Capitol Place I Associates L.P. v. George Hyman Construction Co.

673 A.2d 194, 1996 D.C. App. LEXIS 46, 1996 WL 125997
CourtDistrict of Columbia Court of Appeals
DecidedMarch 21, 1996
Docket95-CV-75 & 95-CV-282
StatusPublished
Cited by24 cases

This text of 673 A.2d 194 (Capitol Place I Associates L.P. v. George Hyman Construction Co.) is published on Counsel Stack Legal Research, covering District of Columbia Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Capitol Place I Associates L.P. v. George Hyman Construction Co., 673 A.2d 194, 1996 D.C. App. LEXIS 46, 1996 WL 125997 (D.C. 1996).

Opinion

MACK, Senior Judge:

Appellant 1 filed a demand for arbitration of claims related to appellee’s construction of a large office building. Appellee sought a preliminary injunction in the trial court on *196 the ground that the demand for arbitration was barred by the statute of limitations. Appellant asserted that the resolution of the statute of limitations question was for the arbitrator alone and, alternatively, that the statute of limitations had not run at the time it filed its demand for arbitration because the period of limitations was tolled pursuant to the “discovery exception.” See Ehrenhaft v. Malcolm Price, 483 A.2d 1192 (D.C.1984). The trial court rejected both of appellant’s arguments and granted the injunction. 2 This appeal followed. We affirm.

I.

Appellant, a partnership that included the American Federation of Teachers (AFT), as well as Gary S. Frank and Sheldon B. Ka-mins, principals in a commercial property development and management firm known as BFK, contracted with appellee, George Hy-man Construction Company, a large commercial builder, for the construction of a 12-story office building to be known as Capitol Place 1, at 555 New Jersey Avenue, N.W. Under the contract, dated December 13, 1982, the parties generally agreed to arbitrate claims arising from the contract, but also provided that, “in no event,” shall a demand for arbitration “be made after the date when institution of legal or equitable proceedings based on such claim, dispute, or other matter in question would be barred by the applicable statute of limitations.” The building was substantially completed by 1984, and one of appellant’s constituent partners (and its primary one today), the AFT, began occupancy. While returning to the building for repairs and the completion of other work over the following few years, appellee last worked on the building no later than February 28,1991.

Prior to entering the construction contract with appellee, appellant contracted with an architectural firm both to design the budding and to monitor its construction. The individual architect assigned to the project eventually became directly employed by BFK and continued to oversee the project. When that occurred, the architectural firm assigned another individual to monitor the project.

From the outset, the building was plagued with problems, most of them related to water infiltration. At and after the time of construction, the architectural firm’s representative and the architect working directly for BFK saw efflorescence on the building’s facade, which is indicative of water infiltration. In 1986, BFK’s architect began complaining to appellee that water was leaking into the budding. In 1989, the AFT repeatedly complained to BFK concerning leakage into the budding, noting symptoms including “squishy” carpets and mushroom growth in two or three offices. In 1990, the AFT continued to note the water infiltration problem in its correspondence to BFK. The building’s on-site engineer recalled seeing efflorescence in 1990.

Appellant, through its architect, learned of masonry distress problems in the building beginning in 1987. Appellee returned to the building and added more expansion joints to the building that year. Appellant complained the next year about the cracking of the facade and improper flashing and, after a meeting with appellee, took steps to remedy the problem including the hiring of an independent expert to examine some of the walls. In 1990, appellee again returned to the building in an attempt to address the leakage problem. Appellant hired an additional expert to inspect the facade in 1990, and this company performed a substantial number of repairs.

In connection with refinancing, an engineer inspected the budding in October 1992, and shortly thereafter issued a report outlining deficiencies in design and construction. In 1993, appellant began questioning BFK, which no longer had an interest in the budding, concerning its knowledge of the problems. Notably, BFK defended against the implication of these questions by noting, among other things, that everyone knew about these problems for more than a decade and that a conscious decision to avoid litigation, and its attendant costs, had been made *197 by the owners of the building. In February 1994, appellant sent a copy of the report to appellee, requesting assistance. On March 15, 1994, appellee denied responsibility, informing appellant that it would not cure the problems.

On April 29, 1994, appellants made a demand for arbitration. On May 31, 1994, ap-pellee sought injunctive relief to prevent arbitration on the ground that the statute of limitations had long passed, leaving the demand for arbitration untimely. On July 22, 1994, the trial court denied a motion to dismiss by appellant, which had argued that the statute of limitations question was for the arbitrator. On January 3,1995, after discovery limited to the statute of limitations question, the trial court granted appellee’s motion for summary judgment on that issue and enjoined appellant from proceeding with arbitration.

II.

Preliminarily, we consider whether the trial court had the power to decide the statute of limitations question at all, or whether it should have permitted the arbitrator to decide that issue.

As the United States Supreme Court has noted, “[T]he question of arbitrability— whether [an agreement] creates a duty for the parties to arbitrate [a] particular grievance — is undeniably an issue for judicial determination.” AT & T Technologies, Inc. v. Communications Workers of America, 475 U.S. 643, 649, 106 S.Ct. 1415, 1418, 89 L.Ed.2d 648 (1986). There is a strong presumption in favor of courts deciding whether an arbitrator has the “power to determine [ ] jurisdiction.” Id. at 651, 106 S.Ct. at 1419. Thus, “[ujnless the parties clearly and unmistakably provide otherwise, the question of whether the parties agreed to arbitrate is to be decided by the court, not the arbitrator.” Id. at 649, 106 S.Ct. at 1418; see Virginia Carolina Tools v. International Tool, 984 F.2d 113, 117 (4th Cir.) (presumption of arbi-trability does not apply to “questions of the arbitrability of arbitrability issues themselves”), cert. denied, 508 U.S. 960, 113 S.Ct. 2930, 124 L.Ed.2d 681 (1993).

In National Railroad Passenger Corp. v. Boston & Maine Corp., 271 U.S.App.D.C. 63, 850 F.2d 756 (1988), the D.C. Circuit considered a dispute over whether all of a contract’s terms — including an agreement to arbitrate disputes — had been extended by subsequent amendments. The court noted:

[T]he parties have it within their power to specify the date and hour at which their obligation to arbitrate is to end, or to specify a clear condition subsequent, such as sending of notice, giving any party the right to terminate that obligation. Where they have done so, there is nothing fairly arguable to refer to arbitration.

Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Matiella v. Murdock Street LLC
District of Columbia, 2023
Capitol Services Management v. Vesta Corporation
933 F.3d 784 (D.C. Circuit, 2019)
Wash. Tennis & Educ. Found., Inc. v. Clark Nexsen, Inc.
324 F. Supp. 3d 128 (D.C. Circuit, 2018)
Com. Land Title Ins. Co. v. Kci Techs., Inc.
297 F. Supp. 3d 106 (D.C. Circuit, 2018)
Hensel Phelps Construction Co. v. Cooper Carry, Inc.
210 F. Supp. 3d 192 (District of Columbia, 2016)
Rocha v. Brown & Gould, LLP
101 F. Supp. 3d 52 (District of Columbia, 2015)
Perry v. Scholar
696 F. Supp. 2d 91 (District of Columbia, 2010)
Menna v. Plymouth Rock Assurance Corp.
987 A.2d 458 (District of Columbia Court of Appeals, 2010)
Hunt v. DePuy Orthopaedics, Inc.
636 F. Supp. 2d 23 (District of Columbia, 2009)
Murray v. Wells Fargo Home Mortgage
953 A.2d 308 (District of Columbia Court of Appeals, 2008)
Johnson v. LONG BEACH MORTGAGE LOAN TRUST 2001-4
451 F. Supp. 2d 16 (District of Columbia, 2006)
The Plan Committee v. PRICEWATERHOUSECOOPERS, LLP
335 B.R. 234 (District of Columbia, 2005)
National Railroad Passenger Corp. v. Lexington Insurance
357 F. Supp. 2d 287 (District of Columbia, 2005)
Jacobsen v. Block
744 A.2d 1028 (District of Columbia Court of Appeals, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
673 A.2d 194, 1996 D.C. App. LEXIS 46, 1996 WL 125997, Counsel Stack Legal Research, https://law.counselstack.com/opinion/capitol-place-i-associates-lp-v-george-hyman-construction-co-dc-1996.