Rivers v. Richard Schwartz/Neil Weber, Inc.

459 N.W.2d 166, 1990 Minn. App. LEXIS 842
CourtCourt of Appeals of Minnesota
DecidedAugust 21, 1990
DocketC4-90-195, C6-90-165
StatusPublished
Cited by5 cases

This text of 459 N.W.2d 166 (Rivers v. Richard Schwartz/Neil Weber, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rivers v. Richard Schwartz/Neil Weber, Inc., 459 N.W.2d 166, 1990 Minn. App. LEXIS 842 (Mich. Ct. App. 1990).

Opinion

*168 OPINION

CRIPPEN, Judge.

The trial court granted judgment in favor of architects, developers, and builders based on a two-year statute of limitations for suits involving defects to real property. The trial court had previously rejected a Miller-Shugart settlement between the parties. On appeal, this litigation was consolidated with the related appeal of Allied Insurance Company from a trial court decision that it could not avoid coverage for construction defects in the property, notwithstanding exclusions within its policy. We affirm the decisions in the defects suit, and reverse the judgment against Allied.

FACTS

1. Statute of limitations.

Appellant The Rivers Association 1 represents owners of a 19-unit condominium constructed in 1979 and 1980. The project was developed by respondent The Rivers, a partnership, and designed by respondent Richard Schwartz/Neil Weber, Inc. Respondent Franklin Construction Company was the construction manager of the project and respondent Bernhagen Brick, Inc. provided the masonry work.

On August 3, 1984, the association, together with the partnership, initiated a suit against Franklin, Schwarz/Weber, and Bernhagen. The suit claimed damages arising from construction defects in the condominium roof, the terrace and garage, and the brick facade. The association contends that evidence would show damages in excess of $1,000,000.

On January 9, 1987, the association, represented by separate counsel, initiated a suit against the respondent partnership for breach of warranty, negligent selection and supervision of architects and builders, and negligent failure to take remedial measures.

In orders of October and November 1989, the trial court ordered judgment for all four respondents on the association’s claims and cross-claims. The court concluded that the 1984 suit and the 1987 cross-claim were precluded by Minn.Stat. § 541.051 (1988). 2 Based on testimony and exhibits, the trial court found that all the defects in the project were known to members of the association more than two years before the defects action was commenced.

2. Insurance.

While the defects suit was pending, appellant Allied Insurance Company filed a separate, declaratory judgment action alleging that certain exclusions in a policy issued to Franklin for the project precluded coverage. The policy issued is a standard form comprehensive general liability policy. The policy excluded coverage for loss of use of property resulting from the failure of Franklin’s work product to meet the level of fitness warranted by Franklin. This exclusion did not apply to loss of use of property other than the work product. A further exclusion applied to property damage to Franklin’s work product arising out of the product itself. The insurance policy also contained a so-called standard broad form endorsement which provided coverage for Franklin’s completed projects. This endorsement contained an exclusion stating that with respect to completed projects, insurance would not be provided for property damage to projects completed by Franklin arising out of the work done on the projects.

*169 In December 1989, applying three theories, the trial court determined that these exclusions did not govern the case. Among those theories, the trial court stated that even though damages were claimed for defects in the construction project, the work product exclusions did not preclude coverage for Franklin’s negligence in rendering services as a construction manager supervising labor and materials of other contractors.

3. Miller-Shugart agreement.

In March 1989, the association, the partnership, Franklin, Bernhagen, and Schwartz/Weber entered into a settlement agreement of the defects claims. Franklin confessed a $1.2 million judgment, subject to a covenant not to sue, under which the association would collect such judgment only from the Allied insurance policy. The agreement purported to release Franklin from all claims even if the trial court rejected the agreement. The agreement also stated that its construction would be governed by the principles set forth in Miller v. Shugart, 316 N.W.2d 729 (Minn.1982). The parties concede that the agreement was made without notice to Allied which had begun its declaratory action. The agreement was also made without notice to counsel furnished to Franklin by Allied to defend the association’s defects claims. The trial court rejected the settlement as fraudulently devised.

ISSUES

1. Was dismissal appropriate?

2. Did coverage exist for Franklin under the insurance policy issued by Allied?

3. Did the trial court properly reject the Miller-Shugart agreement?

ANALYSIS

The standard governing the two year limitations law is whether the association discovered, or in the exercise of reasonable diligence should have discovered, an injury sufficient to entitle it to maintain a cause of action. Greenbrier Village Condominium Two Ass’n, Inc. v. Keller Inv., Inc., 409 N.W.2d 519, 524 (Minn.App.1987). This standard places the burden of discovery of the injury on the plaintiff. Id. at 525.

The injuries here are sufficient to sustain a cause of action. However, the trial court found that “it is clear that the matters of which the association complains had all been known to the members of the association prior to the period two years before the [claims were] commenced.” This finding is sustained by evidence of record and is not clearly erroneous. Testimony to support the finding came from three witnesses, Sol Austrian, Sylvester Brand, and J. Donald Kelly.

Austrian testified that he moved into the building in July 1980. He had been president of the association from 1980 through the end of 1981, was on the association board from September 1983 to September 1985, and was a partner in the partnership. Austrian stated that while he was president of the association and after the construction problems arose, he had received reports from the architect and various testing agencies and that he had brought these reports to the attention of the association. Austrian testified to the existence of water problems in Brand’s unit prior to the Brand’s purchase of the unit. He also testified that drainage channels were constructed in the basement garage in 1981 to correct leakage problems.

Sylvester Brand testified that he lived in unit 501 and that when he first inspected the unit in June 1982 he noted that the ceiling was being repaired. J. Donald Kelly testified that when he moved into the building on April 18, 1981 he had problems with “severe water accumulation” on the floor of his garage stalls. He stated that later, a channel was cut in the garage floor to carry the water away, and that the channel partially carried the water away.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Independent School District No. 775 v. Holm Bros. Plumbing & Heating, Inc.
660 N.W.2d 146 (Court of Appeals of Minnesota, 2003)
Dakota County v. BWBR Architects, Inc.
645 N.W.2d 487 (Court of Appeals of Minnesota, 2002)
Rhee v. Golden Home Builders, Inc.
617 N.W.2d 618 (Court of Appeals of Minnesota, 2000)
Insurance Co. of North America v. Spangler
881 F. Supp. 539 (D. Wyoming, 1995)
Appletree Square 1 Ltd. Partnership v. W.R. Grace & Co.
815 F. Supp. 1266 (D. Minnesota, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
459 N.W.2d 166, 1990 Minn. App. LEXIS 842, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rivers-v-richard-schwartzneil-weber-inc-minnctapp-1990.