Independent School District No. 775 v. Holm Bros. Plumbing & Heating, Inc.

660 N.W.2d 146, 2003 Minn. App. LEXIS 494, 2003 WL 1962140
CourtCourt of Appeals of Minnesota
DecidedApril 29, 2003
DocketCX-02-1701
StatusPublished
Cited by2 cases

This text of 660 N.W.2d 146 (Independent School District No. 775 v. Holm Bros. Plumbing & Heating, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Independent School District No. 775 v. Holm Bros. Plumbing & Heating, Inc., 660 N.W.2d 146, 2003 Minn. App. LEXIS 494, 2003 WL 1962140 (Mich. Ct. App. 2003).

Opinion

OPINION

KALITOWSKI, Judge.

Appellant Independent School District No. 775 challenges the district court’s order staying arbitration, arguing that its demand for arbitration was timely because the limitations period established in the contract it signed with respondent Holm Brothers Plumbing and Heating, Inc., was not triggered when appellant discovered the injury, but rather when appellant knew both the specific cause of the injury and the responsible party.

FACTS

In 1993, appellant retained KKE Architects to develop plans and specifications for a new school building. KKE proposed installation of a geothermal heat pump system to heat and cool the building and developed plans and specifications for such a system. The plans and specifications were available to all bidders on the building project. Section 15510 of the plans called for the installation of balance valves for the geothermal heat pump system.

Respondent was the successful bidder for the installation of the pump system. Appellant and respondent entered into a standard form contract published by the American Institute of Architects (AIA) to perform the work set out in section 15510. That contract incorporated by reference the General Conditions of the Contract for Construction, which is a standard form contract published by the AIA. Paragraph 7.9.1 of the contract required that all disputes between the parties be resolved by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association. And paragraph 7.9.2 stated that no demand for arbitration could be made

after the date when institution of legal or equitable proceedings based on such claim, dispute or other matter in question would be barred by the applicable statute of limitations.

In 1994, respondent certified that it had completed the installation of the heat pumps. But in September 1995, problems began to appear. And between 1996 and 1998, Chappell Central, a heating, ventilating, and air conditioning contractor, was called on 12 times to make repairs to the heat pumps and heat exchangers. On December 9, 1999, Chappell informed the superintendent of the school district that multiple compressor/coils had failed and that they should not have failed in such a short amount of time.

On December 20, 1999, the superintendent hired GHP Systems to analyze the heat pumps and determine the specific cause of the failure of the compressor/coils and the responsible party. On January 4, 2000, Kris Jeppeson of GHP visually inspected the heat pumps and took a failed eompressor/eoil for further analysis.

On February 14, 2000, Jeppeson sent a letter to the superintendent explaining the results of the investigation. Jeppeson blamed the problems on the fact that the system did not have balancing valves installed. Jeppeson concluded that the responsible party was the contractor who performed the work in section 15510 of the bid specifications.

On December 28, 2001, appellant served a demand for arbitration on respondent. Pursuant to Minn.Stat. § 572.09(b), respondent brought a motion in the district court for an order to stay and dismiss the arbitration on the ground that the demand for arbitration was untimely. The district court granted respondent’s motion and stayed the arbitration. The district court *149 found that the school district had discovered an actionable injury by December 9, 1999, if not sooner, and that the two-year statute of limitations in Minn.Stat. § 541.051, subd. 1, began to run by that date. Because appellant did not serve a demand for arbitration until December 28, 2001, the district court determined that the demand for arbitration was untimely.

ISSUES

1. Did the district court have subject matter jurisdiction to decide the issue of whether a timely demand for arbitration was made?

2. Did the district court err when it determined that the limitations period on appellant’s claim against respondent began to run on the date that appellant discovered the injury?

3. Should respondent’s motion to strike be granted?

ANALYSIS

I.

In actions to stay arbitration, the limited issue presented to the district court is the existence and scope of the arbitration agreement. United States Fidelity & Guaranty Co. v. Fruchtman, 263 N.W.2d 66, 71 (Minn.1978). A reviewing court need not defer to the district court’s interpretation of an arbitration agreement. Millwrights Local 548, United Bhd. of Carpenters & Joiners, AFL-CIO v. Robert J. Pugleasa Co., Inc., 419 N.W.2d 105, 107 (Minn.App.1988). This court may independently determine whether the proper interpretation was given to the language in the agreement. R.M. Bennett Heirs v. Ontario Iron Co., 426 N.W.2d 921, 923 (Minn.App.1988); Pugleasa, 419 N.W.2d at 107.

Appellant argues that the district court lacked subject matter jurisdiction to decide the timeliness of appellant’s arbitration demand. Appellate courts review determinations of subject matter jurisdiction de novo. Bisbee v. City of Fairmont, 593 N.W.2d 714, 717 (Minn.App.1999).

We conclude that this court’s decision in 200 Levee Drive Associates, Ltd. v. Bor-Son Bldg. Corp., 441 N.W.2d 560, 562 (Minn.App.1989), is controlling. The contract in that case contained language nearly identical to the language contained in the contract in dispute here, including a requirement that the parties arbitrate their disputes under the terms of the AIA General Conditions, Form A-201 (1976). And paragraph 7.9.2 of the contract stated that

[t]he demand for arbitration shall be made within the time limits specified in Subparagraph 2.2.12 where applicable, and in all other cases within a reasonable time after the claim, dispute or other matter in question has arisen, and in no event shall it be made after the date when institution of legal or equitable proceedings based on such claim, dispute or other matter in question would be barred by the applicable statute of limitations.

(Emphasis added.)

In 200 Levee Drive, we stated that paragraph 7.9.2 of the parties’ agreement indicated an intention by the parties to incorporate the applicable statute of limitations for litigation claims and that the statute of limitations clause thus limited a party’s right to demand arbitration. Id. at 563. Therefore, we found that the time and expense of an action to compel arbitration and the actual arbitration hearing would be eliminated under the provisions of paragraph 7.9.2 if a determination were made that the applicable statute of limitations prevented such action. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nolan and Nolan v. City of Eagan
673 N.W.2d 487 (Court of Appeals of Minnesota, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
660 N.W.2d 146, 2003 Minn. App. LEXIS 494, 2003 WL 1962140, Counsel Stack Legal Research, https://law.counselstack.com/opinion/independent-school-district-no-775-v-holm-bros-plumbing-heating-inc-minnctapp-2003.