Hyland Hill North Condominium Ass'n v. Hyland Hill Co.

549 N.W.2d 617, 1996 Minn. LEXIS 619, 1996 WL 297317
CourtSupreme Court of Minnesota
DecidedJune 6, 1996
DocketC7-94-2564, C8-94-2573
StatusPublished
Cited by11 cases

This text of 549 N.W.2d 617 (Hyland Hill North Condominium Ass'n v. Hyland Hill Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hyland Hill North Condominium Ass'n v. Hyland Hill Co., 549 N.W.2d 617, 1996 Minn. LEXIS 619, 1996 WL 297317 (Mich. 1996).

Opinion

OPINION

TOMLJANOVICH, Justice.

This case involves claims of defective workmanship in the construction of Hyland Hill North Condominium (the Condominium). The respondent Hyland Hill North Condominium Association (the Association) originally sued seven defendants. After a number of defendants were dismissed and others added, only six defendants remain as appellants in this ease. These parties are Hyland Hill Co., Gittleman Corp., Diversified Management Co., Gittleman Management Corp., Melvin C. Gittleman, and Donald W. Anderson (collectively, the “Developer”). 1 The Association claimed the Developer was negligent; breached fiduciary duties; breached implied warranties under Minn. Stat. § 515A.4-111 (1992), the Uniform Condominium Act (UCA), and Minn.Stat. § 327A.02, subd. 1 (1992); and breached express warranties under the UCA. Though the Association also originally named Berwald Roofing (Berwald) as a defendant, the claims were later dismissed. However, the Developer filed a crossclaim against Berwald; thus, it remains a party.

In an order denying partial summary judgment dated June 29, 1993, the Hennepin County District Court found that the Association’s claims, except for breach of fiduciary duties, were barred by the two-year statute of limitations, Minn.Stat. § 541.051 (1992). The court also found, however, that a fact issue existed as to whether the statute had *619 been tolled or should be disregarded on grounds of estoppel.

A jury trial was held May 4 through May 17, 1994. The jury entered a special verdict finding no grounds for tolling the statute of limitations, or for estoppel. This verdict served to bar all the Association’s claims except those for breach of fiduciary duties. Judgment was entered on the latter claims in the amount of $20,010.64. The crossclaim against Berwald was also found to be barred by the statute of limitations.

Both the Association and the Developer appealed and the court of appeals consolidated the separate appeals. The court affirmed the district court in part and reversed in part. See Hyland Hill North Condominium Assoc. v. Hyland Hill Co., 538 N.W.2d 479 (Minn.App.1995). Both sides petitioned for review to this court. By order dated November 30,1995, we granted review of the Developer’s petition and denied the Association’s petition.

Hyland Hill North is a condominium budding in Bloomington, Minnesota. It was constructed in 1983 and 1984. The building was substantially completed by September 1984 and a certificate of occupancy was issued. The Condominium has three separate wings, each wing having three floors, all covered by the “main roof.” There is also a separate roof covering a “party room” and pool area. The building’s first residents, Marilyn and Robert Moore, signed a purchase agreement in February 1984, and moved into their unit in September 1984. The Condominium’s declaration was filed in January 1985. Though the unit owners of the Condominium did not initially have control of the condominium association, they assumed control in May 1987.

Upon moving in, the Moores discovered leakage in their unit. In deposition testimony, Mrs. Moore stated that there had been water damage “since the first rain when we moved in.” Thereafter, the unit “always had leaks.” A second resident who moved in in 1985 recalled leakage since “the early time I was living there.” At trial there was testimony that in May 1987, the Board of Directors of the Association was aware of skylight leakage on the third floor of the Condominium. Minutes of a special meeting of the Association’s members show that on October 6, 1987, the Association was aware of leaks in the party room and garage. 2 In an order denying partial summary judgment, dated June 29, 1993, the district court found that for purposes of the running of the two-year statute of limitations under section 541.051, the Association was aware of its leakage problems on or before October 6,1987.

However, Joseph Kuzniar, who had been a member of the Board of Directors of the Association (the Board) since 1987, testified that until September 1989, the Association was only aware of leaks over the party room and skylight leaks. Kuzniar testified that in 1989, there was a “deluge where the water came from the third floor unit down into the second floor unit and came out the electrical outlets and so on.” He stated that this was the first time the Association was aware of a “serious leak” in the roof. There was additional testimony that in March 1990, it was discovered there were approximately 80 leaks in third floor units.

After the “deluge” of leaks developed in 1989, the Association hired a roofing inspection firm called Inspee to assess the condition of the roof. Inspee examined the roof in October 1989. The Association received In-spec’s report in December. Though Inspee found the overall appearance of the roof to be “fair” for its age, it urged the Association to undertake immediate repairs.

The following spring, Inspee performed an infrared scan of the building’s roof. The test showed that some 10 percent to 15 percent of the roofs insulation was wet. Inspee then changed its earlier position that repair of the roof would be sufficient, and recommended that the roof be replaced. An Inspee representative gave the Association a “worst case” estimate of $200,000 to replace the roof. At an Association meeting on May 8, 1990, *620 based on the $200,000 estimate, the members approved a special assessment to replace the roof. 3 During the summer of 1990, the old roof was torn off and a new one installed.

The Association also experienced “nonroof ’ difficulties with the Condominium building. There was testimony that during and after 1991, leakage occurred in the windows of three-season porches in the Condominium. There was also testimony that in October 1992, wood beams around sundeeks at the Condominium were found to be rotted. Repairs were made to both the three-season porch windows and the rotted wood beams. There was also expert testimony that the budding did not have appropriate expansion joints, which allow the brick facade to “freely breathe,” and that brick was cracking off the budding.

The Association filed this action in November 1990, asserting claims for negligence, breach of warranties, and breach of fiduciary duties. The Association brought a motion for summary judgment. The district court denied the motion, but in an order dated June 19, 1993, found: the Association’s claims (except the claim for breach of fiduciary duties) were governed by the two-year statute of limitations in section 541.051; the Association discovered its injury by October 6, 1987; and factual issues existed as to whether the two-year period was tolled by assurances from the Developer, and whether the Developer should be estopped to raise the statute of limitations.

The case was tried before a jury in May and June 1994. By special verdict, the jury found: Berwald and the Developer were negligent; the Developer breached implied and express warranties to the Association under the UCA; and the Developer breached other implied warranties under Minn.Stat. § 327A.02 (1992).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Westfield Insurane Co. v. Wensmann, Inc.
840 N.W.2d 438 (Court of Appeals of Minnesota, 2013)
Day Masonry v. Independent School District 347
781 N.W.2d 321 (Supreme Court of Minnesota, 2010)
Buscher v. MONTAG DEVELOPMENT, INC.
770 N.W.2d 199 (Court of Appeals of Minnesota, 2009)
Vlahos v. R&I Construction of Bloomington, Inc.
676 N.W.2d 672 (Supreme Court of Minnesota, 2004)
JAS Apartments, Inc. v. City of Minneapolis
668 N.W.2d 912 (Court of Appeals of Minnesota, 2003)
Dakota County v. BWBR Architects, Inc.
645 N.W.2d 487 (Court of Appeals of Minnesota, 2002)
West Circle Properties LLC v. Hall
634 N.W.2d 238 (Court of Appeals of Minnesota, 2001)
Matter of Welfare of JM
574 N.W.2d 717 (Supreme Court of Minnesota, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
549 N.W.2d 617, 1996 Minn. LEXIS 619, 1996 WL 297317, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hyland-hill-north-condominium-assn-v-hyland-hill-co-minn-1996.