Menna v. Plymouth Rock Assurance Corp.

987 A.2d 458, 2010 D.C. App. LEXIS 9, 2010 WL 183423
CourtDistrict of Columbia Court of Appeals
DecidedJanuary 21, 2010
Docket07-CV-1308
StatusPublished
Cited by15 cases

This text of 987 A.2d 458 (Menna v. Plymouth Rock Assurance Corp.) is published on Counsel Stack Legal Research, covering District of Columbia Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Menna v. Plymouth Rock Assurance Corp., 987 A.2d 458, 2010 D.C. App. LEXIS 9, 2010 WL 183423 (D.C. 2010).

Opinion

GLICKMAN, Associate Judge:

Mark Menna appeals the trial court’s denial of his motion to compel Plymouth Rock Assurance Corporation (“Plymouth Rock”) to participate in arbitration. Although Menna and Plymouth Rock were signatories to an arbitration agreement, the court was persuaded by Plymouth Rock’s claims that it had withdrawn from the agreement, and that Menna was barred by the statute of limitations, laches, and his own waiver from enforcing his *460 contractual rights. Plymouth Rock’s purported withdrawal did not render its arbitration agreement with Menna a nullity, however. There is no doubt that the agreement was a valid contract. We conclude that the trial court therefore should have enforced it, leaving Plymouth Rock’s procedural objections to be determined in the arbitration.

I. Background

The dispute at the heart of this appeal is almost two decades old. In 1992, Mark Menna was injured when the taxi cab in which he was riding as a passenger was struck by another vehicle. The driver of that vehicle, Sarah Callahan, was insured by Plymouth Rock. On June 30, 1995, Plymouth Rock (as Callahan’s agent) and Menna entered into a contract to arbitrate his claim under the auspices of United States Arbitration and Mediation of the Northeast, Inc. (“USA & M”).

The contracting parties stipulated to liability; the only matters in dispute were the nature and extent of Menna’s injuries and the amount of his damages. 1 The parties agreed that the arbitrator would be invested with “the authority to settle all points and controversies” in their dispute and would conduct the arbitration in accordance with District of Columbia law and the Rules of USA & M. By their terms, those Rules were deemed to be incorporated in the arbitration contract and Plymouth Rock and Menna were “legally bound to comply with” them. The Rules commit certain procedural matters to the “sole discretion” of the Arbitration Coordinator, including the determination of whether a party has “failed to proceed” with arbitration as contractually required, 2 the resolution of “procedural disputes,” the imposition of “time limits on parties,” and the decision of whether to “require a party to take action or refrain from taking action” in connection with the arbitration. 3

Following the selection of an arbitrator, a hearing originally was scheduled to be held in the fall of 1997. The hearing was postponed, however, allegedly because Plymouth Rock retained new counsel who requested additional time to prepare. Due to a conflict, a new arbitrator was selected in the summer of 1998, but a new hearing date was not set. Menna alleges that he *461 periodically inquired and was told that USA & M would notify him when the arbitration hearing was scheduled. So far as it appears, this notification never came.

Instead, in September 1999, USA & M sent Menna a letter it had received from Robin Sacco, a Plymouth Rock claims representative. That letter, dated September 16,1999, announced Plymouth Rock’s decision to “withdraw” its agreement to arbitrate because of what it claimed was Men-na’s failure to proceed. 4 In light of that announcement, USA & M informed Menna that it had closed its file.

Upon receiving this news, Menna immediately contacted USA & M, which reinstated the arbitration on its docket. Men-na also called Ms. Sacco, who allegedly promised to “let [him] know if they [Plymouth Rock] were going to go forward or not.” Thus, Menna claims, he understood that Plymouth Rock had not yet made a final determination whether to withdraw from its agreement to arbitrate. Over the next few years, however, Menna heard nothing further from Plymouth Rock. He allegedly called USA & M every few months and was told that Plymouth Rock was still considering whether it would proceed with the arbitration. (The contract did not specify a time for performance.) Finally, according to Menna, on September 29, 2003, USA & M informed him that Plymouth Rock had made its decision. The company had decided it would not arbitrate.

Almost three years later, on September 26, 2006, Menna sued Plymouth Rock and Callahan in Superior Court. Menna alleged that Callahan was negligent in causing the automobile accident in 1992, and that the defendants breached the arbitration contract when Plymouth Rock finally refused to proceed with the arbitration in September 2003. The complaint sought monetary damages or, in the alternative, an order requiring the defendants to arbitrate. Plymouth Rock filed an answer denying Menna’s claims.

Several months later, in mid-2007, Men-na moved the court pursuant to the District of Columbia Uniform Arbitration Act 5 to order the parties to proceed with arbitration in accordance with their contract. Opposing that motion, Plymouth Rock argued that there was no contract for the court to enforce because the company withdrew from its agreement to arbitrate in September 1999. Because Menna waited more than three years after its ■withdrawal to file his lawsuit, Plymouth Rock contended, he was barred by the statute of limitations and by laches from asserting any rights under the contract. *462 Moreover, the company asserted, Menna waived his contractual rights by failing to proceed with the arbitration prior to September 1999, when he had the opportunity to do so.

In reply, Menna argued that Plymouth Rock’s claims raised factual disputes regarding the existence of a valid arbitration agreement that would have to be resolved by the court in a summary evidentiary proceeding, as contemplated by the Uniform Arbitration Act, after the parties completed appropriate discovery. 6 Relying on his own deposition (which Plymouth Rock had taken), Menna proffered that he had not abandoned his pursuit of arbitration before USA & M and that Plymouth Rock had retracted its September 1999 withdrawal when it subsequently advised him and USA & M that it was still considering whether to go forward with the arbitration.

On October 26, 2007, the trial court denied Menna’s motion to compel arbitration. It did so without first conducting the evi-dentiary proceeding that Menna had requested. The court’s order states only that the motion was “denied for the reasons set [forth] in Defendant’s Opposition^]” Menna noted a timely appeal. 7

II. Analysis

Although the arbitration contract at issue in this case was made in 1995, we conclude that it is no longer governed by the provisions of the D.C. Uniform Arbitration Act relied upon in the trial court proceedings. That Act, set forth in Chapter 43 of Title 16 of the District of Columbia Code, was repealed effective July 1, 2009, by D.C. Law 17-111, the “Arbitration Amendment Act of 2007.” 8

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jones v. Nvr Incorporation
District of Columbia, 2022
Johansson v. Cent. Props., LLC
320 F. Supp. 3d 218 (D.C. Circuit, 2018)
Johansson v. Central Properties, LLC
District of Columbia, 2018
ABU NASER HOSSAIN v. JMU PROPERTIES, LLC
147 A.3d 816 (District of Columbia Court of Appeals, 2016)
ROSANNE L. WOODROOF v. JOSEPH F. CUNNINGHAM
147 A.3d 777 (District of Columbia Court of Appeals, 2016)
BiotechPharma, LLC v. Ludwig & Robinson, PLLC
98 A.3d 986 (District of Columbia Court of Appeals, 2014)
Bank of America, N.A. v. District of Columbia
80 A.3d 650 (District of Columbia Court of Appeals, 2013)
Parker v. K & L Gates, LLP
76 A.3d 859 (District of Columbia Court of Appeals, 2013)
Giron v. Dodds
35 A.3d 433 (District of Columbia Court of Appeals, 2012)
Rdp Technologies, Inc. v. Cambi As
District of Columbia, 2011
Foulger-Pratt Residential Contracting, LLC v. Madrigal Condominiums, LLC
779 F. Supp. 2d 100 (District of Columbia, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
987 A.2d 458, 2010 D.C. App. LEXIS 9, 2010 WL 183423, Counsel Stack Legal Research, https://law.counselstack.com/opinion/menna-v-plymouth-rock-assurance-corp-dc-2010.