Wittmer v. Ruegemer

419 N.W.2d 493, 1988 Minn. LEXIS 83, 1988 WL 11091
CourtSupreme Court of Minnesota
DecidedFebruary 19, 1988
DocketC6-86-1599
StatusPublished
Cited by57 cases

This text of 419 N.W.2d 493 (Wittmer v. Ruegemer) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wittmer v. Ruegemer, 419 N.W.2d 493, 1988 Minn. LEXIS 83, 1988 WL 11091 (Mich. 1988).

Opinion

OPINION

COYNE, Justice.

This appeal raises once again questions concerning the event which triggers the commencement of the two-year limitations period provided by Minn.Stat. § 541.051, subd. 1 (1984). The trial court granted summary judgment for the defendants, ruling that plaintiffs’ action to recover damages resulting from the negligent design and installation of a septic system was time-barred because it was instituted more than two years after they discovered some damage — namely, standing water over .the seepage area. The court of appeals reversed, holding that the claim was not barred because the plaintiffs neither discovered nor should have discovered the defective condition of the septic system until October 1984, less than two years before they commenced this action. Wittmer v. Ruegemer, 402 N.W.2d 187 (Minn.App.1987). We agree with the court of appeals that the two-year limitation period provided in section 541.051, subd. 1, commences when the injured party discovers, or with reasonable diligence should have discovered, the defective condition of an improvement to real property. Since, however, we are of the opinion that there are genuine issues of material fact concerning when the plaintiffs discovered, or with reasonable diligence should have discovered, the defective condition of the septic system, we reverse that portion of the decision of the court of appeals deciding the question as a matter of law and remand for determination of that issue by the trier of fact.

The recurring difficulties encountered in identifying the events which commence the running of the limitations set by Minn.Stat. § 541.051 (1984) for instituting an action for damages arising out of the defective and unsafe condition of an improvement to real property prompts us once more to review the question. In order to provide a perspective for discussion we deem it necessary to relate the “facts” on which the lower courts relied in reaching differing conclusions. We note, however, that because the matter was presented by defendants’ motions for summary judgment, the events preceding the commencement of the action have been gleaned from the pleadings and plaintiff Leon Wittmer’s affidavit opposing the motions and are not necessarily undisputed.

Plaintiffs Leon and Mary Wittmer commenced this action in October 1985 to recover damages for the negligent design and construction of their home’s septic system, naming as defendants Norbert J. Rue-gemer d/b/a Norco Construction Co. (Rue-gemer), the general contractor; Chester Kottke, the Corcoran building inspector and the designer and installer of the septic system; and the City of Corcoran. Approximately four years earlier, in July 1981, plaintiffs entered into a contract with Ruegemer for the construction of a house on their property in Corcoran, Minnesota. Plaintiffs had previously engaged Ingleside Engineering and Construction to make per- *495 eolation tests on the property and to design an onsite domestic sewage disposal system, and specifications for the Ingleside system were incorporated into the construction contract. Ruegemer subcontracted the construction of the septic system to Kottke, who then proposed an alternative sewage disposal system. With the plaintiffs’ approval, Kottke installed his proposed system and, acting as the Corcoran building inspector, inspected and approved it late in the fall of 1981.

In August 1982, plaintiffs noticed that the lawn at the west end of the seepage bed was constantly wet, but they did not consider the wetness a problem because the ground was firm. By June 1983, however, the wet area was larger, there was some standing water on the lawn, and the ground no longer supported the weight of a lawnmower without its wheels sinking. At plaintiffs’ request Kottke inspected the site. Plaintiffs assert that Kottke assured them the problem was not serious and posed no health hazard and that it could be cured by putting dirt fill at the end of the seepage bed.

The plaintiffs decided to add the fill as a part of some planned landscaping. When the landscaping work began in August 1984, the ground above the west end of the system had begun to sink, a large area of grass was dead, and there was standing water 30 feet from the original wet spot. Kottke again advised additional dirt fill.

In October 1984 Michael Gaffron inspected the plaintiffs’ sewage disposal system and reported that the problem could not be corrected by adding dirt fill and recommended the installation of a new drain field. A second consultant concluded that the system had never worked properly and that it should be replaced by an entirely new system.

After the Corcoran City Council denied their request for redress, plaintiffs commenced this action in October 1985. The trial court granted summary judgment for the defendants, ruling that the statute begins to run when some damage occurs which would entitle the victim to maintain a cause of action and that plaintiffs’ awareness of standing water over the seepage area in June of 1983 was sufficient to commence the limitation period. The court of appeals reversed on the ground that the plaintiffs neither discovered nor reasonably should have discovered the defective condition of the septic system until October 1984, less than two years before the action was commenced. Wittmer v. Ruegemer, 402 N.W.2d 187 (Minn.App.1987). Only the City of Corcoran petitioned for review of the decision of the court of appeals. 1

The parties agree that section 541.051, which limits the time within which an action may be brought for damages arising out of the defective condition of an improvement to real property, is applicable here. See Pacific Indemnity Co. v. Thompson-Yaeger, Inc., 260 N.W.2d 548, 554 (Minn.1977). The pertinent portion of the statute follows:

Except where fraud is involved, no action by any person in contract, tort, or otherwise to recover damages for any injury to property, real or person, or for bodily injury or wrongful death, arising out of the defective and unsafe condition of an improvement to real property, nor any action for contribution of indemnity for damages sustained on account of the injury, shall be brought against any person performing or furnishing the design, planning, supervision, materials, or observation of construction or construction of the improvement to real property or against the owner of the real property more than two years after discovery thereof, nor, in any event shall such a cause of action accrue more than 15 years after substantial completion of the construction. * * *

Minn.Stat. § 541.051, subd. 1 (1984).

We note at the outset that the thrust of section 541.051 differs markedly from that of other statutes of limitations. In general, the limitations period begins to *496 run when a cause of action “accrues,” that is, when the action can be brought without being subject to dismissal for failure to state a claim. O’Neill v. Illinois Farmers Ins. Co., 381 N.W.2d 439

Free access — add to your briefcase to read the full text and ask questions with AI

Related

William A. Graham Co. v. Haughey
646 F.3d 138 (Third Circuit, 2011)
Broek v. Park Nicollet Health Services
660 N.W.2d 439 (Court of Appeals of Minnesota, 2003)
Dakota County v. BWBR Architects, Inc.
645 N.W.2d 487 (Court of Appeals of Minnesota, 2002)
Bertram v. Poole
597 N.W.2d 309 (Court of Appeals of Minnesota, 1999)
Majestic Inc. v. Berry
593 N.W.2d 251 (Court of Appeals of Minnesota, 1999)
J.J. v. Luckow
578 N.W.2d 17 (Court of Appeals of Minnesota, 1998)
W.J.L. v. Bugge
573 N.W.2d 677 (Supreme Court of Minnesota, 1998)
DLH, Inc. v. Russ
566 N.W.2d 60 (Supreme Court of Minnesota, 1997)
Blackowiak v. Kemp
546 N.W.2d 1 (Supreme Court of Minnesota, 1996)
DLH, Inc. v. Russ
544 N.W.2d 326 (Court of Appeals of Minnesota, 1996)
Tower Asphalt, Inc. v. Determan Welding & Tank Service, Inc.
530 N.W.2d 872 (Court of Appeals of Minnesota, 1995)
Klehr v. A.O. Smith Corp.
875 F. Supp. 1342 (D. Minnesota, 1995)
Williams v. Tweed
520 N.W.2d 515 (Court of Appeals of Minnesota, 1994)
ABC v. Archdiocese of St. Paul & Minneapolis
513 N.W.2d 482 (Court of Appeals of Minnesota, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
419 N.W.2d 493, 1988 Minn. LEXIS 83, 1988 WL 11091, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wittmer-v-ruegemer-minn-1988.