Foulger-Pratt Residential Contracting, LLC v. Madrigal Condominiums, LLC

CourtDistrict Court, District of Columbia
DecidedApril 27, 2011
DocketCivil Action No. 2009-2333
StatusPublished

This text of Foulger-Pratt Residential Contracting, LLC v. Madrigal Condominiums, LLC (Foulger-Pratt Residential Contracting, LLC v. Madrigal Condominiums, LLC) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Foulger-Pratt Residential Contracting, LLC v. Madrigal Condominiums, LLC, (D.D.C. 2011).

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA

FOULGER-PRATT RESIDENTIAL ) CONTRACTING, LLC ) ) and ) ) TRAVELERS CASUALTY AND ) SURETY COMPANY OF AMERICA ) ) Case No. 1:09-cv-02333 (GK) Applicants, ) ) v. ) ) MADRIGAL CONDOMINIUMS, LLC ) ) Respondent. )

MEMORANDUM OPINION

This matter is presently before the Court on Foulger-Pratt

Residential Contracting, LLC (“Foulger-Pratt”) and Travelers

Casualty and Surety Company of America’s (“Travelers”) Application

to Confirm Arbitration Award [Dkt. No. 1], under 28 U.S.C. § 1332,

pursuant to 9 U.S.C. § 9 against Respondent Madrigal Condominiums,

LLC (“Madrigal”), and Respondent Madrigal’s Cross-Motion to Vacate

Portions of Interim Arbitration Award [Dkt. No. 27]. Upon

consideration of the Application, Motion, Oppositions, Replies,

Surreply, and entire record herein, Foulger-Pratt’s Application to

Confirm Arbitration Award is granted and Madrigal’s Motion to

Vacate is denied in its entirety. I. Procedural Background1

The dispute in this case arises out of a construction contract

(“Contract”), consisting of the Modified General Conditions of the

Contract for Construction, (“Modified Contract Conditions”)[Dkt.

No. 27-4] , as well as the Modified Standard Form Agreement Between

Owner and Contractor, (“Modified Form Agreement”)[Dkt. No. 27-3],

and the Reconciled GMP Set of Specifications (“GMP

Specifications”).2 In 2005, Madrigal entered into these agreements

with Glen Construction Company, Inc. (“Glen”), the-then general

contractor, for the construction of Madrigal Lofts condominiums,

located at 811 4th Street, N.W. in Washington, D.C. Applicant

Travelers acted as Glen’s bonding company, providing the

performance and payment bonds for the project.

The parties’ Contract included an arbitration provision

providing that claims and disputes with a value exceeding $100,000

be submitted to a three-member Panel of arbitrators, and that any

award be considered as final, binding, and conclusive. Modified

Contract Conditions § 4.4.1. The Contract also contained a

provision directing the parties to first attempt mediation of their

1 The undisputed facts included in this section are based upon the parties’ submissions, as well as the entire record in this case. 2 According to Foulger-Pratt and Travelers, and undisputed by Madrigal, Madrigal drafted the Contract. Foulger-Pratt Reply to App. 20 n.4.

-2- dispute, before proceeding to arbitration. Modified Contract

Conditions § 4.5.2.

In June 2007, Glen stopped paying its subcontractors who were

working on the Project. As a result of Glen’s non-performance under

the Contract, Travelers engaged Foulger-Pratt, one of its long-time

bond customers, to assume control over the project. In mid-2007,

Glen assigned the Contract and its accompanying documents to

Foulger-Pratt, which assumed the role of general contractor and

agreed to achieve substantial completion of the project by December

31, 2007. Although Foulger-Pratt allegedly failed to meet this

completion date, it did achieve substantial completion by early

June 2008, as reflected in the Certificate of Substantial

Completion issued by the project’s Architect and Development

Manager, effective as of June 1,2008 [Dkt. No. 30-4].

Beginning in early 2008, a variety of disputes arose between

the parties regarding payments to Foulger-Pratt and various

subcontractor liens on the project. The disputes came to a head in

December 2008, when Foulger-Pratt filed a mechanic’s lien for

$2,636,467 against the project. In response, Madrigal filed an

emergency motion for a temporary restraining order (“TRO”) in D.C.

Superior Court, which resulted in a court order vacating the lien.

Shortly thereafter, in January 2009, the parties engaged in

mediation to resolve several claims and disputes related to their

underlying written agreements and the project. As a result of these

-3- efforts, on February 2, 2009, the parties executed a partial

settlement agreement, (“APS”) [Dkt. No. 27-7], resolving a number

of these issues. As a part of this settlement agreement, the

parties agreed to designate a “Project Neutral,” who would be a

licensed architect and would certify Foulger-Pratt’s completion of

a punch-list of outstanding construction-related items (“Items 1-8

Punch-List”). APS ¶ 5.3. The Punch-List had been previously

designated in an expert report, The Exterior Building Envelope

Review Report (“Gale Report”) [Dkt. No. 27-18]. The parties further

agreed to submit to arbitration their remaining unresolved claims,

with the exception of those items reserved in the APS for the

Project Neutral, as well as any future disputes that might arise

between them. Id. ¶ 11.

During the arbitration proceedings, Madrigal brought ten

claims against Foulger-Pratt, relating to its work as general

contractor. Interim Award ¶¶ 1-10 [Dkt. No. 27-11]. Foulger-Pratt,

in turn, brought three cross-claims: (1) for damages for extended

direct supervision costs due to Madrigal’s alleged failure to

permit final completion of the project; (2) for entitlement to

payment for final completion of the contract or, alternatively, for

recusal from completing the project due to Madrigal’s actions or

inactions; and (3) for payment to Foulger-Pratt of the entire

contract balance, plus pre-award interest. Id. ¶¶ 12-13.

-4- From May to July 2009, the parties participated in hearings on

these issues before the Arbitration Panel, consisting of three

lawyers who were experienced in handling construction contract

disputes (“Panel”). On May 26, 2009, the Panel issued an Order,

(“May 26, 2009 Order”) [Dkt. No. 27-8], resolving several matters

raised by the parties. The Order noted that Madrigal had

potentially discovered and was investigating additional defects in

the project’s exterior skin and that it might wish to bring claims

pertaining to such “potential” defects before the Panel; the Order

stated that such claims were not ripe and the Panel postponed

ruling on those claims if, and when, they became ripe, to a second

hearing. May 26, 2009 Order ¶ 1.

On September 11, 2009, the Panel received post-hearing briefs

and heard post-hearing argument on September 21, 2009. The Panel

issued an “Interim Award” on November 30, 2009. In this award, the

Panel concluded that Foulger-Pratt was obligated to complete Items

4-8 of the Punch-List and to cure certain deficiencies in special

warranties. Interim Award ¶ 14(c)-(d). The Panel also held that

Foulger-Pratt was entitled to final payment as it had either

satisfied, or was excused from performance of, the remaining

obligations alleged by Madrigal. Id. ¶ 14(f). In connection with

this ruling, the Panel ordered Madrigal to pay $1,694,655 to

Foulger-Pratt within 15 business days and to deposit $1,113,000

into an interest-bearing escrow account, for payment to Foulger-

-5- Pratt upon completion of its remaining obligations. Id. ¶ 16. The

Panel also granted some, but not all, of Madrigal’s requests for

attorneys’ fees, although it reserved final determination of the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bradley v. School Bd. of Richmond
416 U.S. 696 (Supreme Court, 1974)
Landgraf v. USI Film Products
511 U.S. 244 (Supreme Court, 1994)
Mastrobuono v. Shearson Lehman Hutton, Inc.
514 U.S. 52 (Supreme Court, 1995)
Plaut v. Spendthrift Farm, Inc.
514 U.S. 211 (Supreme Court, 1995)
First Options of Chicago, Inc. v. Kaplan
514 U.S. 938 (Supreme Court, 1995)
Howsam v. Dean Witter Reynolds, Inc.
537 U.S. 79 (Supreme Court, 2002)
Hall Street Associates, L. L. C. v. Mattel, Inc.
552 U.S. 576 (Supreme Court, 2008)
Preston v. Ferrer
552 U.S. 346 (Supreme Court, 2008)
Kurke, David S. v. Oscar Gruss & Son
454 F.3d 350 (D.C. Circuit, 2006)
Lessin, Michael v. Merrill Lynch Pierce
481 F.3d 813 (D.C. Circuit, 2007)
Khan v. Parsons Global Services, Ltd.
521 F.3d 421 (D.C. Circuit, 2008)
Williams v. Martinez
586 F.3d 995 (D.C. Circuit, 2009)
Stern v. Stern Co. Of Washington, D.C.
200 F.2d 364 (D.C. Circuit, 1952)

Cite This Page — Counsel Stack

Bluebook (online)
Foulger-Pratt Residential Contracting, LLC v. Madrigal Condominiums, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/foulger-pratt-residential-contracting-llc-v-madrig-dcd-2011.