328 Barry Avenue, LLC v. Nolan Properties Group, LLC, and third party v. Carciofini Company, third party Marvin Windows, Inc., third party Minuti-Ogle Co., Inc., third party R. T. L. Construction, Inc., third party Stellar Contractors, Inc. d/b/a Stellar Concrete & Masonry, third party

Court of Appeals of Minnesota·Decided February 2, 2015·No. A14-724·Unpublished

Opinion

This opinion will be unpublished and may not be cited except as provided by Minn. Stat. § 480A.08, subd. 3 (2014).

STATE OF MINNESOTA

IN COURT OF APPEALS

A14-0724

328 Barry Avenue, LLC,

Appellant,

vs.

Nolan Properties Group, LLC, defendant and third party plaintiff, Respondent,

vs.

Carciofini Company, third party defendant, Respondent,

Marvin Windows, Inc., third party defendant, Respondent,

Minuti-Ogle Co., Inc., third party defendant, Respondent,

R. T. L. Construction, Inc., third party defendant, Respondent,

Stellar Contractors, Inc. d/b/a Stellar Concrete & Masonry, third party defendant, Respondent.

Filed February 2, 2015

Affirmed

Reyes, Judge

Hennepin County District Court File No. 27-CV-12-20125

J. Robert Keena, Hellmuth & Johnson, P.L.L.C., Edina, Minnesota (for appellant)

Michael A. Breen, Amy M. Sieben, Fisher, Bren & Sheridan, L.L.P., Minneapolis, Minnesota (for respondent Nolan Properties Group, LLC)

Cara C. Passaro, Murphy & Passaro, P.A., Mendota Heights, Minnesota (for respondent Carciofini Company)

Michael E. Obermueller, Winthrop & Weinstine, P.A., Minneapolis, Minnesota (for respondent Marvin Windows, Inc.)

Justin P. Short, Timothy A. Sullivan, Kyle R. Hardwick, Best & Flanagan, L.L.P., Minneapolis, Minnesota (for respondent Minuti-Ogle Co., Inc.)

Neal J. Robinson, The Cincinnati Insurance Co., Coon Rapids, Minnesota (for respondent R.T.L. Construction, Inc.)

Considered and decided by Reyes, Presiding Judge; Worke, Judge; and Johnson, Judge.

UNPUBLISHED OPINION

REYES, Judge On appeal from the district court’s grant of summary judgment to respondents, appellant argues that (1) genuine issues of material fact exist as to when appellant discovered its injury for statute-of-limitation purposes; (2) the district court misinterpreted Minnesota’s statute of limitations; and (3) genuine issues of material fact exist regarding whether equitable estoppel should have precluded summary judgment. We affirm.

FACTS

Appellant 328 Barry Avenue, LLC (328 Barry) and respondent Nolan Properties Group, LLC (NPG) are limited-liability companies located at 328 Barry Avenue in Wayzata. Both companies have the same sole owner, John Nolan. 328 Barry owns the property and used NPG as general contractor for the construction of a building on the property. Construction began in 2008. As general contractor, NPG entered into contracts with several subcontractors, including respondents Carciofini Company, Marvin

Windows, Inc., Minuti-Ogle Co., Inc. (MOC), R.T.L. Construction, Inc., and Stellar Contractors, Inc. d/b/a Stellar Concrete & Masonry. But, according to Nolan, there was no construction contract between 328 Barry and NPG.

In October 2009 while construction was ongoing, NPG discovered water intrusion on the property. It asked MOC to correct the water leakage on the east side of the building. MOC applied clear silicone to two window joints and suggested that NPG get the window tested. Two weeks later, NPG asked MOC to perform additional work because water was still leaking. When MOC returned to inspect the property on November 3, NPG and MOC used a garden hose to spray the building and saw water “slowly seep[ing] in” through a window. MOC again told NPG to get the window tested. The record contains no evidence that MOC corrected the problem or that NPG tested the windows at this time. When 328 Barry received a certificate of occupancy for the property in January 2010, not every floor of the building had been completed.

NPG next contacted MOC in August 2010 regarding water infiltration. In response, MOC again recommended that NPG test the windows and window caulking. MOC referred NPG to a forensic building scientist who could test the windows.

In early 2011, NPG hired Indigo Environmental “to assess the stucco cladding at the East elevation to determine the source for the water intrusion into the 2008 constructed building.” According to Indigo, water infiltration had previously been observed “on the East elevation first and second floor[s]” but was now observed “from the North first and second floor windows” and occasionally “from the middle windows on each floor.” Indigo completed its report in June 2011 and determined that “building

materials were installed contrary to the written specifications.” NPG later hired other companies to analyze the property and discovered several areas of water damage.

On October 3, 2012, 328 Barry filed suit against NPG, alleging that its actions as general contractor were negligent. NPG denied responsibility and sued Carciofini, Marvin, MOC, and R.T.L. for contribution and indemnification. NPG later amended its third-party complaint to include Stellar.

Nolan was deposed as both the representative of appellant 328 Barry and the representative of respondent NPG. On behalf of NPG, he stated that all of the issues raised during construction in 2009 with the windows, doors, and caulking were “addressed and corrected” by the subcontractors. As a result, according to NPG, everything was fixed and there were no water-intrusion issues until August 2010. Nolan agreed that the location of the current water intrusion was the same as the intrusion in 2009 but disagreed that the cause of the intrusion was the same.

The parties brought five motions for summary judgment, and the district court conducted a hearing on the competing motions.1 In February 2014, the district court granted Carciofini and MOC’s joint motion for summary judgment based on 328 Barry’s failure to bring suit within the statute of limitations and dismissed the other motions. The district court explained that, because 328 Barry served NPG with its summons and complaint on June 14, 2012, it must have discovered its injury after June 14, 2010 to have

1 After the hearing, 328 Barry reached a settlement with Stellar Contractors “on a [Pierringer] basis.” In a Pierringer release, a plaintiff settles a claim with one or more defendants, the settling defendants are dismissed, and any cross-claims involving those defendants are also dismissed. Frey v. Snelgrove, 269 N.W.2d 918, 922 (Minn. 1978).

met the statute of limitations. See Minn. R. Civ. P. 3.01(a). The district court concluded that 328 Barry first discovered the water infiltration in October 2009 and that this water infiltration “is the same injury [328 Barry] is complaining of now.” The district court therefore dismissed 328 Barry’s complaint because it failed to file suit within the statute of limitations.

328 Barry requested reconsideration of the district court’s order, arguing that the district court erred in its analysis of the statute of limitations. One day before the filing of this request, the district court judge who had heard the case retired. After another district court judge was assigned to the case, 328 Barry again moved for reconsideration. The new district court judge denied 328 Barry’s motion for reconsideration. 328 Barry appeals.2 DECISION

I.

A district court shall grant summary judgment “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that either party is entitled to a judgment as a matter of law.” Minn. R. Civ. P. 56.03. On appeal from an award of summary judgment, this court reviews de novo whether there is a genuine issue of material fact and whether the district court erred when it applied the law. STAR Ctrs., Inc. v. Faegre & Benson, L.L.P., 644 N.W.2d 72, 76-77 (Minn. 2002). “We view the

2 After the filing of this appeal, the parties stipulated to the dismissal of all claims against Stellar, and the district court ordered the dismissal.

evidence in the light most favorable to the party against whom summary judgment was granted.” Id.

The statute of limitations at issue states:

Free access — add to your briefcase to read the full text and ask questions with AI

328 Barry Avenue, LLC v. Nolan Properties Group, LLC, and third party v. Carciofini Company, third party Marvin Windows, Inc., third party Minuti-Ogle Co., Inc., third party R. T. L. Construction, Inc., third party Stellar Contractors, Inc. d/b/a Stellar Concrete & Masonry, third party, (Mich. Ct. App. 2015).

328 Barry Avenue, LLC v. Nolan Properties Group, LLC, and third party v. Carciofini Company, third party Marvin Windows, Inc., third party Minuti-Ogle Co., Inc., third party R. T. L. Construction, Inc., third party Stellar Contractors, Inc. d/b/a Stellar Concrete & Masonry, third party (328 Barry Avenue, LLC v. Nolan Properties Group, LLC, and third party v. Carciofini Company, third party Marvin Windows, Inc., third party Minuti-Ogle Co., Inc., third party R. T. L. Construction, Inc., third party Stellar Contractors, Inc. d/b/a Stellar Concrete & Masonry, third party) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Travelers Indemnity Co. v. Bloomington Steel & Supply Co.
718 N.W.2d 888 (Supreme Court of Minnesota, 2006)
Weston v. McWilliams & Associates, Inc.
716 N.W.2d 634 (Supreme Court of Minnesota, 2006)
DLH, Inc. v. Russ
566 N.W.2d 60 (Supreme Court of Minnesota, 1997)
Day Masonry v. Independent School District 347
781 N.W.2d 321 (Supreme Court of Minnesota, 2010)
Fiveland v. Bollig & Sons, Inc.
436 N.W.2d 478 (Court of Appeals of Minnesota, 1989)
O'Connor v. M.A. Mortenson Co.
424 N.W.2d 92 (Court of Appeals of Minnesota, 1988)
Dakota County v. BWBR Architects, Inc.
645 N.W.2d 487 (Court of Appeals of Minnesota, 2002)
Star Centers, Inc. v. Faegre & Benson, L.L.P.
644 N.W.2d 72 (Supreme Court of Minnesota, 2002)
Vlahos v. R&I Construction of Bloomington, Inc.
676 N.W.2d 672 (Supreme Court of Minnesota, 2004)
Oreck v. Harvey Homes, Inc.
602 N.W.2d 424 (Court of Appeals of Minnesota, 1999)
Frey Ex Rel. Frey v. Snelgrove
269 N.W.2d 918 (Supreme Court of Minnesota, 1978)
Brown v. Minnesota Department of Public Welfare
368 N.W.2d 906 (Supreme Court of Minnesota, 1985)
Rhee v. Golden Home Builders, Inc.
617 N.W.2d 618 (Court of Appeals of Minnesota, 2000)