Giron v. Dodds

35 A.3d 433, 2012 D.C. App. LEXIS 2, 2012 WL 18574
CourtDistrict of Columbia Court of Appeals
DecidedJanuary 5, 2012
DocketNo. 11-CV-37
StatusPublished
Cited by6 cases

This text of 35 A.3d 433 (Giron v. Dodds) is published on Counsel Stack Legal Research, covering District of Columbia Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Giron v. Dodds, 35 A.3d 433, 2012 D.C. App. LEXIS 2, 2012 WL 18574 (D.C. 2012).

Opinion

NEBEKER, Senior Judge:

This dispute arises out of the efforts of appellees John and Teresa Dodds to collect an arbitration award from C & C General Builders, Inc., a construction company ■with which the Dodds contracted for demolition and renovation work. After obtaining an arbitration judgment in their favor and then learning that C & C would be unable to pay the award, the Dodds brought a claim seeking to pierce C & C’s corporate veil to reach C & C’s alleged shareholders, Carlos and Alex Giron (see note 4, infra). The Girons moved to compel arbitration of this claim, and the trial court denied their motion. This appeal followed. Finding no error, we affirm.

I. Facts and Procedural History

In March 2007, John and Teresa Dodds entered into a contract with C & C General Builders, Inc. (C & C) for the demolition and renovation of a residential building the Dodds owned in Northwest Washington, D.C. C & C is a construction company run by Carlos Giron and his son, Alex Giron, C & C’s president and vice president, respectively. Article 9 of the contract between the Dodds and C & C contains an arbitration clause, providing: “Any controversy or claim arising out of or relating to this contract, or the breach thereof, shall be settled by arbitration administered by the American Arbitration Association under its Construction Industry Arbitration Rules, and judgment on the award rendered by the arbitrator(s) may be entered in any court having jurisdiction thereof.”

Under the contract, the Dodds were required to make weekly progress payments for 23 weeks, the agreed-upon period for completing the construction. The Dodds made payments through May 3, 2008, amounting to 70 percent of the contract price. They then received a consultant report concluding that the project was only 40 percent complete and that C & C would not be able to complete it by August 2008 as scheduled. When confronted with these facts, the Girons demanded that the progress payments continue. The Dodds refused, and the Girons abandoned the job site.

In September 2008, the Dodds filed a four-count complaint against Carlos and Alex Giron as individuals, alleging breach of contract, negligent supervision of contract, breach of fiduciary duty, and slander of title. In response to the Girons’ motion to compel arbitration, the Superior Court ordered the parties to proceed with arbitration and stayed the case pending the outcome of arbitration. The Dodds filed a statement of claim with the American Arbitration Association, making essentially the same allegations as those made in then-original complaint. After the Girons filed a request for dismissal but before the arbitrator ruled on that request, the Dodds amended their statement of claim to add C & C as a defendant on the theory that C & C was an undisclosed principal. In an interim order, the arbitrator dismissed the claims against Carlos and Alex Giron, finding that the Dodds knew they had con[436]*436tracted with a corporate entity and not the Girons as individuals, and thus the Girons were not parties to the arbitration agreement. The arbitrator then denied the request for summary dismissal of the Dodds’ claims against C & C. The arbitrator issued a final award on July 27, 2009, finding liability on the part of C & C and awarding the Dodds $120,872.42 “as full and complete settlement of the claims of both parties.” The arbitrator based the amount of the award on evidence “concerning the amount paid by the [Dodds], the extra work performed for the [Dodds], [and] the amount paid by the [Dodds] to complete the work,” as well as expert testimony from both parties about the percentage of work completed at the time the Girons abandoned the project. In response to a motion filed by the Dodds to clarify the award, the arbitrator stated that “no claim was made in this arbitration concerning the piercing of a corporate shield.”

On August 21, 2009, after receiving a letter from counsel for the Girons stating that C & C was “asset-less” and would not pay the award, the Dodds filed a motion in the trial court to confirm the arbitration award. Soon after, on September 20, 2009, the Dodds filed a motion for leave to file an amended complaint. Both motions were granted. In their amended complaint, the Dodds sought to pierce C & C’s corporate veil and hold Carlos and Alex Giron individually liable for the award. The Dodds alleged that the Girons “treated the assets and the funds of the corporate entity as their own[,] ... failed to observe corporate formalities[,] ... intermingled corporate and personal funds and [were] now attempting to use the corporate shell to shield themselves from liability....” Specifically, the Dodds claimed that the Girons “wrongfully and fraudulently converted” for their own use the Dodds’ progress payments intended to be used toward completion of the project. The Girons filed a motion to reconsider the order granting leave to file an amended complaint or, in the alternative, to dismiss for lack of subject matter jurisdiction and failure to state a claim. The trial court denied this motion and the Girons appealed. This court dismissed the appeal as having been taken from a nonfinal order. Giron v. Dodds, 10-CV-1129 (D.C. Nov. 2, 2010). The Girons then filed a motion to compel arbitration for a second time, and the trial court denied that motion in a January 6, 2011 order. Relying heavily on Schattner v. Girard, Inc., 668 F.2d 1366 (D.C.Cir.1981), holding that a party may, under appropriate circumstances, pierce the corporate veil to hold individuals liable for an arbitration award, the trial court concluded that the veil-piercing claim “arises out of the arbitration judgment” not the arbitration agreement in the contract, and it “did not become ripe until after the arbitration was concluded and judgment had been rendered.”

The Girons appeal the trial court’s denial of their motion to compel arbitration, contending that the court should have ordered the parties to proceed with arbitration because, they argue, the allegations in the amended complaint are subject to the arbitration agreement in the contract and have in fact already been decided in arbitration. The Girons further challenge the trial court’s reliance on Schattner, arguing that its reasoning is inapplicable to the facts here.

II. Jurisdiction and Standard of Review

At the outset, we note that unlike the Girons’ earlier appeal from the trial court’s denial of their motion to dismiss the Dodds’ amended complaint, this appeal is properly before us. We have held that “the denial of a motion to compel arbitration under [the District of Columbia Uni[437]*437form Arbitration Act] ‘shall be deemed final’ for purposes of an appeal.” Hercules & Co. v. Beltway Carpet Service, Inc. 592 A.2d 1069, 1071 (D.C.1991) (quoting D.C.Code § 16-4317(a)(l) (1989)).1 The trial court’s denial of the Girons’ motion to compel arbitration was “immediately ap-pealable.” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johansson v. Cent. Props., LLC
320 F. Supp. 3d 218 (D.C. Circuit, 2018)
Johansson v. Central Properties, LLC
District of Columbia, 2018
BiotechPharma, LLC v. Ludwig & Robinson, PLLC
98 A.3d 986 (District of Columbia Court of Appeals, 2014)
Washington Teachers' Union Local 6 v. District of Columbia Public Schools
77 A.3d 441 (District of Columbia Court of Appeals, 2013)
Parker v. K & L Gates, LLP
76 A.3d 859 (District of Columbia Court of Appeals, 2013)
Haire v. Smith, Currie & Hancock LLP
925 F. Supp. 2d 126 (District of Columbia, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
35 A.3d 433, 2012 D.C. App. LEXIS 2, 2012 WL 18574, Counsel Stack Legal Research, https://law.counselstack.com/opinion/giron-v-dodds-dc-2012.