Mutual Service Life Insurance Co. v. Galaxy Builders, Inc.

435 N.W.2d 136, 1989 Minn. App. LEXIS 95, 1989 WL 5724
CourtCourt of Appeals of Minnesota
DecidedJanuary 31, 1989
DocketC8-88-1799
StatusPublished
Cited by8 cases

This text of 435 N.W.2d 136 (Mutual Service Life Insurance Co. v. Galaxy Builders, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mutual Service Life Insurance Co. v. Galaxy Builders, Inc., 435 N.W.2d 136, 1989 Minn. App. LEXIS 95, 1989 WL 5724 (Mich. Ct. App. 1989).

Opinion

OPINION

WILLIAM FLEMING, Judge.

Mutual Service Life Insurance Company (MSI) appeals from the trial court’s grant of summary judgment to all respondents. The action arises from alleged defects in construction of a warehouse concrete floor resulting in cracking allegedly due to insufficient thickness of the concrete and failure to install wire meshing as called for by the construction plans. We affirm the trial court’s grant of summary judgment to BE Architects, Inc. (BE) and Mayeron Engineering Company (Mayeron), based upon a two year statute of limitations, but reverse the trial court’s grant of summary judgment to Galaxy Builders, Inc. (Galaxy) and remand for further proceedings on the issue of estoppel.

FACTS

On March 1, 1982, MSI purchased improved property known as the “Reynolds Building” from Galaxy, the general contractor who constructed and owned the building. BE provided architectural plans and specifications. Mayeron provided structural engineering specifications, drawings and plans, but claims it had no duty to supervise or inspect construction.

Prior to purchase, MSI was given BE’s plans and specifications indicating the concrete floor was to be at least four and up to six inches thick, with wire mesh reinforcing. Prior to purchase, Galaxy and BE executed a certificate of substantial completion dated February 9, 1982. Also prior to purchase, but apparently unknown to MSI, Mayeron wrote a letter to Galaxy dated January 12, 1982, stating the letter was responding to a letter from the construction lender about the Reynolds Building, and stating:

The major part of warehouse floors are 4" thick. This has been standard for warehouse floors. Some areas are 6" thick for special loadings.

On February 24,1983, MSI informed Galaxy of cracks in the concrete floor. Tests were performed by Twin City Testing and Engineering Laboratories, Inc. (Twin City) at Galaxy’s expense. Twin City’s report, dated April 18, 1983, concluded: (1) the concrete slab thicknesses proximate to the worst cracking varied from 2 1 k" to 5", with an average value of less than 4", and (2) the most probable cause of the worst distress to the concrete slab would be an insufficient thickness of concrete in those floor areas subject to forklift traffic. Twin City sent a copy of this report to MSI.

The April 18, 1983, report date is significant. The trial court concluded that MSI was aware of the defective condition on or about April 18, when it received the report. MSI commenced this suit on June 21, 1985, two years and two months later. The trial court by order dated September 5, 1986, granted the summary judgment motions of BE and Mayeron dismissing the contract and negligence claims against them based upon the two-year statute of limitations contained in Minn.Stat. § 541.051, subd. 1 (1984). 1 The trial court denied BE’s and *138 Mayeron’s motions to dismiss Galaxy’s cross-claims against them and granted MSI’s motion to amend its complaint to assert a cause of action for negligent misrepresentation against Galaxy, BE and Mayeron.

Nonbinding arbitration, pursuant to Spec.R.Prac. 4th Jud. Dist. 5, occurred on September 17, 1987. The arbitrator awarded MSI $140,000 in damages from Galaxy. The arbitrator awarded Galaxy contribution from BE of $20,000 and from Mayeron of $20,000. Respondents requested a trial.

Galaxy moved for summary judgment based on the two-year statute of limitations. BE and Mayeron also moved for summary judgment on the remaining action of negligent misrepresentation based on the two-year statute of limitations. MSI opposed the motions arguing (1) causes of action for negligent misrepresentation against all three respondents are causes of action for fraud, and causes of action for fraud are specifically excluded from the statute of limitations and (2) Galaxy is estopped from asserting the statute of limitations because it’s assurances that it would take care of the problem led to MSI’s delay in commencing the lawsuit. MSI moved for leave to again amend its complaint to include an action for intentional misrepresentation against all three respondents.

The trial court granted all three respondents’ motions for summary judgment. The trial court denied MSI’s motion for leave to amend its complaint. In a supporting memorandum, the trial court explained that the recent Minnesota Supreme Court case of Wittmer v. Ruegemer, 419 N.W.2d 493 (Minn.1988) was controlling. This appeal followed.

ISSUES

1. Did the trial court err in its application of the law by holding MSI’s allegations of fraud did not toll the two-year statute of limitations contained in Minn.Stat. § 541.051, subd. 1?

2. Did the trial court err by granting summary judgment to Galaxy because a genuine issue of material fact exists as to whether Galaxy is estopped from asserting a statute of limitations defense?

3. Did the trial court err by denying MSI leave to amend its complaint?

ANALYSIS

Summary judgment shall be rendered if the pleadings, depositions, answers to interrogatories, and admissions on file, together with any affidavits, show that there is no genuine issue as to any material fact and that either party is entitled to judgment as a matter of law. Minn.R.Civ.P. 56.03. On appeal from summary judgment, the role of the reviewing court is to review the record for the purpose of answering two questions: (1) whether there are any material issues of fact to be determined, and (2) whether the trial court has erred in its application of the law. Minneapolis, St. Paul & Sault Ste. Marie Railroad Co. v. St. Paul Mercury-Indemnity Co., 268 Minn. 390, 406, 129 N.W.2d 777, 788 (1964). “A material fact is one of such a nature as will affect the result of the case depending on its resolution.” Zappa v. Fahey, 310 Minn. 555, 556, 245 N.W.2d 258, 259-60 (1976). When reviewing a summary judgment the reviewing court “must take a view of the evidence most favorable to the *139 one against whom the motion was granted.” Abdallah, Inc. v. Martin, 242 Minn. 416, 424, 65 N.W.2d 641, 646 (1954).

1. Statute of limitations. MSI argues causes of action for fraud are specifically excepted from the two-year statute of limitations contained in Minn.Stat. § 541.051, subd. 1. The relevant part of the statute reads:

Except where fraud is involved, no action by any person in contract, tort, or otherwise to recover damages for any injury to property, real or personal, * * * shall be brought * * * more than two years after discovery thereof * * *

Id.

The Minnesota Supreme Court recently addressed the meaning of the fraud exception of the statute in Wittmer v. Ruegemer,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dakota County v. BWBR Architects, Inc.
645 N.W.2d 487 (Court of Appeals of Minnesota, 2002)
Rhee v. Golden Home Builders, Inc.
617 N.W.2d 618 (Court of Appeals of Minnesota, 2000)
Oreck v. Harvey Homes, Inc.
602 N.W.2d 424 (Court of Appeals of Minnesota, 1999)
Gibson v. Gibson
149 B.R. 562 (D. Minnesota, 1993)
Rivers v. Richard Schwartz/Neil Weber, Inc.
459 N.W.2d 166 (Court of Appeals of Minnesota, 1990)
Hydra-Mac, Inc. v. Onan Corp.
450 N.W.2d 913 (Supreme Court of Minnesota, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
435 N.W.2d 136, 1989 Minn. App. LEXIS 95, 1989 WL 5724, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mutual-service-life-insurance-co-v-galaxy-builders-inc-minnctapp-1989.