Oreck v. Harvey Homes, Inc.

602 N.W.2d 424, 1999 Minn. App. LEXIS 1245, 1999 WL 1059628
CourtCourt of Appeals of Minnesota
DecidedNovember 23, 1999
DocketC5-99-752
StatusPublished
Cited by10 cases

This text of 602 N.W.2d 424 (Oreck v. Harvey Homes, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oreck v. Harvey Homes, Inc., 602 N.W.2d 424, 1999 Minn. App. LEXIS 1245, 1999 WL 1059628 (Mich. Ct. App. 1999).

Opinion

OPINION

HALBROOKS, Judge.

Appellant homeowners, Michael and Susan Oreck, challenge the district court’s grant of summary judgment in favor of respondents Harvey Homes, Inc. and JBL Plastering, Inc. The Orecks contend the district court erred in applying the two-year statute of limitations under Minn. Stat. § 541.051 (1996) to their breach of contract and breach of warranty claims and in dismissing their equitable estoppel claim. Because we conclude the district court properly applied the statute of limitations and the Orecks have failed to establish a claim of equitable estoppel, we affirm.

FACTS

Appellants Michael and Susan Oreck contracted with respondent Harvey Homes to provide materials and services for a new *426 home. Under the terms of the June 22, 1994 contract, Harvey Homes agreed to prepare a plan for the home and to furnish the materials and labor necessary to erect the frame, roof, and fascia, and to install the windows. The remaining labor and materials, including the exterior stucco, were provided by subcontractors approved by Harvey Homes with whom the Orecks directly contracted. For the exterior stucco for their home, the Orecks contracted with respondent JBL Plastering, Inc.

Under the terms of the contract between the Orecks and Harvey Homes, Harvey Homes did not agree to act as a general contractor or provide continuing supervision of the construction of the Orecks’ home. According to the Orecks, however, when they hired Harvey Homes, Harvey Homes orally promised to take care of whatever problems occurred. The Orecks contend the residence was constructed, the labor subcontracted and supervised, and materials furnished under the direction and control of Harvey Homes or upon the recommendation or approval of Harvey Homes. Further, as part of Harvey Homes’ services, its vice president, Patricia Green, communicated multiple complaints from, the Orecks to various subcontractors and asked them to correct them. Harvey Homes also sent its representative to the Orecks’ home to make numerous repairs.

Harvey Homes delivered materials and began erection of the Orecks’ home at the end of 1994. Construction was completed in April 1995 and the Orecks moved into their home that month. The Orecks subsequently experienced several continuing problems, which became the subject of this suit: (1) rain leaking in from the north due to alleged defective construction and improper gluing of the roof; (2) problems due to ice build-up and water leakage through allegedly improperly installed windows and stucco; (3) wet insulation; and (4) drafts caused by open outlets and sockets.

In response to the Orecks’ problems, Harvey Homes examined their house and asked JBL Plastering to perform repair work around the windows to solve the window leakage. JBL Plastering performed this work in the summer of 1995. Harvey Homes also sent an employee to the house to caulk the windows that summer, but the problem was not corrected. In the end of 1995 or early 1996, Harvey Homes sent the window manufacturer out to examine the house; the manufacturer concluded there was no problem with the manufacture or installation of the windows.

On October 26, 1995, the Orecks sent a letter to Harvey Homes outlining their continuing problems. In response, Harvey Homes indicated it would forward the Orecks’ concerns to the responsible contractors. Harvey Homes also stated it had determined that the leaks in the Orecks’ home were due to the stucco applied by JBL Plastering in the summer of 1995, and suggested the Orecks contact JBL Plastering. After receiving a letter from the Orecks’ attorney on November 13, 1995, Harvey Homes sent a letter to JBL Plastering outlining the Orecks’ concerns.

On November 14, 1997, the Orecks commenced an action against Harvey Homes alleging breach of contract, breach of express warranties, breach of implied warranties, breach of statutory warranties, breach of covenants of good faith and fair dealing, and negligence. It is uncontro-verted that the Orecks discovered the problems outlined in their complaint by October 26, 1995, at the latest. This is evident from an October 26,1995 letter the Orecks sent to Harvey Homes which outlined each of the problems, with the exception of the defective roof construction, and indicated the problems had been in existence since the Orecks moved into their home in April 1995.

Harvey Homes served its answer on December 5, 1997, but failed to plead the statute of limitations as an affirmative defense. In its answer, Harvey Homes contended that JBL Plastering was responsi *427 ble for the conditions in the Orecks’ home. But, Harvey Homes chose not to add JBL Plastering as a third-party defendant. Several depositions were taken, including the appellants and two principals of Harvey Homes.

On June 19, 1998, the Orecks filed an amended summons and complaint adding JBL Plastering as an additional direct defendant. On July 10, 1998, Harvey Homes served an answer to the amended complaint, including a statute of limitations defense. The Orecks objected to the inclusion of the statute of limitations defense in Harvey Homes’ amended answer.

Harvey Homes and JBL Plastering responded with summary judgment motions to dismiss the Orecks’ action on the grounds that the claims were barred by the statute of limitations. Following a hearing on the motions, the district court granted summary judgment in favor of Harvey Homes and JBL Plastering. This appeal followed.

ISSUES

1. Did the district court err in allowing Harvey Homes to assert a statute of limitations defense even though it asserted the defense for the first time in response to the Orecks’ amended complaint?

2. Did the district court err in granting summary judgment on the Orecks’ breach of contract claims pursuant to Minn.Stat. § 541.051 (1996)?

a. Did the district court err in determining there was no genuine issue of material fact as to whether the conditions in the Orecks’ home were “unsafe” pursuant to section 541.051, subd. 1?

b. Did the district court err in finding there.was no genuine issue of material fact whether Harvey Homes made assurances to the Orecks and was, therefore, equitably estopped from asserting the statute of limitations defense?

3.Did the district court err in granting summary judgment pursuant to Minn. Stat. § 541.051 on the Orecks’ breach of warranty claims?

ANALYSIS

1. Standard of review

On appeal from summary judgment, this court determines whether any genuine issues of material fact exist and whether the district court erred in applying the law. Wartnick v. Moss & Barnett, 490 N.W.2d 108, 112 (Minn.1992). In making our determination, we “view the evidence in the light most favorable to the nonmoving party.” State by Beaulieu v. City of Mounds View, 518 N.W.2d 567, 571 (Minn.1994). No deference need be given to the district court’s application of the law. Frost-Benco Elec. Ass’n v. Minnesota Pub. Utils. Comm’n,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
602 N.W.2d 424, 1999 Minn. App. LEXIS 1245, 1999 WL 1059628, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oreck-v-harvey-homes-inc-minnctapp-1999.