City of Coon Rapids v. Suburban Engineering, Inc.

167 N.W.2d 493, 283 Minn. 151, 1969 Minn. LEXIS 1125
Supreme Court of Minnesota·Decided March 28, 1969·No. 41245·Published·Cited by 16 cases

Opinion

Murphy, Justice.

This is an appeal from a summary judgment for defendants in an action by the city of Coon Rapids seeking damages in connection with defective construction of a storm sewer. Defendants are Vern Donnay Construction Co., Inc., Dailey Construction Company and Land and Properites, Inc., which are two real estate development concerns, and *153 their agents and associates, Suburban Engineering, Inc., Robert P. Minder, Walbon Excavating Company, Duane A. Petrowske and Richard D. Ross (a partnership), and Petrowske and Ross, Inc. Plaintiff-appellant contends that the trial court was in error in determining that there was no genuine issue for trial.

The complaint alleges that the city sustained damages resulting from the defective installation of a storm sewer by defendants. Defendant Dailey owned property within the city limits which it proposed to develop and sell to the public. Donnay owned property in the adjoining village of Blaine which it proposed to develop and sell. Before Dailey could secure the approval of the city council for its proposed development, it was necessary to establish adequate drainage by the construction of a storm sewer system. Donnay, whose property adjoined the Dailey development, sought to secure the benefits of the proposed storm sewer system for its property and joined with Dailey in installing the improvement. The developers and their engineering firm, Suburban Engineering, Inc., preferred to have the system installed on a private basis rather than have the city do it. The city acquiesced in their proposal and agreed to bear the expense for future maintenance of the system after its installation.

Suburban Engineering designed the system and had the overall responsibility for supervising its installation. The specifications provided:

“The upper one-half of all joints shall be mortared inside and out with cement mortar. This mortar shall be worked into the joints between the pipes and is to be struck off flush with the inside of the pipe and built up to one inch at the joint on the outside of the pipe. The outside joint shall taper off flush with the pipe barrel four inches from the joint. Sufficient mortar shall be placed in the bottom of the pipe bell to assure true alignment of the bore of the pipe.”

The contracts for the construction of the project were let to Walbon Excavating Company and Petrowske and Ross, Inc., defendants heretofore named. After the work was completed, the city was assured by the defendant engineering firm that the work had been completed according to specifications. The showing, with reference to whether the city relied *154 upon the representations of the engineering firm or whether they relied upon the report of their own engineer, is equivocal at best. The city engineer, Keith Caswell, who was employed as a consultant at the time the work was completed, had formerly been associated with some of the defendants. Suburban Engineering recommended acceptance of the job, representing to Caswell that the storm sewer “was installed per the plans and specifications as prepared and was checked by us during construction to be sure that it was a first-class job.” It is not clear from the showing presented to the court by the depositions and affidavits that Caswell, acting as city engineer, or his employees actually did any more than make a casual observation of the work after it was completed. Nevertheless, it appears that Caswell did inform the Federal Housing Administration that the storm sewer had been “dedicated to the City and accepted for permanent maintenance.” We gather from the record that when the completed job was offered to the city the pipes had been covered from the top and that the opportunity for inspection from the inside was limited. We cannot agree on the basis of the showing made that the evidence would establish, as a matter of law, that the city relied on its own inspection of the job at the time it informed the Federal Housing Administration that the improvement had been completed.

It appears that the job was completed about March 23, 1960, and soon thereafter the city experienced trouble with the system. This difficulty continued to the point where the city called Caswell in 1963 or 1964 to conduct an inspection. On the basis of this inspection, he advised that the problems experienced with the system were the result of noncompliance with specifications in the contract for installation. The inspection covered an area of about one block, which would include at least 200 sections of pipe, none of which were properly installed. Accordingly, the city had to dig up portions of the system and repair it. The precise defect in the installation was that the pipes were not properly mortared at the joints. As a result, sand infiltrated, causing voids underground which resulted in cave-ins.

The city instituted this action against defendants on June 23, 1966, more than 6 years after Caswell’s letter to the Federal Housing Adminis *155 tration indicating that the work had been completed. The lower court was of the view that the action was barred by the statute of limitations and that the city apparently was attempting to evade this defense by disguising the real cause of action by a complaint that alleged conspiracy and fraud. He accordingly concluded that there was no genuine issue for trial and granted defendants’ motion for summary judgment.

In considering the issues presented, certain preliminary observations may be appropriate. It is well recognized that the statute of limitations can be asserted against the state and municipalities. State v. Bies, 258 Minn. 139, 103 N. W. (2d) 228. And, except in the case of fraud, ignorance of a cause of action will not prevent the running of the statute. Voegele v. Mahoney, 237 Minn. 43, 54 N. W. (2d) 15; Schmucking v. Mayo, 183 Minn. 37, 235 N. W. 633. Minn. St. 541.05 provides:

“Except where the uniform commercial code otherwise prescribes, the following actions shall be commenced within six years:

‡ ‡ ‡

“(6) For relief on the ground of fraud, in which case the cause of action shall not be deemed to have accrued until the discovery by the aggrieved party of the facts constituting the fraud.”

It is conceded that this action was not commenced until more than 6 years after the acceptance of the work on the system. However, it is contended that the proof will establish that defendants’ acts constituting the alleged fraud were not discovered within the 6 years immediately preceding the institution of this action.

The showing, with reference to the issue of fraud, must be considered in light of those authorities which hold that a party is liable for fraud if he makes a false representation of a past or existing material fact susceptible of knowledge, knowing it to be false or asserting it as of his own knowledge without knowing whether it is true or false, with the intention to induce the person to whom it is made to act in reliance upon it, or under such circumstances that such person is justified in acting in reliance upon it and is thereby deceived and induced to act in reliance upon it to his damage. Davis v. Re-Trac Mfg. Corp. 276 Minn. 116, 149 N. W. (2d) 37; 8A Dunnell, Dig. (3ed.) § 3818; Prosser, Torts (3 ed.) p. *156 700.

Free access — add to your briefcase to read the full text and ask questions with AI

City of Coon Rapids v. Suburban Engineering, Inc., 167 N.W.2d 493, 283 Minn. 151, 1969 Minn. LEXIS 1125 (Mich. 1969).

167 N.W.2d 493 (City of Coon Rapids v. Suburban Engineering, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

In re Minn. Living Assistance, Inc.
919 N.W.2d 87 (Court of Appeals of Minnesota, 2018)
Harrison Ex Rel. Harrison v. Harrison
713 N.W.2d 74 (Court of Appeals of Minnesota, 2006)
Grozdanich v. Leisure Hills Health Center, Inc.
25 F. Supp. 2d 953 (D. Minnesota, 1998)
District of Columbia v. OWENS-CORNING FIBERGLAS CORPORATION
572 A.2d 394 (District of Columbia Court of Appeals, 1990)
In Re the Real Estate Salesperson's License of Perron
437 N.W.2d 92 (Court of Appeals of Minnesota, 1989)
Taylor v. Sheehan
435 N.W.2d 575 (Court of Appeals of Minnesota, 1989)
Mutual Service Life Insurance Co. v. Galaxy Builders, Inc.
435 N.W.2d 136 (Court of Appeals of Minnesota, 1989)
ESTATE OF JONES BY BLUME v. Kvamme
430 N.W.2d 188 (Court of Appeals of Minnesota, 1988)
Toombs v. Daniels
361 N.W.2d 801 (Supreme Court of Minnesota, 1985)
Hartford Accident & Indemnity Co. v. Rogers
613 P.2d 1025 (Nevada Supreme Court, 1980)
Lowry Hill Properties, Inc. v. Ashbach Construction Co.
194 N.W.2d 767 (Supreme Court of Minnesota, 1971)
Clements Auto Co. v. Service Bureau Corp.
444 F.2d 169 (Eighth Circuit, 1971)
Berryman v. Riegert
175 N.W.2d 438 (Supreme Court of Minnesota, 1970)