Dakota County v. BWBR Architects, Inc.

645 N.W.2d 487, 2002 Minn. App. LEXIS 635, 2002 WL 1163737
CourtCourt of Appeals of Minnesota
DecidedJune 4, 2002
DocketC5-01-2194
StatusPublished
Cited by7 cases

This text of 645 N.W.2d 487 (Dakota County v. BWBR Architects, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dakota County v. BWBR Architects, Inc., 645 N.W.2d 487, 2002 Minn. App. LEXIS 635, 2002 WL 1163737 (Mich. Ct. App. 2002).

Opinion

*490 OPINION

KLAPHAKE, Judge.

Appellant challenges the grant of summary judgment to respondents, dismissing its claims for damages for defects to real property arising out of a construction project. Because more than two years passed after appellant should reasonably have discovered an actionable injury, we conclude that the district court did not err in granting summary judgment. Further, because any fraud or misrepresentation by respondents, which could have tolled the statute of limitations or estopped respondents from raising the statute of limitations as a defense, occurred before the discovery of the actionable injury, we affirm the district court on this issue as well.

FACTS

In 1988, appellant Dakota County entered into a contract with respondent BWBR Architects, Inc., to design the Eastern Administration Building (EAB). That same year, Dakota County hired respondent M.A. Mortenson Company, Inc. to act as construction manager for the project. As part of its contractual duties, Mortenson agreed to inspect all work for compliance with the plans, identify non-compliant work, monitor construction activity, review payment applications, and notify Dakota County if work was non-compliant. Respondents George W. Olsen Construction Company, Inc., and A.J. Spanjers Company, Inc., among others, worked as contractors or subcontractors on the project. 1 Respondent Trans-america Assurance Company of California provided a performance bond for Olsen. 2 It appears undisputed that the work was not completed in compliance with plans, that shortcuts were taken, and that substandard work was accepted by Morten-son, who apparently failed to undertake the inspections contemplated by its contract with Dakota County.

The construction was completed in 1990, and Dakota County occupied the building in February 1991. Beginning in 1992, Dakota County maintenance workers were notified about leaks in the building. The record contains copies of more than two dozen work orders for repair or inspection of leaks or water infiltration performed by Dakota County maintenance staff in the EAB during 1992-94. Essentially, these work orders included every side and every floor of the building.

Dakota County attempted to repair these leaks in a variety of ways, including caulking and sealing areas, sometimes successfully and sometimes to no avail. On September 15, 1994, Dakota County maintenance supervisor, Scott Daggett, sent a letter to Mortenson, BWBR, and Olsen in connection with one chronic leak, asking that they investigate and repair the problem. In this letter, Daggett identified four areas of concern and stated that although Dakota County had attempted to make temporary repairs,

the original construction design, coordination and workmanship continue to be responsible for this problem. Please take appropriate action immediately to avoid further water damage and deterioration of the structure. * * * Repair work must be completed by November 1,1994.

Copies of this letter were sent to the EAB building supervisor and the county attorney’s office.

*491 Mortenson, Olsen, and BWBR met with Daggett on October 7, 1994, to discuss the water problems. In a follow-up letter, BWBR suggested that Dakota County examine the problem areas more closely and referred Dakota County to Mortenson and Olsen. Mortenson suggested that Dakota County investigate more thoroughly but denied any responsibility. Although Olsen originally offered to make a minor repair, it offered no further information and made no other offers to make any repairs after this meeting. November 1, 1994, passed ■without any action being taken by Dakota County. Instead, Dakota County continued to undertake piecemeal repairs to correct leakage in the years that followed.

In November 1996, Dakota County asked Howard Noziska, a masonry consultant performing other work for it, to view one of the chronic leaks. Noziska removed some sheetrock and made a cursory inspection, but could not identify a source of the leak. He recommended additional caulking.

In October 1997, Noziska did a thorough investigation at Dakota County’s request. He issued a preliminary report on October 28, and a final report on February 26, 1998. He found multiple problems and evidence of non-conforming or substandard construction, including deficiencies not readily noticeable because of concealment by walls and ceilings. Dakota County hired a contractor to make corrective repairs totaling $1.06 million. Dakota County initiated this suit against BWBR, Mor-tenson, Olsen, and other contractors and subcontractors on November 23, 1998, and December 1,1998.

On October 19, 2001, the district court granted summary judgment in favor of respondents, concluding that Dakota County’s claim was barred by the two-year statute of limitations for claims involving improvements to real property, MinmStat. § 541.051, subd. 1 (2000). The district court further held that because any misrepresentations relied on by Dakota County occurred prior to the discovery of an actionable injury, neither fraud nor misrepresentation tolled the statute of limitations or prevented respondents from using a statute of limitations defense. This appeal followed entry of judgment.

ISSUES

1. Did the district court err in granting summary judgment based on the statute of limitations, Minn.Stat. § 541.051, subd. 1 (2000)?

2. Did the district court err in finding that respondents’ misrepresentations or fraudulent concealment, which occurred before discovery of an actionable injury, did not estop respondents from raising a statute of limitations defense?

3. Did the district court err in finding that respondents’ misrepresentations or fraudulent concealment of facts, which occurred prior to discovery of an actionable injury, did not toll the statute of limitations?

ANALYSIS

Summary judgment shall be granted where there are no genuine issues of material fact and either party is entitled to judgment as a matter of law. Minn. R. Civ. P. 56.03. No genuine issue of material fact exists

when the nonmoving party presents evidence which merely creates a metaphysical doubt as to a factual issue and which is not sufficiently probative * * * to permit reasonable persons to draw different conclusions.

DLH Inc. v. Russ, 566 N.W.2d 60, 71 (Minn.1997). Introduction of affidavits contradicting earlier damaging deposition testimony is not sufficient to create a ma *492 terial fact issue. Banbury v. Omnitrition Int’l, Inc., 533 N.W.2d 876, 881 (Minn.App.1995).

I. Statute of Limitations

In actions for damages based on improvements to real property

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
645 N.W.2d 487, 2002 Minn. App. LEXIS 635, 2002 WL 1163737, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dakota-county-v-bwbr-architects-inc-minnctapp-2002.