National Railroad Passenger Corporation v. Boston and Maine Corporation

850 F.2d 756, 271 U.S. App. D.C. 63, 1988 U.S. App. LEXIS 8675
CourtCourt of Appeals for the D.C. Circuit
DecidedJune 24, 1988
Docket87-7190
StatusPublished
Cited by94 cases

This text of 850 F.2d 756 (National Railroad Passenger Corporation v. Boston and Maine Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Railroad Passenger Corporation v. Boston and Maine Corporation, 850 F.2d 756, 271 U.S. App. D.C. 63, 1988 U.S. App. LEXIS 8675 (D.C. Cir. 1988).

Opinion

D.H. GINSBURG, Circuit Judge:

In 1977, the two parties to this case entered into an agreement containing a *758 broad arbitration clause. When a dispute between them arose in 1987, one sought arbitration and the other refused, claiming that the agreement, along with the arbitration clause, had expired. The district court, rather than deciding the question itself, held that it was for the arbitrators to determine whether the agreement had expired, and ordered the recalcitrant party to submit to arbitration on that question. We affirm.

I. Background

In 1977, the Boston and Maine Corporation (“B & M”) entered into a written agreement with the National Railroad Passenger Corporation (“Amtrak”), authorizing Amtrak to operate its “Montrealer” train service over a section of track owned by B & M. Under the agreement, B & M was required to provide various services and facilities to Amtrak, and to maintain its track in such condition as to allow Amtrak’s trains to operate over designated segments of it at not less than specified speeds. In return, Amtrak was to make periodic payments to B & M in accordance with a schedule set forth in the agreement.

Our concern in this case is with the relationship between two provisions of the agreement. One is the arbitration clause, which provides that “[a]ny claim or controversy between Amtrak and B & M concerning the interpretation, application or implementation of this Agreement shall be submitted to binding arbitration in accordance with the provisions of the Arbitration Agreement attached hereto....” 1 The other is the expiration clause, which states that “[t]his contract shall remain in full force and effect for two years, through January 31, 1979, unless terminated or modified by mutual consent of both parties, and thereafter until 90 days after written notice of cancellation by either party is received by the other.”

In 1987, after several years of feuding with B & M over the condition of the track used for the Montrealer service, Amtrak initiated an arbitration proceeding against B & M, claiming that it had breached the agreement by failing properly to maintain several portions of its track. B & M, however, refused to submit to arbitration, arguing that the agreement had expired in 1981, and that it was therefore under no obligation to arbitrate. Amtrak, on the other hand, maintained that the agreement remained in effect, having been extended by numerous “Amendment Agreements” signed by both parties.

Thus, Amtrak petitioned the district court for an order compelling B & M to arbitrate the contract dispute in the pending arbitration proceeding. In the district court, B & M renewed its contention that the 1977 agreement had expired in 1981; since its expiration, B & M maintained, the parties had simply operated under an “informal arrangement.” The parties filed cross-motions for summary judgment, Amtrak seeking a declaration that the arbitration clause continued to bind the parties, and B & M seeking a declaration that it did not. The district court, however, refused to determine the vitality of the arbitration clause after September 30,1981; instead, it ordered B & M to submit to arbitration the question whether the 1977 agreement had expired. The court reasoned that this question had to be referred to arbitration because the arbitration clause itself “requires that each and every claim or controversy concerning the interpretation, application or implementation of the Agreement, including a dispute over the term of the contract, shall be submitted to arbitration.” National R.R. Corp. v. Boston & Maine Corp., No. 87-1507, slip op. at 6 (D.D.C. Aug. 31, 1987) [available on WESTLAW, 1987 WL 16842] (order granting summary judgment).

B & M moved the district court for a stay pending appeal to this court. In the memorandum accompanying its denial of that motion, the district court noted that B & M’s motion had mischaracterized the court’s decision as holding that “the ques *759 tion of whether the parties agreed to arbitrate” is for the arbitrator. Its holding, the district court emphasized, was that by entering into “an expansive, nearly all-encompassing arbitration clause,” the parties had agreed to arbitrate questions relating to the duration both of the contract itself and of its accompanying arbitration clause. National R.R. Corp. v. Boston & Maine Corp., No. 87-1507, slip op. at 4 (D.D.C. Dec. 21, 1987) [available on WESTLAW, 1987 WL 33429] (order denying stay pending appeal).

II. Analysis

The principles that underlie our analysis of this case are long-established, and were recently reaffirmed in AT & T Technologies, Inc. v. Communications Workers of America, 475 U.S. 643, 106 S.Ct. 1415, 89 L.Ed.2d 648 (1986). The “first principle” of arbitrability, the Supreme Court emphasized, is that “ ‘arbitration is a matter of contract and a party cannot be required to submit to arbitration any dispute which he has not agreed so to submit.’ ” Id. at 648, 106 S.Ct. at 1418 (quoting United Steelworkers of America v. Warrior & Gulf Navigation Co., 363 U.S. 574, 582, 80 S.Ct. 1347, 1353, 4 L.Ed.2d 1409 (1960)). This principle recognizes that “arbitrators derive their authority to resolve disputes only because the parties have agreed in advance to submit such grievances to arbitration.” Id. It is a necessary corollary of the principle that “arbitration is a matter of contract” that when the parties have provided that a particular type of dispute should be settled in arbitration, rather than in litigation, a court may not override that agreement by itself deciding such a dispute.

The second principle restated in AT & T Technologies is that “the question of arbi-trability — whether [an agreement] creates a duty for the parties to arbitrate [a] particular grievance — is undeniably an issue for judicial determination.” Id. 475 U.S. at 649, 106 S.Ct. at 1418. In other words, the Court said, “[u]nless the parties clearly and unmistakably provide otherwise, the question of whether the parties agreed to arbitrate is to be decided by the court, not the arbitrator.” Id. (emphasis added).

A.

At the heart of this case is the proper interpretation of this second principle. The parties agree, as they must, that because they have not “clearly and unmistakably” provided otherwise, “the question of whether the parties agreed to arbitrate” must be decided by the court, not by the arbitrators. They disagree, however, about the nature of the “particular grievance” over which the court must find that they agreed to arbitrate. B & M would have us view this case as a dispute over track maintenance. In order to decide whether the parties agreed to arbitrate that dispute, it argues, the court must decide (a) whether the contract, and the arbitration clause it contains, has expired.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Scps, LLC v. Kind Law
District of Columbia, 2025
Xavier v. Grapetree Shores, INC
2024 V.I. 14 (Supreme Court of The Virgin Islands, 2024)
Cruz v. Jimenez Construction LLC
District of Columbia, 2023
Dist. No. 1, Pac. Coast Dist. v. Liberty Mar. Corp.
330 F. Supp. 3d 363 (D.C. Circuit, 2018)
Lapera v. Federal National Mortgage Ass'n
210 F. Supp. 3d 164 (District of Columbia, 2016)
Kotchen & Low LLP v. Precision Discovery, Inc.
210 F. Supp. 3d 39 (District of Columbia, 2016)
Signature Technology Solutions v. Incapsulate, LLC
58 F. Supp. 3d 72 (District of Columbia, 2014)
Skrynnikov v. Federal National Mortgage Assoc.
943 F. Supp. 2d 172 (District of Columbia, 2013)
Unite Here Local 25 v. Madison Ownership, LLC
850 F. Supp. 2d 219 (District of Columbia, 2012)
Kindig v. Whole Foods Market Group, Inc.
811 F. Supp. 2d 410 (District of Columbia, 2011)
Rdp Technologies, Inc. v. Cambi As
District of Columbia, 2011
Unite Here Local 217 v. SAGE HOSPITALITY RESOURCES
642 F.3d 255 (First Circuit, 2011)
Amirmotazedi v. Viacom, Inc.
768 F. Supp. 2d 256 (District of Columbia, 2011)
Sheet Metal Workers' International Ass'n v. United Transportation Union
767 F. Supp. 2d 161 (District of Columbia, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
850 F.2d 756, 271 U.S. App. D.C. 63, 1988 U.S. App. LEXIS 8675, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-railroad-passenger-corporation-v-boston-and-maine-corporation-cadc-1988.