the Owner-Contractor Agreement and with the American Arbitration Association, and a copy shall be filed with the Architect. The demand for arbitration shall be made within the time limits specified in Subparagraph 2.2.12 where applicable, and in all other eases within a reasonable time after the claim, dispute or other matter in question has arisen, and in no event shall it be made after the date when institution of legal or equitable proceedings based on such claim, dispute or other matter in question would be barred by the applicable statute of limitations.

(Emphasis added).

The building was substantially completed in November 1980. In spring 1981, a problem with the building’s brick facade was discovered. One of Levee’s agents complained to the Bor-Son project manager about the discoloration of the brick. Bor-Son notified Levee that the problem was caused by moisture trapped in the brick or the cavity behind the brick. Letters were sent back and forth between agents of both parties over the course of the next year. The brick supplier provided appellant’s property management with a cleaning solution in March 1982.

In June 1987, Levee received a report it commissioned from an engineering firm concerning the results and recommendations stemming from their investigation and testing of the brick facade. The report set forth the water pressure tests performed on the building, along with the resultant cracking and pitting of the bricks and mortar. Although it indicates that the problems may stem from unrelated causes such as design, much of the report notes that the problems relate to water seepage into the facade area; the same problem which caused the brick discoloration.

The engineering report was sent to Bor-Son in late June 1987. Bor-Son informed Levee that it felt the building, including the facade, conformed to the building plans and industry standards, and suggested Levee contact an architect if it desired some structural changes.

Levee filed a demand for arbitration in August 1988, fourteen months later. Bor-Son moved the trial court for an order staying arbitration pursuant to Minn.Stat. § 572.09 (1988). The trial court stayed arbitration, finding that the six-year contract statute of limitations was applicable and therefore barred Levee’s demand for arbitration under the agreement.

ISSUES

1. Did the trial court properly consider and decide the issue of timeliness of the arbitration demand?

*563 2. Did the trial court apply the correct statute of limitations?

ANALYSIS

The parties’ intent to arbitrate is determined by the language in their agreement. State v. Berthiaume, 259 N.W.2d 904, 909 (Minn.1977). A reviewing court need not defer to the trial court’s interpretation of an arbitration agreement. Millwrights Local 548, United Brotherhood of Carpenters & Joiners, AFL-CIO v. Robert J. Pugleasa Co., Inc., 419 N.W.2d 105, 107 (Minn.Ct.App.1988) (Pugleasa). This court may independently determine whether the proper interpretation was given to the language in the agreement. R.M. Bennett Heirs v. Ontario Iron Co., 426 N.W.2d 921, 923 (Minn.Ct.App.1988); Pugleasa, 419 N.W.2d at 107.

1. Levee argues that by reaching the timeliness issue, the trial court went beyond the statutory issue presented to it by Minn.Stat. § 572.09(b) (1988). That statute provides:

On application, the court may stay an arbitration proceeding commenced or threatened on a showing that there is no agreement to arbitrate. Such an issue, when in substantial and bona fide dispute, shall be forthwith and summarily tried and the stay ordered if found for the moving party. If found for the opposing party, the court shall order thé parties to proceed to arbitration.

(Emphasis added.) Appellant maintains the trial court should have sent the dispute to arbitration after it determined that a valid arbitration issue existed because the timeliness of the demand was an issue for the arbitrator, not the court.

The Uniform Arbitration Act does not limit the time in which arbitration must be demanded. Therefore “this gap or arguable deficiency * * * must be filled by agreement of the parties.” Har-Mar, Inc. v. Thorsen & Thorshov, Inc., 300 Minn. 149, 155-56, 218 N.W.2d 751, 756 (1974) (footnote omitted); see also Lucas v. American Family Mutual Insurance Co., 403 N.W.2d 646 (Minn.1987) (parties may restrict arbitration by mutual agreement). In actions to stay arbitration, the limited issue presented to the trial court is the existence and scope of the arbitration agreement. United States Fidelity & Guaranty Co. v. Fruchtman, 263 N.W.2d 66, 71 (Minn.1978).

While no appellate court in Minnesota has determined whether enforcement of a clause of this type is a “scope” issue, the supreme court has indicated in dicta that the trial court is the proper body to make this decision.

Fraud in the inducement, waiver, laches, or limitation statutes, when asserted against a breach-of-contract claim, may be characterized as collateral defenses raising legal issues which, if established, preclude reaching the merits of the dispute sought to be arbitrated.

Har-Mar at 156, 218 N.W.2d at 756 (emphasis added); see also Brothers Jurewicz, Inc. v. Atari, Inc., 296 N.W.2d 422, 427-28 (Minn.1980) (when a defense to an action to compel arbitration is not based on the underlying dispute but instead is derived from activity before the court, the court may rule).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lake Superior Center Authority v. Hammel, Green & Abrahamson, Inc.
715 N.W.2d 458 (Court of Appeals of Minnesota, 2006)
Independent School District No. 775 v. Holm Bros. Plumbing & Heating, Inc.
660 N.W.2d 146 (Court of Appeals of Minnesota, 2003)
Capitol Place I Associates L.P. v. George Hyman Construction Co.
673 A.2d 194 (District of Columbia Court of Appeals, 1996)
Pioneer Wtr. & Sew. v. Civ. Engineer. Pro.
905 P.2d 1245 (Wyoming Supreme Court, 1995)
City of Morris v. Duininck Bros., Inc.
531 N.W.2d 208 (Court of Appeals of Minnesota, 1995)
Patton v. Yarrington
472 N.W.2d 157 (Court of Appeals of Minnesota, 1991)
Western Lake Superior Sanitary District v. Orfei & Sons, Inc.
463 N.W.2d 781 (Court of Appeals of Minnesota, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
441 N.W.2d 560, 1989 Minn. App. LEXIS 695, 1989 WL 61470, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arbitration-demand-of-200-levee-drive-associates-ltd-v-bor-son-building-minnctapp-1989.